Reference no: EM132509620
Sabby Industries has three activity cost pools and two products. It expects to produce 2,700 units of Product SZ09 and 1,500 of Product NZ16. Having identified its activity cost pools and the cost drivers for each pool, Sabby accumulated the following data relative to those activity cost pools and cost drivers.
Activity Cost Pool Cost Driver Estimated Estimated Use SZ09 NZ16
Overhead of Cost Drivers
Machine set-ups Set-ups $78,540 170 130 40
Assembling Machine hours 328,700 17,300 10,400 6,900
Inspection Inspections 7,680 120 50 70
Question 1: Calculate the overhead rates.
Question 2: Assign the overhead cost to the two products.