Calculate the invert elevation of the sewer pipe, Civil Engineering

Assignment Help:

1. The center line elevation of the proposed roadway at station is 345+25.50 is 327.36-ft.   The existing ground top of cut elevation (ft) is most nearly:

2. A design engineer commissioned a test pit to determine the top of pipe elevation for a sewer extension project.  The existing sewer pipe is an 8-ft o.d. reinforced concrete pipe with wall thickness 10-in.  A back sight to a local benchmark with an established elevation of 45.66-ft is obtained with a level and a rod reading of 4.91-ft.

 A foresight is taken to a rod resting on the top of pipe with a reading of 12.43-ft.   

Calculate The invert elevation (ft) of the sewer pipe.


Related Discussions:- Calculate the invert elevation of the sewer pipe

Explain the soil texture and soil structure, (a) Explain the 'Soil Texture'...

(a) Explain the 'Soil Texture' and 'Soil structure'. What are the various terms used to explain the above properties of the soil? (b) A clay sample having natural moisture conte

What is the density index of the natural soil, A sand at a borrow pit is de...

A sand at a borrow pit is determined to have an  in-situ dry unit weight of 18.4 kN/m 3 . Laboratory tests indicate the maximum and  minimum unit weight values of 19.6 kN/m 3 and

Analyse the state of stress, Analyse the state of stress: For the cros...

Analyse the state of stress: For the cross-section shown in above figure, let us take b = 100 mm, d = 300 mm and M = 9 × 10 7 N mm and Q = 18 × 10 4 N and analyse the state

Dissimilarities between pipe culverts and box culverts?, Question What are ...

Question What are main dissimilarities in applications between pipe culverts and box culverts ? Answer Essentially, culvert resources covered hydraulic structure that conveys fl

Two layered spatial structures, Classification of the damage according to t...

Classification of the damage according to the type of structures   The level of damage in spatial trusses has also been classified into three different levels based on the t

Transportation engineering, what is difference between stopping sight dista...

what is difference between stopping sight distance and overtaking sight distance

Explain the coefficient of permeability, A sand deposit of 12 m thick overl...

A sand deposit of 12 m thick overlies a clay layer. The water table is 3 m below the ground surface. In a field permeability pump-out test, the water is pumped out at a rate of 540

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd