Activity on project schedule has these duration estimates

Assignment Help Operation Management
Reference no: EM13758275

1. A certain project has ten activities. Two activities each have a total slack of 5 days. The total duration of the project’s critical path is 40 days. The duration of the project is:

2. A given project’s duration along its critical path is 33 days and the total slack for one of the activities is 1 day. The planned finish time for the project is:

3. An activity on a project schedule has these duration estimates: optimistic (a)=1, most likely(m)=2, and pessimistic (b)=5. The activities expected duration is:

4. An activity on a project schedule has these duration estimates: optimistic (a) =1, most likely (m) =2, and pessimistic (b) =5. The activity’s variance is:

5. A given projects expected duration along its critical path is 50 days, based on optimistic, most likely, and pessimistic duration estimates, what is the probability that the project will finish on or before 50 days?

6. A given project’s expected duration along its critical path is 22.5 days. Management eventually wants to know the probability that the project will finish on or before 28 days. The projects standard deviation along its critical path is 2.03. The appropriate complete z value is:

7. A given project’s expected duration along its critical path is 32 days. The project’s standard deviation along its critical path is 4 days. What is the probability that the project will finish on or before 35 days?

Reference no: EM13758275

Questions Cloud

Annual reports for the coca-cola company and pepsico : Using 2007 annual reports for The Coca-Cola Company and PepsiCo, Inc., answer the following questions. Write these up in a Word document, clearly identifying your response to each lettered item. Show supporting calculations for the items lettered ..
Discuss a preschool classroom and a classroom for children : Discuss a preschool classroom and a classroom for children five years old or more. Describe how the environments should use the principle of age appropriateness
Core competencies and network-based strategies : How does Procter and Gamble Company address change; consider the use of BPM/BPR and other change processes. How is Procter and Gamble Company using synergies, core competencies and network-based strategies to achieve competitive advantage?
What element of establishing an organizational strategy : Satisfying the customers of an organization is a requirement for business success. Therefore, customer perceptions matter when trying to decide what products and services the organization will offer. What element of establishing an organizational str..
Activity on project schedule has these duration estimates : A certain project has ten activities. Two activities each have a total slack of 5 days. The total duration of the project’s critical path is 40 days. A given project’s duration along its critical path is 33 days and the total slack for one of the act..
What is being done to address the issues you identified : What is the Americans with Disabilities Act (ADA)? How does the ADA address issues for the aging population?   What is being done to address the issues you identified
Paper on mobility-cdma and gsm : Discuss a minimum of three mobile web applications that are familiar or that you used regularly.
Write essay on analyze arrangement of classroom environment : write a 2-3 page essay where you will analyze the arrangement of the classroom environment and evaluate why this type of environment could effectively meet the individual needs of children with autism.
Chronic fatigue syndrom : Describe Chronic Fatigue Syndrom and its remedies

Reviews

Write a Review

Operation Management Questions & Answers

  Human resource challenges

Human Resource Challenges Find at least two articles through ProQuest which discuss at least two of the biggest challenges facing human resource departments today

  Ftc regulations on diet product claims

What do you think a court will decide here? If the company wants to comply with the FTC regulations on diet product claims, what language would need to change in the ads mentioned above?

  How many kanbans are required for the bakery

If the average setup and processing time is reduced to 3/8 of a day due to better training and retention of experienced employees. What are the answers to (a) and (b).

  What issues would a judge decide

what issues would a judge decide? What if the person(s) with liability here doesn't have the money to pay Veronica's damages?

  Identify the function you selected and explain

Select one of the functions of law. Identify the function you selected and explain how it is important to American society. Provide at least one example.

  Illustrate what recommendations can you offer dick enrico

Illustrate what recommendations can you offer Dick Enrico to improve his chances of staying successful for the rest of his career.

  Which technology is most useful in tracking inventory

Which technology is most useful in tracking inventory? a. robotics b. CIM c. CAD d. RFID

  Analyze this data using an appropriate control chart

Each week a sample of 100 residents is questioned on their feelings towards project. Results to date are shown below. Analyze this data using an appropriate control chart with a 5% risk of Type I error.

  Compute forecasts for the remaining five months

Compute forecasts for the remaining five months utilizing simple exponential smoothing. Which of the changes being considered by the manager of XYZ contradict the lean philosophy.

  What is a transducer

What is a transducer? How can we classify transducers? On what principles do the variable inductance type of transducers work? What are uses of LVDT for measurement?

  Forecasting the quarterly sales

A two year sales history by quarter for a seasonal product is given below. Using Winter's method, forecast the quarterly sales for the third year.

  Multiple choice questions - operation management

The fraction of orders filled by a distribution center or warehouse within a specific time period is referred to as the

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd