Change order management, Other Management

Change Order Management

In previous section we learnt that incentives motivate and penalties keep a check for faults that occur in a project. In this section we will understand about a change order management.

A change order is order for work that is added to or deleted from the original  scope  of  work  in  a  contract,  which  alters  the  original  contract amount and/or completion date. A contractor?s claim for such an alteration due to a work perceived by him as additional work remains as a claim until the change order is resolved. A claim is a potential source of dispute. Hence resolution of change order situations knowledgably, fairly and promptly benefits both owner and contractor.

Change  order  is  a  component  of  the  change  management  process  in contract management. The change management process should enable implementation of changes in a system in a controlled manner by following a predefined framework/model. Change order management is hence a critical aspect of any construction job.

The rights of a contractor to a change order arise from the contract. If the contractor?s claim is not consistent with the contract, it will be denied, unless you admit it by oversight.

Project construction contracts always incorporate a Changes clause which provides allows you to order extra work without invalidating the contract or make changes to the existing work by altering, adding to or deducting from the work, with the contract sum.

The reasons this change clause is needed are:

  • Impossibility of perfect drawings and specifications: A fundamental truth in the construction industry is that no design can be made perfect.
  • Impractical risk allocations: The fundamental principle of risk allocation is to assign each risk to the party who is best able to control, manage or absorb that risk, which is the way to achieve maximum efficiency and economy. When contract for construction is taken up by a general contractor, his tendency will be to shift the risks to subcontractors and so on down the line leading to improper risk allocation.
  • Contractor-suggested changes: In many project contracts, value engineering proposals from contractor should be encouraged by owner.
  • Owner-suggested changes: You may discover obstacles or possible efficiencies that require them to deviate from the original plan.

Other than the above reasons, incorrectly estimated work or failure to meet commitments can lead to claims by contractor. Examples are:

  • Unforeseen adverse site conditions or actual site conditions being more adverse than what is mentioned in the contract.
  • Failure to make the site available at the time and in the condition required by the contract.
  • Failure to grant, or delay in granting, legitimate time extensions.
  • Unreasonable or mistaken inspection.

Although you can unilaterally order that changes be made, there is a commensurate duty on you, to make adjustments in the contract sum or contract time. Hence changes provisions in contract should typically provide methods for making these adjustments.

Changes in contract sum or contract time are made on the basis of negotiations between owner and contractor. The basis can be:

  • Unit prices for specific items of work.
  • Recognised mark-ups for contractor?s work and subcontractor?s work.
Posted Date: 9/28/2012 2:48:40 AM | Location : United States







Related Discussions:- Change order management, Assignment Help, Ask Question on Change order management, Get Answer, Expert's Help, Change order management Discussions

Write discussion on Change order management
Your posts are moderated
Related Questions
PLANNING AND ORGANISATION: The major items of work are classification and cataloguing. They are of a highly  technical nature and accuracy is the very essence of all technical

Internal Form of the Catalogue: As mentioned earlier, according to the internal farm, the two major types of  library catalogues are the Dictionary Catalogue and the Classifie

U nrecognised to institutionalised The Communities of Practice have many varieties of relationships to with the  organisations which range from completely the unrecognised to

LIBRARY CATALOGUE A modern library provides a number of facilities to its readers for making use of its collection. One such facility is the catalogue of the library which f

HISTORICAL APPROACH: Meaning and Characteristics In  the following text the meaning and characters of historical approach will  be discussed.  Definition:  It is concerne

Until recently, information consolidation products (ICP) were prepared by subject specialists themselves on the basis of the documents furnished by libraries and information center

Question: (a) Change has become an inevitable feature of organisational life in today's competitive business world. Change can manifest itself in two forms. It can either simpl

Usage in the Context of Library and Information Services: In library and information science, there is, however, no need for making such distinction between data and informati

QUESTION 1 Implementation of selected strategies is a phase in the strategic management process. Discuss the key issues that need to be considered in this phase. QUESTION 2

Acquisition Sources: As mentioned earlier, supply is another basic factor. Supply means availability of periodicals / serials for acquisition. Information regarding supply can