ESSENTIALS OF PROJECT MANAGEMENT, Mechanical Engineering

Ask qu1. A small maintenance project consists of the following 10 jobs, whose precedence relationships are identified by their node numbers:
JOB NODE NUMBERS ESTIMATED DURATION (DAYS)
A 1,2 2
B 2,3 3
C 2,4 5
D 3,5 4
E 3,6 1
F 4,6 6
G 4,7 2
H 5,8 8
I 6,8 7
J 7,8 4

i. Draw an arrow diagram representing the project and find the critical path?
ii. Find the total slack and free slack for non-critical activities
iii. Draw the time scale network according to Earliest Start Times.
estion #Minimum 100 words accepted#
Posted Date: 10/16/2014 3:57:37 PM | Location : USA







Related Discussions:- ESSENTIALS OF PROJECT MANAGEMENT, Assignment Help, Ask Question on ESSENTIALS OF PROJECT MANAGEMENT, Get Answer, Expert's Help, ESSENTIALS OF PROJECT MANAGEMENT Discussions

Write discussion on ESSENTIALS OF PROJECT MANAGEMENT
Your posts are moderated
Related Questions
Define the Application of Abrasive Jet Cutting Machines Cleaning purpose. Cutting fine lines. Machining semiconductors. Drilling and cutting thin section of har


Discover the fixing torques set up at the ends of the shaft: A solid shaft 6.5 m long is securely fixed at each of the end. A torque of 91 Nm is applied to the shaft at a sect


what do you mean by law of belting and also explain the crowning of pulleys ?

(a) Comment on the require to idealise a body as a particles, a rigid body or a continuum. (b) What do you mean by an inertial reference ? (c) Define quantitatively a force 1

What type of low lube oil security recommended for API612 steam turbines.(Electronic/Mechanical). Please give refrences

Convert the flow-rate from Am3/h to Sm3/h Consider a compressor (model ABC-Z4).  The compressor has a suction pressure of 3 barg, and a discharge pressure of 6 barg.  The inlet

What are the advantages and disadvantages hard working over cold working