Graphical method, Financial Management

Assignment Help:

The graphical method is a simple one, and is the most easily understood of the several linear programming methods. A thorough knowledge of the graphical procedure provides necessary insight and confidence to understand the more advanced methods and concepts behind these methods. However, it should be pointed out that the graphical method can be applied only in the case of two variables. It cannot be applied to problems with many variables.

Maximization

Example 

Consider a small foundry which specializes in the production of iron castings. For the sake of simplicity, assume that the foundry specializes in producing two types of castings - casting A and casting B. Because of a strong consumer demand for these products, it is assumed that the foundry can sell as many units as it produces. The profit is Rs.70 and Rs.40 for each of casting A and casting B respectively. The foundry manager should decide the quantity of these castings to be produced each week so as to maximize the total profit.

Production of castings requires certain resources like raw materials, labor and foundry capacity. The requirements and their availabilities are given in the following table:

Resources

 

Required per unit of

Available in a week

 

Casting A

Casting B

Raw material -1

Raw material -2

Labor

Foundry capacity

2 kgs.

0.8 kgs.

3 man-days

4 units

1 kg.

none

2 man-days

3 units

120 kgs.

40 kgs.

200 man-days

360 units

Let us formulate this problem in terms of mathematical equations or inequalities.

As the manager has to decide the number of type A and type B castings to be produced, let us define the variables:

         q1 = number of type A castings to be produced

         q2 = number of type B castings to be produced

For this production schedule, the total profit will be

                   70q1 + 40q2

This function is known as the objective function which is to be maximized. If there are no constraints, the profit can be increased to infinity. In real life, there are restrictions of different kinds. These are formulated as constraints.

Let us consider raw material-1, of which only 120 kgs are available. If q1 of type A castings and q2 of type B castings are produced, then the requirement of raw material-1 is 2q1 + 1q2, and this should be less than or equal to the available quantity of raw material-1. This can be shown by the following inequation:

                   2q1 + 1q2 < 120

This implies that we are interested in the values of q1 and q2 for which the left-hand-side value is less than or equal to the right-hand-side value of 120. Otherwise, the requirement will exceed the availability and the production of that quantity will not be feasible.

By a similar argument, we get the constraints for raw material-2, labor and foundry capacity as:

         Raw material-2       :0.8q1  + 0q2 < 40

         Labor                   :3q1 + 2q2  < 200

         Foundry capacity   :4q1 +  3q2  <  360

As one cannot produce negative quantities, we have the restrictions:

         q1 > 0, q2 > 0

Putting together the above elements, the problem may be represented as:

Maximize Z: 70q1 + 40q2                  ....(1)

Subject to constraints:

    2q1  +  q2        <    120.

    8q1   +   0q2     <      40               ....(2)

    3q1   +  2q2     <     200

    4q1   +  3q2     <     360

      q1 >0, q2 > 0                            ....(3)

We have to find the values of q1 and q2 which will satisfy constraints (2) and (3) and at the same time maximize function (1). The function given in (1) is called an objective function. The inequalities in (2) are called constraints and the inequalities in (3) are called non-negativity restrictions or constraints. This problem cannot be solved by the calculus method because of the inequality constraints.

The first step in the graphical method of solution is to identify the region in the graph which corresponds to all pairs of values of q1 and q2 for which (2) and (3) are valid.

Let us consider the non-negativity restrictions given by (3). The values of q1 and q2 which satisfy these restrictions should fall in the first quadrant of the graph. Hence, We can ignore pairs of values of q1 and q2 which fall in other quadrants. This is indicated by arrow marks on the q1-axis (or x-axis) and q2-axis (or y-axis) in the graph shown below.

1125_graphical method.png

Let us next find the region corresponding to the values of q1 and q2 for which the first constraint

                   2q1 + q2 < 120

is satisfied. To do this, we have to first draw the line

                   2q1 + q2 = 120

For this, we need to fix two points on this line. The points that we have chosen are:

                   q1 = 0                    q2 = 120 and

                   q1 = 60                   q2 = 0

By joining these points, we get the line, and the points below the line, indicated by arrows, will satisfy the first constraint.

