Calculate the amount of concrete - construction management, Civil Engineering

Assignment Help:

An electrical contractor is preparing to place the duct bank concrete encasement for the high voltage feeders between manhole # 11 and # 12, total distance is 323-ft. The duct bank is 2-ft x 3-ft and holds nine 4.5-in Schedule 80 PVC conduits. The amount of concrete to be ordered is most nearly: 

547_Calculate the Amount of Concrete.png

Solution:

Nominal 4-in Schedule 80 PVC pipe is 4.5-in O.D. 

Total Volume = 2' x 3' x 323' = 1938-ft3 / 27-ft3/CY = 71.77-yd3

 Total Deduct = 9 x (π ((4.5"/12")/ft)2)/4 x 323' = 321-ft3 / 27-ft3/CY = 11.89-yd3

Total Concrete = 71.77-yd3 - 11.89-yd3 = 59.88-yds3

 


Related Discussions:- Calculate the amount of concrete - construction management

The ferromagnetic materials loos property at , The ferromagnetic materials ...

The ferromagnetic materials loos property at which point? Answer: At Curie point it loos property

Explain the process of directed track maintenance, Q. Explain the process o...

Q. Explain the process of Directed Track Maintenance? DTM is a method to maintain the track is directed every day and not as a prescribed routine. DTM essentially consists of n

Purpose of dowel bars in elastomeric bearing, Q. Purpose of dowel bars in e...

Q. Purpose of dowel bars in elastomeric bearing? Elastomeric bearing is generallycategorized into two types: free andfixed. For fixed types bridge deck is permitted only to rot

Explain the toxic characteristics - hazardous waste, Explain the Toxic Char...

Explain the Toxic Characteristics - Hazardous Waste - From the results of either  - Extraction Procedure(EP) toxicity (prior to March 1990) or Toxicity Characteristic Leachi

Reinforcement in thrust blocks, Reinforcement in thrust blocks In gene...

Reinforcement in thrust blocks In general situation, reinforcement isn't essential for thrust blocks in pressurized pipelines. Though certain amount of reinforcement hasto be

Transportatoin engineening, explain the construction while aligning roads o...

explain the construction while aligning roads on hilly areas

Hydraulics and Hydrology , A flow rate of 200 gpm of oil with u=1.5 x 10-3 ...

A flow rate of 200 gpm of oil with u=1.5 x 10-3 lb-sec/ft2 and p=1.7 slug/ft3 occurs in a 4-in pipe. Determine the Reynolds number. Classify the flow as laminar or turbulent. What

Sucker deck principle for changeable depth bridge decks, Question What is t...

Question What is the sucker deck principle for changeable depth bridge decks ? Answer For a variable depth bridge deck, depth of continuous multi-span bridge deck is greate

#title, define distribution factor and shape factor

define distribution factor and shape factor

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd