Change order management, Other Management

Change Order Management

In previous section we learnt that incentives motivate and penalties keep a check for faults that occur in a project. In this section we will understand about a change order management.

A change order is order for work that is added to or deleted from the original  scope  of  work  in  a  contract,  which  alters  the  original  contract amount and/or completion date. A contractor?s claim for such an alteration due to a work perceived by him as additional work remains as a claim until the change order is resolved. A claim is a potential source of dispute. Hence resolution of change order situations knowledgably, fairly and promptly benefits both owner and contractor.

Change  order  is  a  component  of  the  change  management  process  in contract management. The change management process should enable implementation of changes in a system in a controlled manner by following a predefined framework/model. Change order management is hence a critical aspect of any construction job.

The rights of a contractor to a change order arise from the contract. If the contractor?s claim is not consistent with the contract, it will be denied, unless you admit it by oversight.

Project construction contracts always incorporate a Changes clause which provides allows you to order extra work without invalidating the contract or make changes to the existing work by altering, adding to or deducting from the work, with the contract sum.

The reasons this change clause is needed are:

  • Impossibility of perfect drawings and specifications: A fundamental truth in the construction industry is that no design can be made perfect.
  • Impractical risk allocations: The fundamental principle of risk allocation is to assign each risk to the party who is best able to control, manage or absorb that risk, which is the way to achieve maximum efficiency and economy. When contract for construction is taken up by a general contractor, his tendency will be to shift the risks to subcontractors and so on down the line leading to improper risk allocation.
  • Contractor-suggested changes: In many project contracts, value engineering proposals from contractor should be encouraged by owner.
  • Owner-suggested changes: You may discover obstacles or possible efficiencies that require them to deviate from the original plan.

Other than the above reasons, incorrectly estimated work or failure to meet commitments can lead to claims by contractor. Examples are:

  • Unforeseen adverse site conditions or actual site conditions being more adverse than what is mentioned in the contract.
  • Failure to make the site available at the time and in the condition required by the contract.
  • Failure to grant, or delay in granting, legitimate time extensions.
  • Unreasonable or mistaken inspection.

Although you can unilaterally order that changes be made, there is a commensurate duty on you, to make adjustments in the contract sum or contract time. Hence changes provisions in contract should typically provide methods for making these adjustments.

Changes in contract sum or contract time are made on the basis of negotiations between owner and contractor. The basis can be:

  • Unit prices for specific items of work.
  • Recognised mark-ups for contractor?s work and subcontractor?s work.
Posted Date: 9/28/2012 2:48:40 AM | Location : United States

Related Discussions:- Change order management, Assignment Help, Ask Question on Change order management, Get Answer, Expert's Help, Change order management Discussions

Write discussion on Change order management
Your posts are moderated
Related Questions
Information Services: Some of the significant information services which have been evolved as a result of developments in communications are: electronic delivery of documents,

Cataloguing-in-Publication (CIP): Centralised cataloguing led to the logical step of publishing bibliographic entries of documents in the publication itself, on the reverse si

The purpose of this assignment is to develop learners' ability to relate the current relevant principles, concepts and theories of compensation management with their professional p

Approach of Readers for Documents: As stated earlier, documents can be arranged in libraries on the basis of the colour of the binding, the size, the language, the year of pub

QUESTION 1 Negotiators are likely to make systematic errors while processing information. Discuss the cognitive biases that are likely to hold back the performance of negotiato

Question 1 What do you mean by barriers of communication? Explain different types of barriers to communication 2 Explain the different types of listening 3 Discuss the SQ

Non Probability Sampling: Convenient sampling or accidental sampling entails the use of the most conveniently available people  as  subjects  in  the  study. Quota sampling ar

PROBLEMS OF DDS AND ROLE OF INTERNATION ORGANISATION: Copyright issues, non-availability of publications and restrictions imposed on the storage and delivery of documents elec

Factors Driving Contracting  In this section let us try to analyse the factors which drive contracting decisions. Here, the buy mode is referred as contracting, subcontracting