Other constraint equations are also drawn on the graph. The region common to all the regions identified gives the set of points for which the values of the co-ordinates q1 and q2 satisfy constraints (2) and (3). The region identified is OABCD is called the feasible region. It may be noted that all values of q1 and q2 which satisfy constraints (2) and (3), lie within the region OABCD and all points in the region OABCD will have the co-ordinates q1 and q2, which will satisfy constraints (2) and (3). Hence, an optimal solution to the problem should have co-ordinates q1 and q2 within or on the boundary of region OABCD.

Now let us search for the optimal solution.

Suppose, we are interested in finding a product mix which will give a profit of say, an arbitrarily chosen value of Rs.2,800. To get the product mix, we have to search in the region OABCD to examine whether any point gives a profit of Rs.2,800. The easiest way is to draw the straight line whose equation is

                   70q1 + 40q2 = 2,800

and examine whether it passes through any points in the region OABCD. In the graph given below, the feasible region OABCD and the above mentioned straight line are shown. We can observe that there are many points on this straight line which come under the feasible region, and each point will give the co-ordinates which refer to the production levels that yield the same profit of Rs.2,800. For example, take the two points (40,0) and (0,70) on this line. The production levels corresponding to these points are (i) 40 of type A castings and 0 of type B castings and (ii) 0 of A castings and 70 of type B castings. It can be verified that each co-ordinate gives the same profit. Thus, the straight line drawn is also the profit line.

573_graphical method1.png

Suppose we wish to increase the profit, we look for a product mix which will give a profit of, say, Rs.3,080. As done earlier, we draw the line

                   70q1 + 40q2 = 3,080

and examine whether it passes through the region OABC. This line is parallel to the first line and passes through the feasible region, thus indicating that it is possible to increase the profit to Rs.3,080. This suggests that, as we move up this line in the Northeastern direction, parallel to itself, we can obtain product mixes which will give higher and higher profits. We should move the line as far as possible without removing it completely from the region of feasible solutions as otherwise we will not find any feasible product mix which will satisfy the constraints. The optimal solution is then given by the point of final contact, which will be one of the corner points. In this case, the point is B, whose co-ordinates are (40, 40), indicating that the production level should be 40 for each of type A and B castings and this will yield a profit of

         70 x 40 + 40 x 40 = 2,800 + 1,600 = Rs.4,400


Related Discussions:- Graphical method

Calculate total amount of dividends in arrears, QTL Tech has an issue of pr...

QTL Tech has an issue of preferred shares outstanding with a $50 stated value that pays a dividend of 7.5%. There are 325,000 shares outstanding. QTL has not paid preferred share d

Accrued income, Income that is received in a fund or by company by providin...

Income that is received in a fund or by company by providing a service or selling a product, but still has to be received. Mutual funds or other pooled assets that build up income

Estimate the montly deposite, Mr. Moore will be 35 years at the end of the ...

Mr. Moore will be 35 years at the end of the month and he wishes to retire in 25 years. He plans to invest in a mutual fund earning 7.5 percent annual return compounded monthly an

Cost centre, a)   What are the pre-requisites of installation of responsibi...

a)   What are the pre-requisites of installation of responsibility accounting system? b)  Diffrence between 'cost centre' and 'profit centre'.

Find out the price of the swap from corporation's viewpoint, A company ente...

A company enters into a five-year interest rate swap along with a swap bank where it  agrees to pay the swap bank a fixed-rate of 9.75 percent yearly on a notional amount of DM15,0

Above the line deduction, Above the line deductions are certain kinds of de...

Above the line deductions are certain kinds of deductions that are deducted from your income before the adjusted gross income is computed for tax purposes. Above the line deduct

Profit maximization-objectives of a business entity, Profit maximization ...

Profit maximization Traditionally, this was considered to be the major goal of the firm. Profit maximization refers to attaining the maximum possible profits throughout the yea

#title.operating cycle., discuss the applicability of an operation cycle in...

discuss the applicability of an operation cycle in a vegetation business

Define the services that international banks provide, Briefly discuss some ...

Briefly discuss some of the services that international banks provide their customers and the market place. Answer:  International banks can be categorized by the types of servic

Steps, how control the steps

how control the steps

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd