Construction activities for plant, Mechanical Engineering

Assignment Help:

Construction Activities for plant

Construction activities, such as shoring and bracing of excavations, lifting and rigging activities and scaffolding need to be considered as part of the design.

The primary hazard of trenching and excavation is employee injury from collapse. An excavation design shall include adequate sloping and benching or adequate support and protective system to protect personnel during the construction activities. Soil analysis is an important part of determining the appropriate sloping, benching and shoring. An added hazard exists if excavation extends below the groundwater table.

A number of features need to be addressed during the plant layout including crane access to equipment and drop areas, height of crane to accommodate the size and shape of items to be lifted, clearance over other facilities and sling allowance, personnel access to gantry, and size of buffers and structural steel to accommodate loadings.

Lifting of heavy equipment into place by crane may require the construction of specific foundations or lift pads. Rigging requires careful evaluation of slings for use because of the wide variety of safety factors which must be considered for each case. These factors include but are not limited to:

• Size and type of sling.

• The method of fastening.

• Sheaves, sprockets, and drums.

• Condition of equipment or material.

• Size and shape of load.

• Type of attachment.


Related Discussions:- Construction activities for plant

Safety organization, Safety Organization Each industry must have a sa...

Safety Organization Each industry must have a safety organisation along with well defined objective and well identified functions. It has been experienced that safety policie

Find out the modulus of elasticity, Find out the modulus of elasticity: ...

Find out the modulus of elasticity: A unidirectional FRP is produced with fibre volume ratio of 60%. The density of fibre is 1480 kg/m 3 and that of matrix is 1200 kg/m 3 . C

CENTRE OF GRAVITY OF WIRE, WHATIS CG OF A WIRE BENT IN THE FORM OF A QUARTE...

WHATIS CG OF A WIRE BENT IN THE FORM OF A QUARTER ELLIPSE

Hardness testing, After final PWHT, the hardness of the deposited weld meta...

After final PWHT, the hardness of the deposited weld metal and heat affected zone (HAZ) shall be examined. Hardness values shall not exceed 200 BHN. Heat treatment shall be perfo

Example of process capability, Example of Process Capability The speci...

Example of Process Capability The specifications for one characteristic of a part call for its width to be 3.000 + 0.008 centimetres. The procedure has been run under controll

Determine the resultant of the system of forces, Determine the resultant of...

Determine the resultant of the system of forces: Four forces act on a body as illustrated in Figure. Determine the resultant of the system of forces. Figure Sol

Principle of submerged arc welding, PRINCIPLE OF SUBMERGED ARC WELDING In...

PRINCIPLE OF SUBMERGED ARC WELDING In submerged arc welding, the arc zone is submerged beneath the molten flux and hence there is no visible signature of the arc. Welding current

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd