Example of production rate, Mechanical Engineering

Example of Production Rate

The turret lathe section contains six machines, all devoted to the production of the similar part. The section operates 10 shifts/wk. The number of hours per shift averages 8.0. Average production rate of each machine is 17 unit/hr. Calculate the weekly production capacity of the turret lathe section.

Solution

Given  Number of machines n = 6

Number of shifts per week S = 10

Number of hours per shift H = 8

Production rate Rp = 17

Production capacity = n x S x H x Rp

∴ PC = 6 (10) (8.0) (17) = 8160 output unit/wk

Posted Date: 12/26/2012 8:09:52 AM | Location : United States







Related Discussions:- Example of production rate, Assignment Help, Ask Question on Example of production rate, Get Answer, Expert's Help, Example of production rate Discussions

Write discussion on Example of production rate
Your posts are moderated
Related Questions
A cart is moving along a track at a constant velocity of 5 m/s as shown. Water (? = 1000 kg/m3) issues from a nozzle at 10 m/s and is deflected through 180° by a vane on the cart.

Show that the force exerted by jet of water on a fixed semi-circular plate in the direction of jet when the jet strikes at the centre of the semi-circular plate is two times the fo

Q. What is Boiler feedwater? The boiler feedwater will be a mixture of desalinated water, treated make-up water and returned condensate, deaerated and heated, supplied by other

Calculate pressure on each side of spherical ball : Heavy spherical ball of weight W rests in V shaped trough whose sides are inclined at the angles and to the horizontal

What is the difference between von-mises and maximum principal stress? What is axisymmetric, plane stress, and plane strain modeling? What is difference between a beam, spar,

Isentropic flow through the nozzle: In an isentropic flow through the nozzle, air flows at rate of 600Kg/hr. At inlet to the nozzle, the pressure is 2Mpa and temperature is 1

INTRODUCTION: At any point of time, it may be required to disassemble the whole or any part of motorcycle. Whenever a part of motorcycle malfunctions or is damaged then it may be

Implementation of Material Requirement Planning: The total requirements for a material from an MRP schedule are given in the following table :

Workplace Operations Requiring Safety The operations performed through workers in their workplace are of dissimilar nature but they involve a number of machine, equipment and

Grinder: Grinders are used to sharpen the cutting edges of the tools. They are basically fast rotating grinding wheels carried at one or two ends of a shaft. The grinding wheel ar