Calculate the amount of concrete - construction management, Civil Engineering

Assignment Help:

An electrical contractor is preparing to place the duct bank concrete encasement for the high voltage feeders between manhole # 11 and # 12, total distance is 323-ft. The duct bank is 2-ft x 3-ft and holds nine 4.5-in Schedule 80 PVC conduits. The amount of concrete to be ordered is most nearly: 

547_Calculate the Amount of Concrete.png

Solution:

Nominal 4-in Schedule 80 PVC pipe is 4.5-in O.D. 

Total Volume = 2' x 3' x 323' = 1938-ft3 / 27-ft3/CY = 71.77-yd3

 Total Deduct = 9 x (π ((4.5"/12")/ft)2)/4 x 323' = 321-ft3 / 27-ft3/CY = 11.89-yd3

Total Concrete = 71.77-yd3 - 11.89-yd3 = 59.88-yds3

 


Related Discussions:- Calculate the amount of concrete - construction management

Define the term - permanent load, Define the term - permanent load Wher...

Define the term - permanent load Where the permanent load is less than or equal to 25% of the design imposed load, deflections may be calculated using any elastic method. When

Classification of timber based on modulus of elasticity, Classification Bas...

Classification Based on Modulus of Elasticity: Young's modulus is resolute by conducting bending test. On this basis timber is classified as following: Group A: E = 12.5 kN

Show the stresses during pile driving, Q. Show the Stresses during pile dri...

Q. Show the Stresses during pile driving? Stresses during pile driving In pile driving operation, proper selection of piling hammers is necessary to prevent the damage of

Fly levelling, we are given a project on field.i''d like to know about how...

we are given a project on field.i''d like to know about how to start n proceed vd fly levelling in the field

Draw the shape of the pressure line, Draw the shape of the Pressure line. ...

Draw the shape of the Pressure line. Solution The locations of resultant force at sections A-A, B-B  and C-C have already been determined. Joining these locations, we can dr

Delay of bituminous laying on top of sub-base, Question In case if ther...

Question In case if there is a delay of bituminous laying on top of sub-base, have to tack coat be applied on the top surface of sub-base? Answer When there is a d

Define sample collection - clean water act, Define Sample Collection - Clea...

Define Sample Collection - Clean Water Act? The collection of the sample is able to have significant effects on the complete analytical process. Additionally, to make sure some

How to design banks, Q. How to design banks? When approach banks are of...

Q. How to design banks? When approach banks are of medium height upto 3 m, the material may be homogeneous. For bigger heights zoned section with impervious core and pervious o

Compass surveying, Compass Surveying: You have studied about the compa...

Compass Surveying: You have studied about the compass and its use for bearings of measuring survey lines. The angular measurements are carried out with prismatic compass that

Determine the cubic yard in the ground, An earthwork contractor encountered...

An earthwork contractor encountered a location within the borrow area where the geological conditions changed.  Instead of encountering 100 cubic yards of wet clay, the contractor

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd