Progress and Performance Measurement and Evaluation

Project Management Ch 13

6th Edition

1:The second step in the project control process for measuring and evaluating project performance is to

A)Review the baseline plan with top management

B)Analyze inputs to control system

C)Compare plan against actual

D)Measure progress and performance

E)Review spending with team members

2:A ___________ Gantt chart is a simple and effective way to depict progress on a project.

A)Baseline

B)Control

C)Variance

D)Tracking

E)Simple

3:A tool used to monitor past project schedule performance, current performance, and to estimate future schedule trends is a simple line chart known as a

A)Project control chart

B)Gantt chart

C)PERT chart

D)Network diagram

E)Milestone chart

4:The earned value system starts with the time-phased costs that provide the project baseline, which is called the

A)Planned budgeted value of work scheduled

B)Planned budgeted value of work completed

C)Earned value of work scheduled

D)Scheduled value of work scheduled

E)Scheduled value of work completed

5:The cost variance for a project is calculated by

A)EV-AC

B)AC-SV

C)PV-EV

D)CV-EV

E)EV-PV

6:Baseline project budgets are derived from

A)The organization's overall budget

B)Time-phasing the work packages

C)Top management directions

D)The total direct, direct project overhead and G&A overhead costs

E)The earned value system

7:Of the following costs, which are NOT included in baseline?

A)Suppliers

B)Equipment

C)Labor

D)Budget reserves

E)Contractors

8:Which of the following methods will measure the cost efficiency of the work accomplished to date?

A)SV/CV

B)EV/PV

C)EV/AC

D)AC/SV

E)AC/CV

9:A CPI or SPI value less than one indicates that the project is

A)Under cost or behind schedule

B)Over cost or ahead of schedule

C)Under cost or ahead of schedule

D)Over cost or behind schedule

E)On cost or on schedule

10:The value that tells you the planned value of work that has actually been completed is the

A)SV

B)PV

C)EV

D)AC

E)CV

11:The indicator that tells you the amount each remaining dollar must earn in order for the project to stay within budget is the

A)PCIC

B)VAC

C)CPI

D)SPI

E)TCPI

12:Nancy tells her supervisor that as of right now, $1.05 worth of work has been accomplished for each $1 worth of scheduled work. Nancy got this information from viewing the

A)SV

B)TCPI

C)CPI

D)SPI

E)PCIB

13:Sally receives the following information on her project: PV=100, AC=75, EV=100. How well is the project doing in terms of budget?

A)Right on budget

B)25 under budget

C)25 over budget

D)50 under budget

E)50 over budget

14:Jessica just received the following information on her project: PV =200, EV=300, AC=250, BAC=1500, EAC=1208. In terms of cost at completion

A)The project will currently finish under budget

B)The project will currently finish over budget

C)The project will currently finish on budget

D)The project will currently finish behind schedule

E)There is insufficient information to draw conclusions

15:Which of the following is NOT true regarding scope creep?

A)It commonly occurs late in projects

B)It is frequently unnoticed until time delays or cost overruns are observed

C)It wears down team motivation and cohesiveness

D)Project suppliers resent frequent changes

E)Scope changes can represent significant opportunity

Reference no: EM131392581

Questions Cloud

Show how the gauges are wired into a bridge circuit : Show how the gauges are wired into a bridge circuit to provide temperature compensation. If each gauge has the same gauge factor, GF, derive an equation for the bridge off-null voltage as a function of strain.
Role of the federal reserve bank in regulating the economy : Explain how an easing of monetary policy impacts on the economy through its effect on exchange rates. Explain the role of the Federal Reserve Bank in regulating the economy. When a firm engages in predatory pricing, what strategy does it use to drive..
What is the speed and the distance moved : An object falls from rest near the Earth's surface, accelerating downward at 1 g. After 5 s, what is the speed and the distance moved?
Identify legal and ethical requirements of property sales : CPPDSM4008A  Identify Legal and Ethical Requirements of Property Sales to Complete Agency Work. Briefly explain each of the following titles to land (i.e. land tenure ship): Free hold, Lease hold, and Torrens Title
Baseline project budgets are derived from : Nancy tells her supervisor that as of right now, $1.05 worth of work has been accomplished for each $1 worth of scheduled work. Nancy got this information from viewing the.A tool used to monitor past project schedule performance, current performan..
Calculate the average shock in gs : Calculate the average shock in gs experienced by a transistor that falls 1.5 m from a tabletop, if it takes 2.7 ms to decelerate to zero when reaching the floor.
Calculate the peak acceleration in gs : An automobile fender vibrates at 16 Hz with a peak-to-peak amplitude of 5 mm. Calculate the peak acceleration in gs.
True about price matching strategies : Which of the following is true about price matching strategies? consumers are often mislead because they believe they are charged the same price as competing firms. if one consumer finds a lower price at Firm A,then Firm B will match its price to Fir..
Find the maximum acceleration that can be measured : Find the relation between acceleration in and output voltage, the maximum acceleration that can be measured, and the natural frequency.

Reviews

Write a Review

Operation Management Questions & Answers

  Assess how oligopoly market structure impacts

Assess how oligopoly market structure impacts Apple's financial performance as measured by performance variables over the past three years. Support your response with data and graphs illustrating two performance variables of your choosing (e.g., sale..

  Identify potential quality concerns in the traditional areas

Identify potential quality concerns in the traditional areas of machinery, employees, measurements, and materials. Organize these quality concerns using a cause-and-effect diagram.

  Determine the earliest completion time for a project with

what is the earliest completion time for a project with this information about activities?activityoptimistic timemost

  Share your advice on selecting markets for new sales

A CEO of a successful US clothing store that sells men’s and women’s athletic wear is considering expanding to markets outside the USA. The company is well established in the US and most popular with teenagers and young adults between the ages of 20-..

  Finds the median age of the population in the chain region

An ethnic restaurant, in serving a lovely, four-hour, seven-course dinner for two for $150, is giving particular emphasis to which dimension of competitive priorities

  Creat a rfp for a bpo in a ficticous organization

Creat a RFP for a BPO in a ficticous organization and explain why you would use different parts. Defend you choices to the executive team tasked with the outsourcing project.

  Implement in your grocery delivery business

Efficiency is a critical element both in terms of individuals and machinery in any business. Describe some efficiency measures that you would implement in your grocery delivery business. What are the analysis tools that you would utilize to determine..

  How much gravy should be ordered using a fixed order

Service level of 95%, standard deviation of 3.5 units per week, moving average weekly demand of 35 servings. Each gravy mix comes in packs of two servings. Currently three packs in inventory.

  Consider providing termination packages to employees

Should a company consider providing termination packages to employees who have ongoing disciplinary problems rather than taking the time and effort to go through the progressive discipline process? What are the implications of each approach?

  Pure and mixed strategies in production planning

Distinguish between pure and mixed strategies in production planning. Provide examples of each strategy.

  Explain the purpose of background investigations

Evaluate the relationship between the development strategy in one hand and recruiting and selection ? Explain why employee training is important? Also discuss Why career development is valuable to organizations? Explain the purpose of background inve..

  Progress in mastering the course competencies

The objective of this assignment is to measure your progress in mastering the following course competencies:

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd