The higher reliability, Management Theories

Nitin's  production line has three machines A, B, and C, with Reliabilities of 0.99. 0.96, and 0.93, respectively. The machines are arranged so that if one breaks down, the others must shut down. Engineers are weighing 2 two alternative designs for increasing the lines, reliability.  Plan one involves adding an identical back up line, and plan two involves providing a backup for each machine. In either case, three machines (A, B, C ) would be used with reliabilities equal to the original three.

a) Which plan will provide the higher reliability? Show all your calculations.
                                 
b) Describe why the two reliabilities are the same.
                      

c) What other factors may enter into the decision in which plan to adapt?
                                           
(d) Suppose that the single switch used in plan on98% reliable, while readabilities of the machine remain the same. Recalculate the ratability of plan one. Compare the reliability of this plan with the ratability of plan one calculated in solving the original problem. How much did the ratability of plan one decrease as a result of a 98% reliable switch?
                                       

e)  Suppose that the three switches used in plan two are all 98% reliable, while reliabilities of the machines remain the same. Recalculate the reliability of plan two. Compare the reliability of this plan with the reliability of plan two calculated in solving the original problem. How much did the reliability of plan two decreases?

Posted Date: 3/14/2013 8:10:43 AM | Location : United States







Related Discussions:- The higher reliability, Assignment Help, Ask Question on The higher reliability, Get Answer, Expert's Help, The higher reliability Discussions

Write discussion on The higher reliability
Your posts are moderated
Related Questions

what are the secondary sources of information while pursuing market research?

Ask question #Minimum 100 words acc? Evaluate (Using examples) the systems and contingency theories. epted#

Strategic MIS Categories in Detail.

example of selection process

Do you offessistance or do projects on project Management?


Why would I be interested in completing an operations management program

A company produces electrical metering devices that monitor power quality. The company's fixed cost is $68,000 per month. The variable cost is $80 per metering device. The selling

QUESTION Explain with supporting reasons, whether or not you agree with each of the following statements: a) Because we are a big manufacturing company we have a lot of fixe