Activities on the critical path exhibit positive slack times

Assignment Help Operation Management
Reference no: EM131794882

1. Activities on the critical path exhibit positive slack times.

TRUE FALSE

2. The variance of project completion time equals the variances of all activities in the project.

TRUE FALSE

3. The expected activity time is the average of an activity’s optimistic and pessimistic times.

TRUE FALSE

4. Dummy activities are found in activity-on-arc (AOA) convention PERT/ CPM network models.

TRUE FALSE

5. The dummy activity has an expected time of zero by definition.

TRUE FALSE

6. Early start time ( ES ) is computed from right to left (backward pass)

TRUE FALSE

7. The project-group approach extends little or no formal authority to the project coordinator.

TRUE FALSE

8. The expected completion time of a task (activity) is approximated by the normal probability distribution.

TRUE FALSE

9. CPM was developed for a project for which task (activity) times were uncertain.

TRUE FALSE

10. With probabilistic PERT, we are able to calculate the probability of finishing the project on a particular day or week.

TRUE FALSE

11. The 3 time estimates employed in PERT are optimistic time, average time, and pessimistic time.

TRUE FALSE

12. In PERT, the early start time for a task is equal to the latest of the early finish times of all of its immediate predecessors.

TRUE FALSE

13. PERT stands for Probabilistic Evaluation and Review Technique.

TRUE FALSE

14. In PERT, we assume project completion time can be modeled by the normal probability distribution.

TRUE FALSE

15. In PERT, the variance in project completion time is equal to the variance of the most time-consuming task (activity) on the critical path.

TRUE FALSE

Reference no: EM131794882

Questions Cloud

Production process consists of three-step operation : A production process consists of a three-step operation. The scrap rate is 14 percent for the first step and 8 percent for the other two steps.
Recruiting is one of the areas of HR : Recruiting is one of the areas of HR that you like to research more:
International business venture requires creativity : Starting a new, international business venture requires creativity, planning, financing and marketing among the key ingredients for a successful undertaking.
Significance of culture in marketing product or service : What is the significance of culture in marketing a product or service?
Activities on the critical path exhibit positive slack times : PERT stands for Probabilistic Evaluation and Review Technique. Activities on the critical path exhibit positive slack times.
Write a driver program to test the look ahead stack class : Design Look Ahead Stack as a class template derived from a Stack class template.Write a driver program to test the Look Ahead Stack class .
Write a driver program to test the document class : You should also write driver programs to test them as instructed in the programming problems at the end of this chapter.
Write a complete payroll program for a company : Write a complete payroll program for a company in which each employee falls into one of the five categories described in the text.
Write a driver program to test the sales person class : Salespersons are paid a salary plus a commission on their sales; their total pay, therefore, is their salary plus the amount of their sales times the commission

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd