Estimate the activity durations - construction management, Civil Engineering

Estimate the Activity Durations

The total labor cost for emergency bridge rehabilitation on an interstate highway is $5,716,440.  The average crew-hour cost is $15,879 for this nonstop project.  The number of work days the roadway was shut down is most nearly:

Solution:  Assigning duration of actives is the estimated or actual time that it will be required to complete it. Accordingly:

  Total labor cost ÷ crew-hour cost = total crew-hours

  $5,716,440 ÷ $15,879 = 360 crew-hours

Nonstop project constitutes work at 24-hr 7-days/week

Total crew hours ÷ 24-hrs/day = project days

360 crew-hour ÷ 24-hrs/day = 15 days

Posted Date: 5/29/2013 1:14:27 AM | Location : United States







Related Discussions:- Estimate the activity durations - construction management, Assignment Help, Ask Question on Estimate the activity durations - construction management, Get Answer, Expert's Help, Estimate the activity durations - construction management Discussions

Write discussion on Estimate the activity durations - construction management
Your posts are moderated
Related Questions
what is maximum flood level

Reinforcement of concrete in contact with internal vibrators  At the time of concreting, if internal vibrators are placed accidentally in contact with some of the reinforcemen

1. The cantilever beam-like structure  shown below is modeled  using  a 2 x 10 mesh of rectangular four-node plane stress elements of equal size. Do the following and compare with

workability agents

Explain Civil Fe Hydraulics and Hydrologic Systems When spills occur at grade on soils in areas where unconfined aquifers are present, remediation procedures to remove the poll

what is the difference between bitumin and asphalt

how to know about he sign convention for equllibrium forces

how to make plain scale

Impact Test: Resistance of stones to impact is found by conducting tests in impacting testing machine .It contain of a frame with guides in which a metal hammer weighing 13.

Maintenance of Terminal Building: All accessories such as lighting, water, sanitation, telephone and public address system should be maintained in a good condition. Disposal