Calculate a suitable power rating of the wind generator

Assignment Help Other Engineering
Reference no: EM131911825

Smart Grid Fundamentals Coursework Assignment

Part 1 - Microgrid design

This part of the coursework consists of the design of a large microgrid that can supply a DC load. Your goal is to design a microgrid that can operate exclusively on renewable energy.

To do so you will need the following information:

  • Assume that all days in the year are the same, and within each day there are four time periods, with the properties shown in Table 1.1.
  • Solar PV can be built for a capital cost of £2000/kW (all costs included)
  • Wind can be built for a capital cost of £1500/kW (all costs included)
  • Battery storage can be built for £400/kWh + £100/kW. For example, the capital cost to build a 10 kW storage plant that can store 20 kWh, will be: 20kWh x £500/kWh + 10kW x £100/kW = £11, 000

Assume that battery storage system will have a round trip efficiency of 85%.

The allowed depth of discharge of the battery is 80%. This means that the state of charge of the battery should not be allowed to go below 20%.

Assume that the operating costs for the resulting system are negligible, that the system will last for 25 years, and that you can obtain a 25 year loan at 5% interest for this project.

Table 1.1: Load, wind and solar data

Time

Load (kW)

Wind (kW/kW)

Solar (kW/kW)

12am-6am

10

0.90

0.05

6am-12pm

20

0.30

0.40

12pm-6pm

25

0.20

0.40

6pm-12am

15

0.60

0.05

Note that in Table 1.1, kW/kW refers to generated output (in kW) per unit of installed capacity (in kW).

Given these assumptions, you are required to:

a) Give an expression for the total initial cost of the microgrid.

b) Calculate a suitable value of the battery capacity and power rating considering its efficiency and allowed depth of discharge. Use manufacturer's data for actual lead acid batteries to select a battery bank that can be purchased in the market and that is reasonably close to your calculations.

c) Provide a charge/discharge schedule for the battery. Note that in order for the schedule to be a feasible solution, the amount of energy in the battery will need to be the same at the beginning and the end of each day (since this pattern repeats day after day).

d) Calculate a suitable power rating of the wind generator. Use manufacturer's data for actual DC wind generators to select a power rating that can be purchased in the market and that is reasonably close to your calculations.

e) Calculate a suitable power rating of the solar PV system. Use manufacturer's data for actual PV panels to select a power rating that can be purchased in the market and that is reasonably close to your calculations. Specify how many panels would be required.

f) What would be the total initial cost of the microgrid? Can this cost be reduced to a minimum? If so, explain how and provide calculations to support your answer.

g) Calculate the annual loan repayment amount, given the total initial cost, the loan period of 20 years and the annual interest rate of 5% for the configuration that you found to give the minimum initial cost.

h) What would be the minimum price in £/kWh at which the generated energy can be sold to the customer to recover the annual loan repayment amount given the total annual load in kWh?

i) Discuss your solution. What factors might have changed your answer?

In the report, please ensure that you:

1. Clearly explain your method (including computer code, if appropriate). Explain your equations.

2. Clearly describe your solution, paying particular attention to ensure that your solution is feasible. Use tables and, if appropriate, graphics to present your results. Show what each resource is doing during each of the four time periods.

Part 2 - Economic dispatch and optimal power flow analysis

2.1 - Power system data

Consider that in a simple power system there are four power plants. The generating plants capacity, type and marginal costs are:

1. 1100 MW nuclear plant with marginal cost of £10/MWh, connected to bus 1.

2. 600 MW coal plant with marginal cost of £20/MWh, connected to bus 2.

3. 400 MW natural gas plant with marginal cost of £30/MWh, connected to bus 3.

4. 100 MW of diesel units marginal cost of £150/MWh, connected to bus 5.

Every day there are four 6-hour periods of demand:

  • 12am-6am: 800 MW
  • 6am-12pm: 1200 MW
  • 12pm-6pm: 1920 MW
  • 6pm-12am: 1600 MW

The system consists of a network with 5 buses. The load above is distributed evenly among the five buses. The transmission lines (branches) have the data shown in Table 2.1.

Table 2.1: Transmission line data

From Bus

To Bus

R

X

Power limit (MW)

1

2

0

0.1

400

1

3

0

0.1

400

2

3

0

0.1

400

2

5

0

0.1

300

3

4

0

0.1

300

4

5

0

0.1

300

Given this information, do the following.

2.2 - Economic dispatch / power flow problem

a) Solve the simple economic dispatch problem for each time period. Report the system marginal price.

b) Solve the DC power flow problem for this system at each time period.

c) For each time period report (in a table) the flows on the transmission lines for your solution.

2.3 - Optimal power flow

a) Solve the optimal power flow problem for this system at each time period.

b) For each time period report (in a table) the flows on the transmission lines for your solution.

c) For each time period report (in a table) the locational marginal prices (LMPs).

