Change Order Management

In previous section we learnt that incentives motivate and penalties keep a check for faults that occur in a project. In this section we will understand about a change order management.

A change order is order for work that is added to or deleted from the original  scope  of  work  in  a  contract,  which  alters  the  original  contract amount and/or completion date. A contractor?s claim for such an alteration due to a work perceived by him as additional work remains as a claim until the change order is resolved. A claim is a potential source of dispute. Hence resolution of change order situations knowledgably, fairly and promptly benefits both owner and contractor.

Change  order  is  a  component  of  the  change  management  process  in contract management. The change management process should enable implementation of changes in a system in a controlled manner by following a predefined framework/model. Change order management is hence a critical aspect of any construction job.

The rights of a contractor to a change order arise from the contract. If the contractor?s claim is not consistent with the contract, it will be denied, unless you admit it by oversight.

Project construction contracts always incorporate a Changes clause which provides allows you to order extra work without invalidating the contract or make changes to the existing work by altering, adding to or deducting from the work, with the contract sum.

The reasons this change clause is needed are:

  • Impossibility of perfect drawings and specifications: A fundamental truth in the construction industry is that no design can be made perfect.
  • Impractical risk allocations: The fundamental principle of risk allocation is to assign each risk to the party who is best able to control, manage or absorb that risk, which is the way to achieve maximum efficiency and economy. When contract for construction is taken up by a general contractor, his tendency will be to shift the risks to subcontractors and so on down the line leading to improper risk allocation.
  • Contractor-suggested changes: In many project contracts, value engineering proposals from contractor should be encouraged by owner.
  • Owner-suggested changes: You may discover obstacles or possible efficiencies that require them to deviate from the original plan.

Other than the above reasons, incorrectly estimated work or failure to meet commitments can lead to claims by contractor. Examples are:

  • Unforeseen adverse site conditions or actual site conditions being more adverse than what is mentioned in the contract.
  • Failure to make the site available at the time and in the condition required by the contract.
  • Failure to grant, or delay in granting, legitimate time extensions.
  • Unreasonable or mistaken inspection.

Although you can unilaterally order that changes be made, there is a commensurate duty on you, to make adjustments in the contract sum or contract time. Hence changes provisions in contract should typically provide methods for making these adjustments.

Changes in contract sum or contract time are made on the basis of negotiations between owner and contractor. The basis can be:

  • Unit prices for specific items of work.
  • Recognised mark-ups for contractor?s work and subcontractor?s work.

Related Discussions:- Change order management

Tools and techniques used for quality planning, T ools and techniques used...

T ools and techniques used for quality planning Let us now see some of the tools and techniques used for quality planning. They are: C ost /benefit analysis: This is an

Describe talent management system, Problem 1: What is the importance of...

Problem 1: What is the importance of talent management? Describe Talent management Importance of Talent management Problem 2: Describe the five stage approa

Investment anlysis mangement, define,fuctions, principals, and introduction...

define,fuctions, principals, and introduction,how to speculation

Physical mobilisation, The areas to be considered while monitoring and cont...

The areas to be considered while monitoring and controlling a contract are wide spread. They are: P h y sical mobilisation: In this stage, the contractor gathers people, m

History of project management, H i story of project management While ...

H i story of project management While quality management was developing, around the same time a number of events led to the need for better project management. In the 1950?s

Methods of stock verification , Methods Following is a brief descrip...

Methods Following is a brief description of the prevalent methods of stock taking.  Stock Verification by Accession Numbers:  The  accession numbers of the books from t

Library organisational structure -library management, LIBRARY ORGANISATION...

LIBRARY ORGANISATIONAL  STRUCTURE   OBJECTIVES  We have learnt in Unit 1 that an organisation has to be structured in order to achieve its goals and objectives. In this

Explain the philosophy behind quality management system, Question 1: (a...

Question 1: (a) Explain the basic philosophy behind quality management systems such as those specified in ISO 9000:2000 series. (b) Discuss how an effective quality manageme

What is the importance of technology diffusion, Question 1 Write a short n...

Question 1 Write a short note on technology strategy. Describe in detail about the innovation management Question 2 What is the importance of technology diffusion? What are t

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd