OLAP CUBES, Database Management System

1) Define a job scheduling strategy that will meet business requirement of reporting availability by 6am CST for the following cubes? Show the job scheduling dependencies in a pictorial form so that it is easy to understand.
a. Finance cube (3 hours to build)
b. Warranty cube (4 hours to build)
c. Order cube (2 hours to build)
d. Customer master data (30 min run time)
e. Vendor master data (60 min run time)
f. Product master data (60 min run time)
g. Other Master data (2 hour run time)
Finance and Order cubes cannot run together
Posted Date: 3/26/2013 2:28:53 PM | Location : USA







Related Discussions:- OLAP CUBES, Assignment Help, Ask Question on OLAP CUBES, Get Answer, Expert's Help, OLAP CUBES Discussions

Write discussion on OLAP CUBES
Your posts are moderated
Related Questions
what is Nested relational model? Explain with examples.

Use of partial data by applications : In common, applications work with views rather than whole relations. Thus, it may be more appropriate to work with subsets of relations rather

Write short notes on tuple relational calculus. The tuple relational calculation is anon procedural query language. It defines the desired information without giving a particul

A super key is an attribute or set of attributes used to recognize the records uniquely in a relation. For instance, in the Relation PERSON defines earlier PERSON_ID is a super

i have assignments I don''t have time to finish because of work and other assignments, can you help with this? All are from the book Darabase design, application development and a

basic structure of xml

How can you connect to the MySQL Server? In order to connect to the MySQL server it is necessary to give the username and password so this be able to done with The following

How to create a table from existing table? Create table as e.g, To create a new table ‘N_emp' with employee names and their identification numbers only from employee ta

Differentiate between horizontal & mixed horizontal fragmentation?