2.4 - Discussion

a) What is the impact on this power system of having transmission line constraints?

b) How might smart grid technology impact this power system?

c) How should this system be upgraded to improve its operation?

Reference no: EM131911825

Questions Cloud

Your broker to trade december contract : how much must you deposit with your broker to trade the December contract?
How many cases should be ordered at a time : What is the effect on EOQ and total cost of the following types of changes for the data in problem 1? a. A 40 percent increase in demand.
What must expected return on market : What must the expected return on the market be?
Contribution income and traditional income statement : What is the difference between a contribution income statement and a traditional income statement? Under what circumstances would a firm use each?
Calculate a suitable power rating of the wind generator : ENG733S2 Smart Grid Fundamentals Coursework Assignment. Calculate a suitable power rating of the wind generator. Provide a charge/discharge schedule for battary
Cash flow from the mark-to-market proceeds on contract : Find the cash flow from the mark-to-market proceeds on the contract. Assume that the parity condition always holds exactly
How many lots will be produced each year : The famous Widget Company sells widgets at the rate of 80,000 units per year. Each widget sells for $100, and it costs 30 percent to carry widgets in inventory.
Net present worth from investing in stock : What is the variance and standard deviation of the net present worth from investing in the stock?
Appropriate price for futures using parity relationship : Calculate the appropriate price for December futures using the parity relationship?

Reviews

len1911825

3/23/2018 12:50:30 AM

Deadline For Submission: Thursday 29. Submission Instructions Submit your report via Moodle unit website. Instructions for completing the assessment: Details are provided in the document. Further information and clarifications can be given during the lectures, if needed.

len1911825

3/23/2018 12:50:23 AM

General guidance and Information - You should produce a report addressing Parts 1 and 2, reflecting as appropriate the structure of this coursework brief. The maximum word count for your report is 2000 words, excluding the cover page. Your report should briefly introduce each sub-problem, describe the method(s) used, and present the results obtained, including where appropriate details of the calculations made and computer code used (if any), ensuring that the specific questions asked in parts 1 and 2 are answered.

len1911825

3/23/2018 12:50:14 AM

If you are including computer code, please ensure that the computer code that you have written is inserted within a numbered textbox, so that it can be referred to from within the text as if it was a figure (for example, you may write “see the computer code in Figure 2”) You are free to use specialist software tools that may be available to you to solve the problems involved in this coursework. Details of suitable tools will be given in the lectures. You can include screenshots of the software package used and computer generated plots, if appropriate. You are only allowed to work on your own, no team work is permissible. The report will be marked out of 100 marks, with part 1 having a maximum of 50 marks, and part 2 having a maximum of 50 marks.

len1911825

3/23/2018 12:50:06 AM

For the marking criteria, 80% and above (Distinction) an outstanding depth and breadth of work carried out, showing exceptional and thorough knowledge of the relevant field, exceptional insight, critical analysis and originality, such as might make the work of comparable quality with published work in its field, an excellent and well-defined focus, clear structure, clearly presented and well written, with no significant errors of syntax or expression, accurate numerical results, excellent use of tables and graphics to present information.

Write a Review

Other Engineering Questions & Answers

  Draw timing diagram and determine the counters modulus

Draw its timing diagram and determine the counter's modulus

  Calculate the net cubic yards of excavated materials

Problem 1: Given the tabulated cut/fill data below, calculate the net cubic yards of excavated materials. Neglect soil type, water content, shrinkage, & swellage.

  Create a micro-hydro project to augment

A small village in a rural area wants to create a micro-hydro project to augment their photovoltaic system.

  An example of a product-of-sum expression

QUESTION 1. Which answer is an example of a product-of-sum (POS) expression?

  What dimensions will require the least amount of fencing

If a 20-foot side of the kennel is used as part of one side of a rectangular yard with 900 square feet, what dimensions will require the least amount of fencing

  Compute the critical edge load

Compute the critical edge load NxCR for a plate simply supported around the boundary, with length a = 2 m (along x), width b = 1 m, t = 1 cm.

  Discrete-time signals and systems

A discrete-time system can be described in one of two ways.  One is by the unit-pulse response of the system, and the other is by the difference equation.  In the first case, if we are given an input and want to find the output, we have to convolv..

  Design a control system to achieve the objectives

The process in Figure involves the chemical reaction with the over all stoichiometry of 3A + B ? C taking place in a packed-bed reactor.

  Gauge pressure at the bottom of the cylinder

What volume of water must be added to double the gauge pressure at the bottom of the cylinder?

  Compare frequency-division and time-division multiplexing

Compare frequency-division and time-division multiplexing. What physical characteristics of the communication channel does each technique require?

  Discuss the rise of signature architecture

Discuss the rise of signature architecture. The rise of Dubai as the "exemplar" 21st century city. Cite any architect to add to/amplify this discussion.

  Process of transforming data using an algorithm

Do project title is Data Encryption and hide in Images the title is in fill (project proposal) and all steps of the project in fill (project planning).

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd