Example of production rate, Mechanical Engineering

Example of Production Rate

The turret lathe section contains six machines, all devoted to the production of the similar part. The section operates 10 shifts/wk. The number of hours per shift averages 8.0. Average production rate of each machine is 17 unit/hr. Calculate the weekly production capacity of the turret lathe section.

Solution

Given  Number of machines n = 6

Number of shifts per week S = 10

Number of hours per shift H = 8

Production rate Rp = 17

Production capacity = n x S x H x Rp

∴ PC = 6 (10) (8.0) (17) = 8160 output unit/wk

Posted Date: 12/26/2012 8:09:52 AM | Location : United States







Related Discussions:- Example of production rate, Assignment Help, Ask Question on Example of production rate, Get Answer, Expert's Help, Example of production rate Discussions

Write discussion on Example of production rate
Your posts are moderated
Related Questions
give equivalence of screw jack and friction on an inclined plane

(a) Show that for an adiabatic process Pv r = C, holds good. (b) One Kg of a contain gas is at 0.11 KPa and 15 o C. It is compressed until its volume a 0.1m 3 . if the compress

computer aided design of piercing press tool

Distribution of shearing stresses on l--sections and miscellaneous sections

all information about lifting machine

Motion on the inclined plane when the surface is smooth: Sol:  WHEN THE SURFACE SMOOTH   The Figure given shows a body having weight W, sliding down on a smooth in

Consider a fully developed laminar flow of a fluid through a 200 m long and 4 cm diameter horizontal and circular pipe. The density and the viscosity of the fluid are 1400 kg/m 3

Flow through pipes in series and parallel

Types Of Polymerisation When some of bifunctional molecules connect in a chain structure, the reaction is termed as addition polymerisation.  However, these polymerizations do