Module site installation preparation, Mechanical Engineering

Assignment Help:

Q. Module Site Installation Preparation?

The following tasks shall be accomplished at the Facility site prior to setting the modules on the piles:

After module support piles have been installed, the cap plate of each pile shall be surveyed to determine the top elevation of the cap plate when flat shim plates are used. Survey each corner of the cap plates when tapered shims are used. Refer to the construction drawings as appropriate, for various site conditions.

The ground between the piles shall be cleared of debris and the entire area shall be levelled as required to suite the placement of module either by crawler, RTVs and/or crane. The Project Site construction support shall obtain from logistics the area and elevation of the ground that needs levelling. In many instances an area in front of RTV or crawler setting the modules must also be levelled.


Related Discussions:- Module site installation preparation

Battery-electrical system , Battery: Battery is a device that produces dir...

Battery: Battery is a device that produces direct current (DC). The chemical energy of battery ingredients converts into electrical energy in the form of direct current. This is a

Low alloy creep resisting and electrodes for cryogenic , LOW ALLOY CREEP RE...

LOW ALLOY CREEP RESISTING ELECTRODES AND ELECTRODES FOR CRYOGENIC APPLICATIONS The flux coating contains small amount of alloying elements like Cr, Mo and sometimes V for creep r

Engineering mechanics, how to solve engineering mechanics statics problem?

how to solve engineering mechanics statics problem?

Find out the amount of energy spent, Find out the amount of energy spent: ...

Find out the amount of energy spent: 6 cubic metre of water is to be lifted to a height of 40 metres and delivered having velocity of 4 metres/sec. If this operation takes 12

Ratio of belt tension, Prove that the ratio of belt tension is given by the...

Prove that the ratio of belt tension is given by the T 1 / T 2   = e μθ Let  T1 = Tension in belt on the tight side T2 = Tension in belt on the slack side θ = Angle

Difference between the open and closed systems, Provide short answers to th...

Provide short answers to the following questions: a)   What the necessary condition for a heat transfer process to occur? b)   What is a difference between the steady state c

SOM, Torsion of shaft

Torsion of shaft

Kinematics of machine, what is the cross head velocity in slider crank mech...

what is the cross head velocity in slider crank mechanism.

Schedule selection -schedule evaluation-heuristics, Schedule Evaluation ...

Schedule Evaluation The schedules are evaluated as per to the criterion weighted loss of slack. Now let t 0 si be the slack (time buffer) of job I as per to the initial sched

Mechanics, what are the angle between two force to make their resultant a m...

what are the angle between two force to make their resultant a minimum and maximum respectively .

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd