Project network , Operation Management

Heckman of Saul and Saul Consultants has get a request from Deborah, the head of Human Resources, to make an interactive icon-and-menu-driven software package to be used by the advantages specialists in her department.  Based on preliminary discussions with Deborah, Heckman has identified two basically different types of functions that the package will have to serve, so he is planning on having it written in two modules.  Based on this initial information, Heckman has broken the project down into 8 basic activities along with their predecessors and estimated times as follows:

ACTIVITY    DESCRIPTION        PREDECESSOR    TIME (in weeks)
A        Survey users' needs            --                           2
B        Design graphic icons            A                           3
C        Develop flowchart            A                               1
D        Design input/output screens        B, C                 3

E        Code module 1            C                                    4

F        Code module 2            C                                    5
G        Merge modules and graphics        D, E, F             1
H        Test program                G                                   2
    
(a)    Illustrate a project network for the above activities.
(b)    Verify which activities are critical
(c)    Verify which activities are non-critical and their respective slack times.
(d)    How long will the project take to accomplish?

Posted Date: 3/25/2013 4:08:40 AM | Location : United States







Related Discussions:- Project network , Assignment Help, Ask Question on Project network , Get Answer, Expert's Help, Project network Discussions

Write discussion on Project network
Your posts are moderated
Related Questions
You are writing a System Safety Program Plan (SSPP). What are some of the key elements/tasks you should include in the SSPP to make this plan effective?

What are the negative impacts of business intelligence? How does a database and data warehouse support business intelligence?

Standard Deviation - Statistical Aspects of Variability Although the range gives an indication of variability, its value is solely determined by two measurements, the largest

Total and Partial Factor Productivity Measurements  Total factor productivity (TFP) is the best measure when describing national productivity, because it includes all the inpu

#question. 1. how does a formal procurement policy affect customer service

What is the business community's responsibility regarding mitigating social problems?

Suppose the length of critical path in a project is 40 days and the standard deviation is 2 days. What due date should be set for the project so that the probability of completing

What operation management decisions would need to be made to change wheeled coach repetitive focus strategy to: a. process focused? b. product focused?

Discuss the idea that an information system by itself can rarely provide a sustainable competitive advantage?

(Teddy Bower Boots) To ensure a full line of outdoor clothing and accessories, the marketing department at Teddy Bower insists that they also sell waterproof hunting boots. Unfortu