10) Bragg's Bakery is building a new automated bakery in downtown Omaha.  Here are the activities that need to be completed to get the new bakery build and the equipment installed.

Activity

Predecessor

Normal Completion Time (Weeks)

Crash Completion Time (Weeks)

Crash (Expediting) Cost/Week

A

--

9

6

$3,000

B

A

8

5

$3,500

C

A

15

10

$4,000

D

B,C

5

3

$2,000

E

C

10

6

$2,500

F

D,E

2

1

$5,000

As with the other test problems, you must show your work to receive full credit.

a) What are the normal project completion time and the critical path?

b)  What activity(ies) should be crashed to reduce the completion time found in a) by one week?  What activity(ies) should be crashed if you want to reduce the completion time found in a) by six weeks?

c)  Bragg's loses $3,500 in profit per week for every week the bakery is not completed.  How many weeks will the project take if the bakery is willing to pay the crashing cost as long as it is economically the right decision? 

d) What is the project completion time if all activities are crashed to their minimum Crash Time?  Also, ignoring the $3,500 lost profit in c), what is the total additional cost incurred for crashing all of the activities to their minimum Crash Time compared to the Normal Times? 

Reference no: EM13358303

Questions Cloud

Depreciation using the revised amounts and straight : depreciation using the revised amounts and straight linecomputer equipment was acquired at the beginning of the year at
Important information about reward systemi need assistance : important information about reward systemi need assistance with a power point presentation. here are the
Describe an information systemplease provide a description : describe an information systemplease provide a description of an information system that you have encountered such as
Important information about hardware and softwarecould : important information about hardware and softwarecould someone explain in a short paragraph how can participants in the
10 braggs bakery is building a new automated bakery in : 10 braggs bakery is building a new automated bakery in downtown omaha.nbsp here are the activities that need to be
Standard costing and process costing1 azzurra company : standard costing and process costing1. azzurra company manufactures computer chips used in aircraft and automobiles.
9 anbsp the academic service process commonly referred to : 9 anbsp the academic service process commonly referred to as registration consists of several smaller processes
Mbatm 592 baderman island business planindividual - : mbatm 592 baderman island business planindividual - presenting the business case for a technology solutionin a
Organizations are becoming more socially conscience or : organizations are becoming more socially conscience or less?do you think organizations are becoming more socially

Reviews

Write a Review

Operation Management Questions & Answers

  Management of the new fangled softdrink company

Management of the New Fangled Softdrink Company believes that the probability of a customer purchasing Red Pop or the company major competition

  What are key characteristics of effective objectives

When is the implementation of a personal Balanced Scorecard completed?

  Organizational metaphors

Organizational Metaphors

  Discuss the factors influencing employee issues

Discuss the factors influencing employee issues including the right to work, employment at will, due process and employee participation, health and safety standards, family responsibilities, the right to privacy, and substance abuse testing.

  Calculate the average setup cost per year

Radovilsky Manufacturing Company, in Hayward. California. makes flashing lights for toys. The company operates its production facility 300 days per year.

  Analyze three key organizational capabilities

Online publications such as BusinessWeek and The Economist, and assorted websites, will help you gather these facts.

  What is the minimum amount of swiss francs

what is the minimum amount of Swiss Francs they should receive on September 28th, 2014 given the 9-month forward rate for one US dollar in terms of Swiss Francs you calculated in problem one? What are two other ways Nestle might hedge its SF/US$ e..

  Determine company contribution to the pension fund

Each year, the Schriber Corporation must determine how much to contribute to the company's pension plan. The company uses a ten-year planning horizon to determine the contribution which, if made annually in each of the next ten years, would allow for..

  Compute the total variable inventory cost with the optimal

Compute the total variable inventory cost with the optimal Q* and R*. a. $400 b. $200 c. $800 d. $600 e. $1000

  Predict the out come of the risk schedule

Predict the out come of the risk schedule of the risk management process within this organization. Include examples(ie the incorrect assessment) to support your prediction.

  Discuss factors that affect employee motivation

Recruitment is of little use if an organization cannot retain key employees. Therefore, it is critical that organizations properly motivate and reward their employees.

  Discuss the issue of project constraints

Discuss the issue of project constraints also other unique aspect of the bridge in the risk management process. Were these issues taken into consideration why.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd