an electric company which generates and distributes electricity conducted a study on the life of poles. tha appropriate life data are given in the following table:
years after installation 1 2 3 4 5 6 7 8 9 10
percentage poles failing 1 2 3 5 7 12 20 30 16 4
1.if the company now installs 5000 poles and follows a policy of replacing poles only when they fail, how many poles are expected to be replaced each day during the next ten year.
Posted Date: 10/29/2012 1:01:24 AM | Location : United States







Related Discussions:- replacement, Assignment Help, Ask Question on replacement, Get Answer, Expert's Help, replacement Discussions

Write discussion on replacement
Your posts are moderated
Related Questions
Anthology or Book with Articles  or Works by Many Authors   The name  of the person  compiling the book  will be  given  followed  by the  word editor. For more  than one  edit

The scientific methods is based on certain article of path these are: 1. Reliance on Evidence: Truth is established on the basis of evidence. Conclusion is admitted onl

Scattered Responsibility and Authority: In a big industry responsibility and authority of decisions making is scattered throughout the organization and thus the organization.

a paper mill prodecs two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper in

Maximize Z= 3x1 + 2X2 Subject to the constraints: X1+ X2 = 4 X1 - X2 = 2 X1, X2 = 0

Secondary Periodicals: Secondary Periodicals Secondary periodicals are  abstracting and indexing periodicals.  They are also called documentation periodicals. They are a  syst


Normal 0 false false false EN-IN X-NONE X-NONE MicrosoftInternetExplorer4

#questionA paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grad

Solve the following Linear Programming Problem using simple method Maximize Z= 3x1 + 2x2 Subject to the constraints: X1 + X2 = 4