How to calculate the dry density and void ratio, Civil Engineering

Assignment Help:

A moist soil sample compacted into a mould of 1000 cm3 capacity and weight 35 N, weighs 53.5 N with the mould. A representative sample of soil taken from it has an initial weight of 0.187 N and even dry weight of 0.1691 N.

State (a) water content, (b) wet density, (c) dry density, (d) void ratio and (e) degree of saturation of sample.

 


Related Discussions:- How to calculate the dry density and void ratio

Define collisions - underwater inspection of bridge, Define Collisions - Un...

Define Collisions - Underwater Inspection of Bridge? Structural damage to underwater portions of a bridge can either be collision related or direct result of a collision. Colli

Factors that affect design facility of screw pumps, Question While sele...

Question While select screw pumps in polder scheme projects , what are factors that affect design facility of screw pumps? Answer Commonly used angles of inclination

Explain the term - uniaxial - biaxial -triaxial prestressing, Explain the t...

Explain the term - Uniaxial - Biaxial -Triaxial Prestressing These terms refer to cases when the concrete is prestressed in only one direction, in two mutually perpendicular di

Bricks, BRICKS Brick is obtained by moulding good clay into a block, wh...

BRICKS Brick is obtained by moulding good clay into a block, which is dried and then burnt. It is the oldest building block to replace stone. Manufacture of brick started havin

Advantages of bonded post-tensioning systems, Advantages of bonded post-ten...

Advantages of bonded post-tensioning systems Some advantages of bonded post-tensioning systems over unbonded post-tensioning ones are the following : (a) Large reduction in

Proctor test for GSB material, what is the procedure for gsb proctor test f...

what is the procedure for gsb proctor test for matrial sampling for lab density

Define npdes sampling requirements, Define NPDES Sampling Requirements? ...

Define NPDES Sampling Requirements? The sampling needs under NPDES are given at 40 CFR Part 122, as part of the needs for applying for an NPDES discharge allow. The needs are b

Railway bridge, how to measure the waterways of railway bridges

how to measure the waterways of railway bridges

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd