Module site installation preparation, Mechanical Engineering

Assignment Help:

Q. Module Site Installation Preparation?

The following tasks shall be accomplished at the Facility site prior to setting the modules on the piles:

After module support piles have been installed, the cap plate of each pile shall be surveyed to determine the top elevation of the cap plate when flat shim plates are used. Survey each corner of the cap plates when tapered shims are used. Refer to the construction drawings as appropriate, for various site conditions.

The ground between the piles shall be cleared of debris and the entire area shall be levelled as required to suite the placement of module either by crawler, RTVs and/or crane. The Project Site construction support shall obtain from logistics the area and elevation of the ground that needs levelling. In many instances an area in front of RTV or crawler setting the modules must also be levelled.


Related Discussions:- Module site installation preparation

Internal energy - thermodynamics, Internal Energy (U): It is the energ...

Internal Energy (U): It is the energy possessed by the system on account of its configurations, and motion of atoms and molecules. Not like potential energy and kinetic energy

State the need and function of foundation, Need and Function of Foundation ...

Need and Function of Foundation A foundation can be defined as that part of a structure which serves to transmit the forces and moments coming from the structure above the gro

Explain welding process, Welding Process: There are many definition of a we...

Welding Process: There are many definition of a welding process. But the most comprehensive definition is below. Welding is defined as a "a localized coalescence of metals, wher

Newtons first law, Problem: Newton's First Law Newton's First Law of Mo...

Problem: Newton's First Law Newton's First Law of Motion says that, in the absence of external forces, an object at rest stays at rest and an object in motion continues at cons

.high lead copper alloy castings, I have faced a serious problem of Lead se...

I have faced a serious problem of Lead segregation and porosity in Copper Tin Zn alloy containing 26-30 % lead sand castings.Can anybody throw light on this

Gears, what is gear kinematics

what is gear kinematics

Effective communication is an intergral aspect, Effective communication is ...

Effective communication is an itergral aspect in the mechanical engineering field, base on arguement

Find stress intensity factor - thick cylinder, Find stress intensity factor...

Find stress intensity factor - thick cylinder: A thick cylinder of r i = 10 mm, r 0 = 70 mm carried equal and symmetric radial cracks 6 mm long on opposite sides of inner su

What are main important terms included in the footings, What are main impor...

What are main important terms included in the footings? Term included in the footings: a. described different types of footings and the process of selecting each type, b.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd