Space Age Furniture Company The Space Age Furniture Company manufactures tables and cabinets to hold microwave ovens and portable televisions. These products are made in various sizes and with various features, but all follow basically the same production and assembly operations. However, two of these products-the Saturn microwave stand and the Gemini TV stand-have a part (no. 3079) that requires machining on a special lathe used only for making that part. At present the machine is run by Ed Szewczak, a machinist who also operates other machines in Space Age's shop. Once set up and started, the lathe can run nearly unattended. How- ever, the machinist must be present (even if not actually attending the machine) any time one of the machines, including the lathe, is in operation. At present, Ed works a regular 40-hour week. However, due to the workload for producing part 3079, it has been neces- sary to schedule frequent overtime for him in order to finish the necessary parts on time.

Coral Snodgrass, operations manager for Space Age, has just heard from Ed's foremen that Ed is becoming unhappy about so much overtime. As Coral knows, Ed has been with the company a long time and is an excellent, reliable employee. Skilled machinists with Ed's experience and employment record are extremely difficult to find. Coral wonders what can be done to alleviate this problem.
Recently, Space Age began using an MRP system that has helped reduce inventories greatly and improve on-time deliveries. In fact, Space Age carries no finished-goods inventory. Instead, everything in the master schedule is being produced for customer orders, so all products are shipped almost immediately. Previously Space Age had estimated that it cost $1.25 per week to store each Gemini and $1.50 per week to store each Saturn that wasn't shipped immediately. The master schedule for producing these two items for the next six weeks is shown below.

Master Schedule
Week 1 2 3 4 5 6
Gemini 600 400 700 500 400 600
Saturn 300 400 400 600 300 300

The part in question, 3079, is used in two different subassemblies: no. 435, which is used in the Gemini TV stand, and no. 257, which is used in the Saturn microwave stand. One of part 3079 is used in each subassembly, and one of each subassembly is used in each of the final products.

Part 3079 may be produced in any quantity since the lathe that makes it is not used for anything else.

However, both of the subassemblies are produced using the same equip- ment. To minimize change over time, Space Age has decided that these subassemblies should be made in minimum quantities of 1,000 at a time, although there is no problem with capacity on the equipment that makes them. In fact, an order for 1,000 of subassem- bly 435 is due to be received in week 1, as is an order for 1,000 of subassembly 257. Lead time for both these subassemblies is one week, and no inventory is expected to be on hand for either part at the beginning of week

1. There is not any on-hand inventory of part 3079, and there are no orders in process.

Ed Szewczak earns $22 per hour and gets a 50% premium for any overtime work. When- ever part 3079 is made, there is no set-up time, but processing takes 0.03 hour per unit. It costs $0.25 per week to hold any of these parts over from one week to the next. The cost of holding each subassembly in inventory is $0.75 per unit per week

Respond to the following and include any Materials

Requirement Planning (MRP) calculations:
Develop an MRP for Space Age Furniture Company using the information in the case including the production of sub-assemblies in lot sizes of 1,000.
Calculate a new MRP that improves the base MRP.

Reference no: EM13223906

Questions Cloud

How individual learns is essential to improving performance : How an individual learns is essential to improving performance and effectiveness. How an organization learns is critical to remain viable and competitive. Learning is key to forward movement for an organization.
Explain the stages of buying decision process : Write a report to evaluate its buying process from the marketer's point of view using the five stages of the buying decision process.
Industry consortium marketplace instead of setting up : Describe the reasons a buyer might have for wanting to participate in an industry consortium marketplace instead of setting up its own private company marketplace.
Give description of the number of bonds between o-o atoms : In the actual O3 molecule the best description of the number of bonds between O-O atoms is____ bonds.
Calculate a new mrp that improves the base mrp : The part in question, 3079, is used in two different subassemblies: no. 435, which is used in the Gemini TV stand, and no. 257, which is used in the Saturn microwave stand. One of part 3079 is used in each subassembly, and one of each subassembly ..
Determine the present value of the continuous cash flow : 1. A new channel production facility that is under construction is expected to be in full commercial operation one year from now. Once in full operation, the facility will generate $95,000 cash profit daily over the plant's services life of 10 yea..
Civil rights movement and labor movement led by cesar chavez : What similarities and difference do you see between civil rights movement and the labor movement led by cesar chavez. what was the influence of property of these governments. Give two specificexamples that show the influence of proverty.
Explain compound is the oxide : Consider the molecules CsO2, Na2O, K2O2, MgO, and H2O2 and answer the questions below. If there is more than one answer, give both separated by a comma with no spaces. Order doesn't matter.
As what type of market would be characterized each brand : - perfume: A $100 bottle of perfume may contain $4 to $6 worth of ingredients - Jeans and "alligator/animal" shirts: The "plain pocket" jeans and the Lacoste knockoffs often cost 40 percent less than the brand-name items, yet the knockoffs are ess..

Reviews

Write a Review

Operation Management Questions & Answers

  Illustrate what are the essential feature of the systems

Illustrate what are the 5 essential feature of the queuing systems at the consumer service counter, the garage also the car wash at thrifty car rental.

  Case study - motorola

Motorola obtains cell phones from its contract manufacturer located in China to serve U.S. market. The U.S. is served from a warehouse located in Memphis, Tennessee.

  Explain nationalist groups to oppose headscarves

What are the likely motivations of the first group and what probably incites the nationalist groups to oppose headscarves?

  Given that the profit per chair and of the desk

A furniture company manufacture desk and chairs. . Given that the profit per chair is $50 and that of the desk is $100, determine the optimal production mix for the company.

  Determine the four major types of contracting officers

Determine the four major types of contracting officers and analyze how they differ in scope and responsibility from one another.

  Explain how you will resolve them

explain how you will resolve them. Also address any matters or requirements specific to your state. If there are none, state that.

  How organization use different components of marketing mix

Select an organization with which you are familiar. How does your selected organization use the different components of the marketing mix?

  Quarterly bonus for perfect attendance

If a company pays a PAT member a base wage of $24,000, a PAT incentive bonus of $1 per camera assembled, a $75 quarterly bonus for perfect attendance

  Determine the appropriate length of rail dock

Determine the appropriate length of a rail dock (in feet) given the following information. The average railcar loaded is 42 feet long and hold on average 40,000 pounds.

  Complete the network diagram do the necessary calculations

Complete the network diagram, do the necessary calculations, and state the critical path(s) and the project completion time. In a reply to this Sakai message

  The carousel ride

At a carnival, the carousel ride has a problem with keeping the mechanical horses working. Repair technicians can be hired at a rate of $30 per hour, while working as only one team. This means the technician will work alone. If two or more techs are ..

  Does an organizations culture follow its strategy

Does an organizations culture follow its strategy or does an organizations strategy follow its culture?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd