At what earned value measurement finds out the projects

Assignment Help Operation Management
Reference no: EM13390917

Your project to deliver a product has five activities, each with a finish-to-start relationship. Project baseline information is presented below indicating the planned schedule and budgeted cost of each activity.

Baseline:

Activity Name

% Complete

Duration

(Baseline)

Start

(Baseline)

Finish

(Baseline)

Cost

(Baseline)

Product

0

256 days

6/1/11

5/23/12

 

   Requirements

0

60 days

6/1/11

8/23/11

70,000.00

   Design

0

60 days

8/24/11

11/15/11

   85,000.00

   Build

0

90 days

11/16/11

3/20/12

100,000.00

   Test

0

45 days

3/21/12

5/22/12

60,000.00

   Release

0

0 days

5/23/12

5/23/12

0.00

You have to report project status as of January 31, 2012. The associated schedule and cost information is provided below. Assume a constant resource loading (i.e., planned expenditures are constant over the duration of each activity).

Actual:

Activity Name

% Complete

Duration

(Actual)

Start

(Actual)

Finish

(Actual)

Cost

(Actual)

Product

 

215 days

6/1/11

NA

 

   Requirements

100

65 days

6/1/11

8/30/11

68,000.00

   Design

100

70 days

8/31/11

11/20/11

   85,000.00

   Build

80

80 days

11/21/11

NA

90,000.00

   Test

0

0 days

NA

NA

0.00

   Release

0

0 days

NA

NA

0.00

Calculate planned value (PV), earned value (EV), and actual cost (AC) as of January 31, 2012 and answer the questions below. Show all work. Calculate dollar values to two decimal places. Calculate all other variables to three decimal places.

1. What earned value measurement determines whether or not the project is ahead of schedule or behind schedule? What is that value?

2. What earned value measurement determines the project's rate of schedule progress? What is that value?

3. Is the project ahead of schedule, on schedule, or behind schedule? Why?

4. What earned value measurement determines how much the project is under budget or over budget? What is that value?

5. What earned value measurement is used to determine project cost efficiency. What is that value?

6. Is the project over budget, under budget, or on budget? Why?

7. Based on the current project status, what is the estimated total project cost at completion? How much more or less money (other than the current budgeted amount) will you need to finish the project?

Reference no: EM13390917

Questions Cloud

Suppose market demand is given by q 300-2p and mcac30 find : assume the market demand is given by q 300-2p and mcac30. compute the price quantity consumer surplus profits and dwl
Calculate the break-even point in units and dollars : keller company estimates that variable costs will be 60 of sales and fixed costs will total 1920000. the selling price
Workers in center 2 are scheduled to receive a 10 pay : considering the number of pieces processed per hour as its output merrifield post office is evaluating the productivity
Assume government forces monopolist to behave like : a monopoly faces demand given by q 200 - p. the marginal cost mc 10 is constant. the marginal revenue mr 200 - 2q.a.
At what earned value measurement finds out the projects : your project to deliver a product has five activities each with a finish-to-start relationship. project baseline
During the second year xtreme sports paid cash dividends of : xtreme sports has 100000 of 8 noncumulative nonparticipating preferred stock outstanding. xtreme sports also has 500000
Complete the following stock value calculations assume that : write a brief overview concerning stock valuation.nbsp your overview should includea brief explanation of the legal
Sketch the graph of ppf for each state and then draw graph : graph the equation y 14 - 2x. your graph should be carefully labeled with y on the vertical axis and x on the
Describe the target market and apparent marketing mix of : select a company that uses either b2b a company that provides products services or information to other business or b2c

Reviews

Write a Review

Operation Management Questions & Answers

  Is the customer always right

What type of leader inspires your best work? Have you have the opportunity to work for such a leader?

  A prior contract requires that the firm produce at least

The Grand Valley Company, run by the J. Motwani family, produces two products: bed mattresses and box springs. A prior contract requires that the firm produce at least 30 mattresses or box springs

  Calculate the schedule variance and cost performance index

A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low.

  How construct a new factory would result

Not constructing a new factory would result in no additional revenue being generated because the current factories cannot produce these new products. Construct a decision tree to help Expando make the best decision.

  Discuss how team basics can be applied in real situations

Discuss how the team basics can be applied in real situations where team thinking becomes important.

  Describe boeing collaborative work environment

Describe Boeing's collaborative work environment, specifically discussing collaboration techniques, interaction between leaders and followers, and supportive communication.

  Improve the corporate image of your gym

have a goal to meet/exceed monthly membership targets, and maintain/improve the corporate image of your gym

  Discuss how persuasion differs from negotiation

List and describe the top 5 factors you believe should be considered when building an effective negotiation strategy. Explain your rationale for choosing the factors you included.

  Why do you think ikea''s expansion into europe

Why do you think IKEA's expansion into Europe went so well? Why did the company subsequently stumble into North America? What lessons did IKEA learn from this experience? How is the company applying these lessons?

  Compute the total cost

ssuming transportation costs are $1 per load per meter, develop a suitable layout that minimizes transportation costs using the given information. Compute the total cost.

  Find the reorder point necessary to provide service

The annual demand for a product is 16,000 units. The weekly demand is 308 units with a standard deviation of 80 units. The cost to place an order is $30.50, and the time from ordering to receipt is six weeks.

  What are its drawbacks

We have now covered the steps of the Active Threat and Opportunity Management (ATOM) process. What is your opinion of the process as it relates to risk management? What are its benefits? What are its drawbacks?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd