ESSENTIALS OF PROJECT MANAGEMENT, Mechanical Engineering

Ask qu1. A small maintenance project consists of the following 10 jobs, whose precedence relationships are identified by their node numbers:
JOB NODE NUMBERS ESTIMATED DURATION (DAYS)
A 1,2 2
B 2,3 3
C 2,4 5
D 3,5 4
E 3,6 1
F 4,6 6
G 4,7 2
H 5,8 8
I 6,8 7
J 7,8 4

i. Draw an arrow diagram representing the project and find the critical path?
ii. Find the total slack and free slack for non-critical activities
iii. Draw the time scale network according to Earliest Start Times.
estion #Minimum 100 words accepted#
Posted Date: 10/16/2014 3:57:37 PM | Location : USA







Related Discussions:- ESSENTIALS OF PROJECT MANAGEMENT, Assignment Help, Ask Question on ESSENTIALS OF PROJECT MANAGEMENT, Get Answer, Expert's Help, ESSENTIALS OF PROJECT MANAGEMENT Discussions

Write discussion on ESSENTIALS OF PROJECT MANAGEMENT
Your posts are moderated
Related Questions
Q. Mechanical Design Calculations? The Mechanical Design Engineer/Specialist shall be responsible for mechanical design calculations that are required to ensure that the end pr


hardness of bore well water is less than sea water .justif

Determine the width and depth of the beam: A timber beam of rectangular section is only supported over a span of 5 m. It carries an uniformly distributed load of 15 kN/m over

System of force


Example of change of enthalpy: Q 0.5kg/s of a fluid flows in steady state process. The properties of fluid at the entrance are measured as p 1 = 1.4bar, density = 2.5k


How can punching shear failure are characterised in bearing capacity? Punching Shear Failure This mode of failure is characterised by large deformations beneath the footing

Expected quarterly sales in Year 1 (vehicles) The work content of a single unit of each product in each process has been estimated at: Using MS-Excel, calculate the workloads