Determine the depth of exploration, Civil Engineering

Determine the Depth of Exploration

The depth of exploration depends on the following factors:

i) Size, type of the structure and loading intensity.

ii) Design considerations such as safety against foundation failure, seepage, earth pressure, excessive settlement.

iii) Character and sequence of sub-soil conditions.

The bore hole/boring must penetrate through all the deposits which are not suitable for foundation. In other words, the bore hole should extend upto strata, which is of adequate bearing capacity. You can use the geophysical profile to estimate the depth of boring.

In the absence of geophysical profile the depth of boring can also be estimated based on stress distribution criteria. This must include all the strata which are likely to undergo settlements due to load of the structure. This depth is called significant depth. De Beer recommends that the increase in stresses at the needed minimum depth of exploration should not exceed by 10% of the original vertical stress or less than 5% of the effective stress in the soil at this depth.

You must always keep in the mind that this significant depth will not account for coefficient of compressibility of the strata.

 

Posted Date: 9/3/2013 5:39:16 AM | Location : United States







Related Discussions:- Determine the depth of exploration, Assignment Help, Ask Question on Determine the depth of exploration, Get Answer, Expert's Help, Determine the depth of exploration Discussions

Write discussion on Determine the depth of exploration
Your posts are moderated
Related Questions
i want to know more about civil engineering


chaining on level surface

describe in detail the uses of concrete

determine the force p if the block is move yto the right at an angle of friction on all contact points @20 degrees

Absolute is equivalent to gauge pressure plus atmospheric.

What is linear waterway?

Q. Show the Settlement due to Vibration? The foundation resting on cohesionless soil and subjected to vibrations will result in settlements of higher magnitude. In sandy soil

Maximum shear stress: The state of stress at a critical point of a strained solid is given by σ x = 70 kN/mm 2 , σ y = - 50 kN/mm 2 and τ xy = 45 kN/mm 2 . If the strength

A contractor has both a 3-cy and a 5-cy shovel in the equipment fleet. Select the minimum size shovel that will excavate 450,000 bcy of common earth in a minimum of 120 working day