Estimate the activity durations - construction management, Civil Engineering

Estimate the Activity Durations

The total labor cost for emergency bridge rehabilitation on an interstate highway is $5,716,440.  The average crew-hour cost is $15,879 for this nonstop project.  The number of work days the roadway was shut down is most nearly:

Solution:  Assigning duration of actives is the estimated or actual time that it will be required to complete it. Accordingly:

  Total labor cost ÷ crew-hour cost = total crew-hours

  $5,716,440 ÷ $15,879 = 360 crew-hours

Nonstop project constitutes work at 24-hr 7-days/week

Total crew hours ÷ 24-hrs/day = project days

360 crew-hour ÷ 24-hrs/day = 15 days

Posted Date: 5/29/2013 1:14:27 AM | Location : United States







Related Discussions:- Estimate the activity durations - construction management, Assignment Help, Ask Question on Estimate the activity durations - construction management, Get Answer, Expert's Help, Estimate the activity durations - construction management Discussions

Write discussion on Estimate the activity durations - construction management
Your posts are moderated
Related Questions
Question Have to emulsified asphalts or cutback asphalts be selected as staple coat in bituminous road works? Answer Emulsified asphalt is a postponement of asphalt

Design the 2-span continuous center T-beam, B2, for the floor syetem shown below. The girders that the beam frames into are all 24" wide. Using fc'= 5 ksi, and fy = 60 ksi. The ser

Explain the Interim inspection - underwater inspection of bridge An interim inspection is an inspection scheduled at the discretion of the engineer. An interim inspection is us


Effect of rusting on steel reinforcement Corrosion of steel reinforcement inside a concrete structure is undesirable in the subsequent ways:  (i)  Presence of rust impairs

Lock Entrance: Wet docks have lock entrances to overcome the high fluctuations in water level in the sea. Figure 7 gives a layout of a lock entrance. It consists of a lock cha

At a large port facility near New York City tractor-trailer trucks are lined-up in long queues as their drivers wait to have their containers inspected and documents processed.  As

what are lab and field test carried on soil subgrade?

Define Role of Diver in Underwater Inspection of Bridge? Diver's role is primarily to point out a potential scour problem. The diver can use one of the following equipment to m

Solve the following problems and show all steps and calculations clearly: 1. A water treatment plant uses a dual media filter. The two media used are: a) Anthracite coal with ef