Operation Planning and Scheduling System

Operation planning g and scheduling system concern the volume and timing of the outputs utilizations of the operations capacity and the balancing output with capacity at desired levels for competitive effectiveness.

The overview structure can be understood with the help of the diagram given below:

1291_Operation Planning and Scheduling System.png

Aggregate production or Output Planning: This plan is the production portion of the business plan and addresses the demand side of the firms activities by showings the outputs it will produce expressed in numbers of units of its product groups or families. Since various products groups may be produced at diverse plants facilities, or division each of them needs its own production plan. The division aggregate output (o/p) plan covers the emerging out from 6 to 18 months on a weekly or monthly basis. Planning at the level ignores such details as how many of each individual product, style color option /model to generate. The plan identifies the division existing fixed capacity and the company complete policies for maintaining inventories and back log employment stability and subcontracting.


Related Discussions:- Operation planning and scheduling system

Explain the importance of learning curves, Describe the importance of learn...

Describe the importance of learning curves in a services-based operation and how they can be used to increase organization efficiency. Please provide a specific example.

Describe skills or abilities you would need to develop, "CIOs" Please respo...

"CIOs" Please respond to the following: •Assess the role of the CIO within any health care organization and describe the key characteristics a CIO would need to possess to be effec

How the use of strikes has increased, The use of strikes has increased in t...

The use of strikes has increased in the last decade such that the FMCS reports now show a 10% utilization rate

Explain control board meeting to approve a scope change, Which of the follo...

Which of the following is normally not addressed in a change control board meeting to approve a scope change? Answer Cost of the change Which functional unit will perform

Process strategy at wheeled coach, Why do you think major auto manufacturer...

Why do you think major auto manufacturers do not build ambulances?

Organizing process flows, Organizing Process Flows Five types of proc...

Organizing Process Flows Five types of process are distinguished. They are Project Production System Job Shop Production system Batch Production system

I need excel backup to understand a problem, Need Excel backup to understan...

Need Excel backup to understand how to answer this question. Bob White leaned back and wiped his forehead with his hand. He was the president of the home oven division of Winkley &

Explain swot analysis of united airlines, Can you help me with the swot ana...

Can you help me with the swot analysis of united airlines?

Define potential risks and bottlenecks that occur in project, Briargrove ha...

Briargrove has agreed to your plan. The CLN Team is asking for a refined version of the plan making the corrections based on their recommendations. They are requesting a comprehens

Expected effectiveness of plan, Expected effectiveness of plan: Ramon ...

Expected effectiveness of plan: Ramon Martinez is the general manager of Classic Inn, a local mid-priced hotelwith 100 rooms. His job objectives include providing resourceful

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd