A formal change request

Assignment Help Operation Management
Reference no: EM13751893

Your task for Week 4 is to prepare a project proposal on how to adjust the project schedule. The proposal should include only descriptions of the ways in which you propose to modify the project schedule. Your final project (due in Week 8) will include the following:

  • A formal change request
  • An evaluation of the impact of the change (as submitted to the Change Control Board)-time and labour only. Note: It will be necessary to create the original project schedule and budget to analyse the impact of the change request. Consider that the additional wing will be built concurrently.
  • A list of all the assumptions made
  • An analysis of risk factors due to the change request
  • A new project schedule that shows:
    • The additional time required
    • The additional labour cost
    • The new completion date
  • A statement of work for one contractor
  • A contract closure process description for one contractor
  • A project closure process description

The project details are as follows:

The Smiths decide to build a house on a piece of land that they have purchased. They have consulted with an architect and have the blueprints created. You are a general contractor and have agreed to build the house for them. The Smiths inform you that they had been considering the addition of an extra wing in the house but have now decided against it as the additional space is unnecessary. The original blueprints that the Smiths gave you did not have the additional wing.

You have projected that it will take you 12 weeks to complete the house. However, you need a buffer to accommodate the uncertain weather conditions, and you tell the Smiths that you will need 14 weeks. The Smiths are really anxious to move into their new house. Although they agree for 14 weeks, they also want to put in a penalty for late completion. You agree, provided they also put in a bonus for early completion. You reach an agreement with the Smiths, and the contract is signed. You have figured the project duration and effort as follows:

Task

Duration (days)

Effort (staff days)

Comments

Get a building permit.

5

1

Clear the site.

5

20

Dig the foundation and footings.

3

9

Install forms.

3

9

Pour concrete.

1

5

Wait for the concrete to harden.

5

0

This is referred to as lag time.

Remove forms.

1

3

Build the floor.

1

5

Frame the first floor.

2

10

Build the second floor.

2

10

Frame the second floor.

3

15

Sheath the house.

3

12

Install windows and doors.

4

8

Install siding.

2

6

Put up roof framing.

2

8

Can start as soon as the second floor is framed

Shingle the roof.

1

4

Install plumbing.

4

8

Can start as soon as the roof is shingled

Inspect the plumbing.

1

0

Install wiring.

6

12

Can start as soon as the roof is shingled

Inspect the wiring.

1

0

Hang and finish sheetrock.

4

12

Can start only after the plumbing and electrical work are inspected

Paint the interior.

3

9

Lay the carpet.

2

6

Install the hardwood flooring.

3

6

Install trim.

3

6

Procure the certificate of occupancy.

5

0

Total

75

184

Just as your crew starts framing the second floor, the Smiths tell you that they would now like the additional wing in the house they mentioned previously. The Smiths present you with a new set of blueprints, containing the new wing and ask for a projected difference in price and time for the addition.

You figure that to add the extra wing the following would be required in terms of duration and effort:

Task

Duration (days)

Effort (staff days)

Comments

Dig the foundation and footings.

2

6

Install forms.

2

6

Pour concrete.

1

3

Wait for the concrete to harden.

5

0

This is referred to as lag time

Remove forms.

1

2

Build the floor.

1

4

Frame the first floor.

1

4

Build the second floor.

1

4

Frame the second floor.

2

8

Sheath the house.

2

6

Install windows and doors.

2

4

Install siding.

1

3

Put up roof framing.

2

6

Shingle the roof.

1

3

Install plumbing.

2

4

Inspect the plumbing.

Install wiring.

2

4

Inspect the wiring.

Hang and finish sheetrock.

2

6

Paint the interior.

1

3

Lay the carpet.

2

4

Install the hardwood flooring.

Install trim.

1

3

Total

34

83

This new estimate to add the wing, assumes the sheathing will go on the base house and then work will stop until the extra wing is sheathed. You believe this will be the most economical way to add the additional wing to the property. Another option would be for the project to continue as originally planned, and then add the wing after the Smiths have moved in. After considering both options, the Smiths choose to follow your recommendation to add the new wing now so that they move in when the whole house is complete. The additional work required is as follows:

Task

Duration (days)

Effort (staff days)

Comments

Procure the building permit.

5

1

Dig the foundation and footings.

2

6

Install forms.

2

6

Pour concrete.

1

3

Wait for the concrete to harden.

5

0

Remove forms.

1

2

Build the floor.

1.5

6

Frame the first floor.

1.5

6

Build the second floor.

1.5

6

Frame the second floor.

2

8

Add the sheath.

2

6

Install windows and doors.

2

4

Install the siding.

1

3

Put up roof framing.

2.5

7

Shingle the roof.

1

3

Install plumbing.

2

4

Inspect the plumbing.

1

0

Install wiring.

2

4

Inspect the wiring.

1

0

Hang and finish sheetrock.

2

6

Paint the interior.

1

3

Lay the carpet.

2

4

Install trim.

1

3

Total

38

90

The rates for the various trades (in $/hour) are as follows:

Code

Description

Rate

Comments

GC

General contractor

40.00

HE

Heavy-equipment operator

50.00

Includes equipment

C

Concrete worker

30.00

F

Framer

20.00

F

Siding installer

20.00

W

Window/door installer

30.00

R

Roofer

20.00

P

Painter

20.00

E

Electrician

35.00

FL

Flooring installer

20.00

T

Trim carpenter

35.00

PL

Plumber

35.00

In this project, you will analyse the situation andthe effect of the change request on the schedule, cost, and features. The final project, due in Week 8, will be based on your answers for this week and for Week 6.

Please make sure that you cite and reference all your outside sources properly, as per the Harvard Referencing System.

Reference no: EM13751893

Questions Cloud

Effect on return on equity of raising capital through debt : Debt has deadlines. Deadlines can be missed. Common stock lasts indefinitely. The higher percentage of resources raised from debt, the higher percentage resources subject to deadlines, hence risk. What is the effect on return on equity of raising cap..
Governance and fraud in health care organizations : Governance and Fraud in Health Care Organizations - Legal and Ethical Responsibilities - Management's Financial responsibility and consequences of a violation.
Instrument divisions income from operations increase : Materials used by the Instrument Division of Dart Industries are currently purchased from outside suppliers at a cost of $180 per unit. However, the same materials are available from the Components Division. How much would the Instrument Division's i..
Why you think we are difficult time recover from depression : With our vast resources today, why do you think we are having such a difficult time recovering from the depression of 2008?
A formal change request : Prepare a project proposal on how to adjust the project schedule. The proposal should include only descriptions of the ways in which you propose to modify the project schedule. Your final project (due in Week 8) will include the following: A forma..
Intermediate products should be processed further : Beets 'R' Us processes sugar beets in batches that it purchases from farmers for $57 a batch. A batch of sugar beets costs $12 to crush in the company's plant. Two intermediate products, beet fiber and beet juice, emerge from the crushing process.
Net cash flow for the last year of the computers useful life : Avis Corporation currently records $4,000 of depreciation each year on the computer that it uses for its major data processing needs. The computer currently has one more year of useful life left and it will have a salvage value of zero at the end of ..
What was the nature of massachusetts bay colony : What was the nature and character of Massachusetts Bay Colony Plymouth in Massachusetts, and the establishment of Maryland Based on your reading of the articles?
Examine the concepts of managing operations : Examine the concepts of managing operations as they apply to the production of goods and services - Apply the appropriate operations tools to aid in decision-making and optimize performance.

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd