Cost-reimbursable contracts , Project Management

Cost-reimbursable contracts 

In cost-reimbursable contracts you pay the contractor the costs necessarily incurred in the construction plus a fee. The latter portion viz. the fee can be fixed in a number of ways which we will discuss later in this section. The main reasons for adopting this mode of contracting are: 

  • At the time of contracting, the scope of the work is indeterminate or highly uncertain and the kind of labour, material and equipment needed are also uncertain. 
  • At the time of contracting, you are unable to finalise the plans and specifications for the project.  
  • At the time of contracting, you are not certain whether the construction project will be completed in full. 
  • Cost-reimbursable contracts offer an easy response to unexpected conditions arising during project implementation. 
  • Under this arrangement complete records of all time and materials spent by the contractor must be maintained. (These types of contracts are also called Time and Material contracts or Cost-plus contracts). Evidently the  risk of cost increase in the project depends entirely upon you. 

The most important question that should be resolved for finalising cost-reimbursable contracts is to identify the following costs: 

  • Reimbursable costs (costs that are reimbursable to contractor that is. costs that are necessarily incurred in the performance of the work). 
  • Non-reimbursable costs (costs that are not reimbursable to contractor). 
  • Costs that are included in the base figure which is agreed as the basis for determining the fee. 

Typically these costs comprise the following elements: 

  • Reimbursable costs (that is. costs that are necessarily incurred in the performance of the work), which includes: 

 

  1. Wages, payroll taxes and fringe benefits. 
  2. Cost of all materials, supplies and equipment including the costs of transportation, unloading thereof. 
  3. Payments to subcontractors. 
  4. Rental and maintenance charges for all equipment, trucks and hand tools. 
  5. Cost of salaries of all contractor?s staff stationed at the field office. 
  6. Cost of salaries of contractor?s staff utilised for expediting of supplies, supervising of transportation and so on calculated for time specifically spent on the project. 
  7. Cost of travel and travel incidentals of contractor?s staff directly incurred on the project. 
  8. Premiums of all bonds and insurances incurred by contractor for the work. 
  9. Permit fees. 
  10. Cost incurred for communication that is, telephone, electronic communication and so on and for stationery at site. 
  11. Cost of temporary site facilities like removal of debris. 
  12. Losses and expenses not compensated by insurance which result from causes other than the fault or negligence of the contractor. 

Non-reimbursable costs which includes:

  1. Salaries or other compensation for the contractor?s officers and employees while working at the contractor?s main office or branch offices. 
  2. Expenses of the contractor?s principal or branch offices other than the field office. 
  3. Any capital expenses including interest on the contractor?s capital and any additional capital required to perform the work. 
  4. All general overhead expenses.

Costs due to negligence of the contractor, subcontractors, or anyone directly employed by the contractor. While the above list is typical, there can be some variations to the list depending on the agreement between owner and contractor. But the contract should make these costs clear in order to avoid disputes.   

Posted Date: 9/27/2012 7:52:43 AM | Location : United States







Related Discussions:- Cost-reimbursable contracts , Assignment Help, Ask Question on Cost-reimbursable contracts , Get Answer, Expert's Help, Cost-reimbursable contracts Discussions

Write discussion on Cost-reimbursable contracts
Your posts are moderated
Related Questions
Give three reasons why this is necessary to plan an IS project in detail before starting work on this. Only the simplest projects that probably imply one developer working for

The Client Masterplan includes introduction, rationale, client objectives and stakeholder management. This should be a rationalisation of the requirements. Guidelines

Question 1: "HRM is regarded by some personnel managers as old wine in new bottles". (Armstrong, 1987). Discuss. Question 2: "The contribution of HR function is insig

Are the principal advantages and disadvantages of the sequential approach to system development offered through the waterfall and ‘V’ lifecycle models? The waterfall approach a

The primary benefit of implementing quality design techniques is a significant decrease in time to market. Other benefits of quality by design techniques are: 1. Faster

Specification is an important quality document for the product because it is here that quality fo the product as a whole is defined in precise technical terms. Although the use

Weightings of performance against the success criteria In any discussion on success, it is necessary that a distinction is made amid project success and the success of the proj

Scope Work breakdown structure Gantt chart Scope cchange management Project budget Project ccash flow

Flow Charts Flow chart is the most familiar tool to understand processes. It is used to identify a sequence of events in a process. Using flow charts require six deliberate act

Question: (a) Describe cost benefit analysis as used to appraise large public sector investments. (b) Compare and contrast cost benefit analysis with investment appraisal.