Cooling water supply for distillation condenser, Mechanical Engineering

Your team has been charged with creating the pumping and piping system to supply cool water to the condenser, E-310, for the newly installed distillation column T-304 running at 120 psi. The condenser will be supplied with once-through cooling water from a nearby lake, T=70°F. The condenser duty, Q, is calculated to be 0.5 MMBtu/hr. You must design a pumping and piping system to provide adequate cooling to the condenser. Below is a schematic of the relevant location of process equipment. The water will be pumped out of a lake by a pump you will design. You must determine the location the pump will be placed. The piping system you develop may be placed along preexisting pipe racks as described in the above graphic. The piping will continue to E-310 which is located at 85 ft above elevation (ground level), at the top of T-304. The water exits the condenser and is returned to the lake.

The return temperature of the water plays a critical role in determining the size of pumping and piping equipment. This is a design variable for you to decide.

Some helpful equations are:

Q= F. CP. ρ. ΔT

The cooling water will experience an estimated 5 psi pressure drop over the condenser and be returned to an underground common return which empties into the lake akin to a sewer system in the plant.

Where Q is the heat duty on the condenser and F is the volumetric flow rate, Cp is the heat capacity, is the density, and is the temperature differential of the lake water through the condenser.

The diameter of the pipe also plays a critical role in determining power needed by a pump to move liquid from one location to another. A larger diameter decreases the required pumping power, but at the cost of higher initial investment. Your job is to develop a pumping and piping system for E-310 with this optimization in mind.

The project life will be 10 years. Capital investment will be paid for over the project life in equal payments. Your goal is to minimize total yearly cost as defined by:

Deliverables:

C= Annual Electrical cost +TotalCapital/10

1. There are many different types of pumps. Justify your decision for this situation

2. Complete equipment list - From lake extraction to return of water.

3. Return temperature selection

4. Fully described optimization equation using the optimization variable pipe diameter

5. Describe any environmental or safety concerns with the system

Your report must include a description and defense of your design choices. This should include a drawing of your design, cost estimates, the methods used to obtain your design and safety concerns. The report should be no longer than 5 single spaced pages excluding tables, figures, equations, and alternate designs and should be organized as follows:

1.       Abstract - A brief summary of your conclusions

2.       Introduction - A summary of the system required and constraints

3.       Optimum Design - Drawings and written description of your piping and pumping design

4.       Discussion - Discuss and defend the design laid out. Think about each decision you made and defend it

5.       Alternate Designs - Briefly discuss any alternate designs which may have been considered and why they were not used. Do not create alternate designs for use in this section. This section is for you to be able to present material you already spent a lot of time and effort on, but for some reason scraped it.

Note: As with all open-ended problems, there is no single correct answer. Thus the problem statement may seem a bit vague. It is certainly possible that as you work on the problem, your findings will require revisions and/or clarifications to this problem statement. Be aware that you will be responsible for any revisions or clarifications made. All clarifications will be logged above this document.

Posted Date: 3/9/2013 12:43:12 AM | Location : United States







Related Discussions:- Cooling water supply for distillation condenser, Assignment Help, Ask Question on Cooling water supply for distillation condenser, Get Answer, Expert's Help, Cooling water supply for distillation condenser Discussions

Write discussion on Cooling water supply for distillation condenser
Your posts are moderated
Related Questions
Q. Show Hazard assessment of plant operation? Using the hazard assessment of each plant operation will help establish the layout or orientation of process units within the plan

Q. Describe the type of Facing and Backing sand? Facing sand. This sand is used directly next to the surface of the pattern and comes into contact with the molten metal when th


Cross Belt Drive: When shafts are rotating in the opposite direction, cross belt drive can be obtained. Figure In the diagram given to us pulley 'A' is called as

Scheduling and Sequencing: This unit begin with the basic concept and the role of scheduling in industry. Several job- sequencing rules to address the manufacturing process ar

Manufacturing DATABASE system in FMS

ROTARY CONVERTERS Historically, these type of power sources were developed first for arc welding applications and even now these types are popular. These rotary converters are of

This project involves a test of the basic idea behind the bootstrap method. Essentially you will write a program that: 1. Generates a parent population of size 100,000 whose dis

The Cu-Sb system contains 2 eutectics, 1 eutectoid, 1 peritectic and 1 peritectoid. Mark them all on the figure, write down the temperature and composition of each point, and ident

2 x 2 m square gate opens clockwise on a horizontal hinge located at point A, which is 100 mm below the centroid of the gate. The gate sits against solid rubber blocks which create