Calculate a schedule using least-total-cost lot sizing

Assignment Help Operation Management
Reference no: EM13251863

Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown in Figure 1. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram in Figure 2. Phil noted that the Gear Box is assembled by the subassembly Department and subsequently is sent to the main engine assembly line. The Input Shaft is one of several component parts manufactured by Brunswick that are needed to produce a Gear Box sub-assembly. Thus, levels 0, 1, and 2 are included in Figure 2 to indicate the three manufacturing stages that are involved in producing an engine: The Engine Assembly Department, the Sub-Assembly Department, and the Machine Shop. Figure 1 Model 1000 Master Schedule Week 1 2 3 4 5 6 7 8 9 10 11 12 Quantity 15 5 7 10 0 15 20 10 0 8 2 16 The manufacturing lead times required to produce the Gear Box and the Input Shaft components are also indicated in Figure 2. Note that two weeks are required to produce a batch of Gear Boxes and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub- Assembly Department stockroom before Monday morning of that week. In preparing the MRP example, Phil planned to use the attached worksheets and to make the following assumptions: 1. Seventeen Gear Boxes are on hand at the beginning of week 1 and five Gear Boxes are currently on order to be delivered at the start of week 2. 2. Forty input shafts are on hand at the start of week 1, and 22 are scheduled for delivery at the beginning of week 2. ASSIGNMENT: 1. Initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts. Assume that lot sizing is done using lot-for-lot. 2. Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. There costs are as follows: PART COST Gear Box Setup=$90/order Inventory carrying cost=$2/unit/week Input Shaft Setup=$45/order Inventory carrying cost=$1/unit/week Given the cost structure, evaluate the cost of the schedule from (1). Assume inventory is valued at the end of each week. 3. Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?

Reference no: EM13251863

Questions Cloud

Determine the magnitude of the emf induced in the rod : A metal rod with a length of 22.0cm lies in the xy-plane and makes an angle of 37.9 degrees with the positive x-axis, What is the magnitude of the emf induced in the rod
Evaluate the cell potential at 298 k of the galvanic cell : Calculate the cell potential at 298 K of the galvanic cell below. Assume no current draw and a perfect salt bridge. Pt(s)| Cu2+ (0.05 M), Cu+ (0.50) || Fe2+ (0.01 M), Fe3+ (0.10 M) | Pt(s)
What is the current maximum output of the entire process : Given your answer for part a, how long will it take (in hours) the processing and packing operations if the operators work at their maximum capacity?
Define the purified aluminum metal : Calculate the mass of aluminum deposited on the purified aluminum metal by the application of a current of 1.225 kiloamperes for 30 minutes from a very large quantity of a solution containing Al3+ ion in the Al2O3/Na3AlF6 molten state.
Calculate a schedule using least-total-cost lot sizing : Calculate a schedule using least-total-cost lot sizing. What are the savings with this new Schedule?
How many machine that host databases do provide file sharing : A cloud company has 20 computers total. Out of the 20 computers, 9 run web servers and 12 host databases. Furthermore, 8 machines offer file sharing. Note that a particular machine can offer multiple services.
Calculate the needed percent increase in pressure : Smoking causes blood vessels to constrict. If the average blood vessel radius of a smoker decreases 1.6% Calculate the needed percent increase in pressure
Determine the reorder point : Assume the demand occurs 365 days per year. a. Determine the order quantity. b. Determine the reorder point.
Calculate the flow rate in cubic centimeters : Calculate the flow rate in cubic centimeters per second in an aorta of radius 60 cm if the average blood velocity in it is 0.81 cm/s

Reviews

Write a Review

 

Operation Management Questions & Answers

  Illustrate what are some optimizations problems you have see

Illustrate what are some optimizations problems you have seen or think companies have that cannot be structured in a format.

  Determine the resulting reliability

a computer has three modules that must work for the computer to work properly. Two modules .97 and one .99.=.97x.97x.99=0.9315. If an identical backup is installed and we assume the new computer will function if the other fails how do I determine ..

  How many boxes of lettuce should the supermarket

Past history says that tomorrow's demand for lettuce averages 230 boxes with a standard deviation of 33 boxes. How many boxes of lettuce should the supermarket purchase tomorrow?

  Which artists and movies will sell most next year

If you were the database administrator for the iTunes store, how might you use predictive analysis to determine which artists and movies will sell most next year?

  List dimensions of planning and administration competency

List four dimensions of "Planning and Administration Competency" a manager should have in order to fulfill his/her managerial responsibilities.

  Describe the type of documents or other communication needed

Describe the type of documents or other communication needed to complete the task.

  Low-cost restaurant mcdonald''s and a high quality restaurant

How might such systems differ between a low-cost restaurant such as McDonald's and a high quality, five star restaurant such as Le Cliq in Paris? How must these systems interact with the systems of supplies, vendors and customers?

  Define and discuss job analysis

Define and discuss job analysis. List and describe in detail the steps involved in conducting a job analysis. Be sure to include a discussion of some benefits and challenges of this technique.

  Summarize the unique security challenges

Malpass International has been reliant on a legacy human resource management database for the past 12 years. Now, senior management has approved funds for a complete replacement.

  Supply and demand and inventory control

Next week, Super Discount Airlines has a flight from New York to Los Angeles that will be booked to capacity. The airline knows from past history that an average of 25 customers

  What you have researched and studied throughout modules

Using what you have researched and studied throughout Modules 1 - 7, write a report addressing a quantitative analysis (QA) project

  Impact of leveling within slack on sensitivity of network

What is the impact of leveling within slack on the sensitivity of the network? Assume the project is resource constrained and resolve any overallocation problems by leveling outside of slack. What happens?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd