Determine the depth of exploration, Civil Engineering

Determine the Depth of Exploration

The depth of exploration depends on the following factors:

i) Size, type of the structure and loading intensity.

ii) Design considerations such as safety against foundation failure, seepage, earth pressure, excessive settlement.

iii) Character and sequence of sub-soil conditions.

The bore hole/boring must penetrate through all the deposits which are not suitable for foundation. In other words, the bore hole should extend upto strata, which is of adequate bearing capacity. You can use the geophysical profile to estimate the depth of boring.

In the absence of geophysical profile the depth of boring can also be estimated based on stress distribution criteria. This must include all the strata which are likely to undergo settlements due to load of the structure. This depth is called significant depth. De Beer recommends that the increase in stresses at the needed minimum depth of exploration should not exceed by 10% of the original vertical stress or less than 5% of the effective stress in the soil at this depth.

You must always keep in the mind that this significant depth will not account for coefficient of compressibility of the strata.

 

Posted Date: 9/3/2013 5:39:16 AM | Location : United States







Related Discussions:- Determine the depth of exploration, Assignment Help, Ask Question on Determine the depth of exploration, Get Answer, Expert's Help, Determine the depth of exploration Discussions

Write discussion on Determine the depth of exploration
Your posts are moderated
Related Questions

important considerations in case doors and windows


Q. Reasons for blockage in pumping concrete ? Concrete pumping is normally adopted in highly elevated locations for which access for concrete trucks is difficult. Construction

The objective of this module is:- - For the student to identify the track design issues and there relationships that will need to be considered in the development of a feasibili

A masonry retaining wall is 1.5 m wide at the top, 3.5 m wide at the base and 6 m high. It is trapezoidal in section and has a vertical face on the earth side. The backfill is leve

Ask What is the density of cement?



Q. Write short notes on Aqua Privy Latrine? There are a sort of latrines also called septic tank latrines. These are constructed over septic tanks & flushing is also provided.