How abrasion and earthquake causes deterioration in steel structures

Define the Arrow Diagramming Method Activity-on-Arrow (Branch) with nodes as dependencies Uses finish-to-start precedence only. The solution method for an activity on


Loss of prestress due to creep of concrete Creep of concrete means time dependent deformation of concrete. Its effect depends upon the interval of  time for which the member is

Question After construction of watermain, earlier to hydrostatic pressure test , swabbing is approved out. What is main purpose of swabbing ? Answer Pipelines ha

A 2 m wide strip footing is to be constructed in a sandy stratum of 2 m thick. The depth of the footing is 1 m below ground surface. The sand layer is underlain by lm thick cla

briefly explain the stacking of materials in the site for general building?

Q. Holes in steel plates connecting to H-piles There are two types of holes present in the steel plate associated to H-piles in the pile cap. The first type of holes is design

The transmission main from the well field to the community is 2500 ft, the velocity of flow at peak pumping capacity is 3.5 fps, water temperature is 10oC, and pH is 7.5. If free c

A capital improvement project requires the installation of a property line fence along the 250-ft Northern boundary line.The decorative aluminum fence is constructed of posts space