Analysis assumptions explicitly, Supply Chain Management

Assignment Help:

Steve Rothel was purchasing manager for the mid-west division of the Terpend Corporation. Shortly before his company was to install an exhaust system in a new construction project, Steve was asked to compare fabricating the pipe with purchasing the pipe from an outside source.

Terpend Corporation, a mechanical and sheet metal contract, was founded over 50 years ago. Although it had a number of branches in North America, the majority of its metal fabrication work was performed in its Midwest facility. The company mission stressed quality workmanship, competitive pricing, and timely performance.

A LABORATORY EXHAUST SYSTEM

Terpend recently was awarded the bid to provide the HVAC system in a corporate headquarters building that housed a research laboratory. This was a complex project with many nonstandard features due to the specialized use of the building.

The system included a need for over 6500 feet of 10-inch diameter, 16-gauge stainless steel pipe. This piping would be used for venting the laboratory exhaust. When the cost estimation department at Terpend prepared the original bid, they had planned to fabricate this pipe at their Midwest facility.

A REQUEST FOR COST REDUCTION

As the project got underway, the VP of Operations asked Steve Rothel "if it would be possible to provide the stainless steel pipe at a lower cost than the original estimate." Steve knew, of course, that any reduction in cost must not come at a sacrifice of quality. Because of toxins that would be present in the laboratory exhaust, it was critical that his system be absolutely leak proof. Every pipe run would be individually tested to insure integrity. If leaks were uncovered in the welds, it would require a time-consuming effort to reweld the joints on-site.

Steve realized that there were two approaches to providing the pipe. Terpend could proceed as planned and fabricate the pipe in-house, using the lowest-cost, acceptable quality steel available on the market. The second possibility would be to find a supplier who could provide the pipe already formed at a better cost.

THE PURCHASE OPTION

Steve first explored the purchase option. He did a thorough search of the market, and found that most suppliers were asking from 23 to 28 dollars per linear foot (delivered) for 10-inch-diameter, 16-gauge stainless steel pipe. He was pleasantly surprised, however, to find a supplier who would provide the pipe for $18.10 per linear foot. These suppliers provided the pipe in 20-foot sections and guaranteed the pipe to be sound (no leaks). In addition, their pipe was "perfectly" true (round), a trait that Terpend's current equipment could not always provide. This feature would reduce the time needed to make connections between sections of pipe and reduce the likelihood of bad weld joints.

Although this option sounded very attractive, Steve, a veteran in the purchasing area with 14 years of experience, knew he would have to subject his options to a thorough analysis to ensure a wise decision.

THE MAKE OPTION

Steve had access to the data necessary for manufacturing cost estimating. He knew that the process of making pipe required two steps. First, a flat sheet of steel is formed into a cylinder through the process of "rolling." Then the seam is joined in a welding process. For a 10-inch-diameter pipe of 16-gauge steel, it takes about six minutes per piece to roll, including loading and unloading the part. The equipment Terpend had available for this process could roll lengths up to eight feet. The welding process was estimated to take ten minutes for an eight-foot section. The figure the company used for cost estimating purposes for hourly labor rate was $32.60 per hour. An overhead charge of 40 percent was added to the variable costs.

Stainless steel sheets were available in 36-inch, 48-inch, and 60-inch widths at any length up to 10 feet, with the best price being $1.80 per pound. A square foot of 16-gauge steel weighs two and one-half pounds. The welding process required welding wire and welding gas. Welding wire cost around $5.20 per pound and .03 pounds were needed per foot of weld. Welding gas cost around 25 cents per eight-foot seam.

Many of the lengths of pipe needed in the project were longer than eight feet. Thus, Steve thought it necessary to include the cost of an extra joint (which, for example, would make two eight-foot lengths into one sixteen-foot length) in the "make in-house" alternative. Such a joint required welding around the diameter of the pipe, a process that, with setup, would take around 18 minutes per joint.

THE DECISION

Steve wondered which option would be best. Should Steve recommend purchasing the pipe or making it?

General Instructions

  • Write a 2-paged maximum, double-spaced, 12-point font memorandum outlining your recommendation. All computations should be included in the appendix, as well as assumptions that you make.
  • Bullet form responses are acceptable as long as your thoughts are complete and, again, ensure that your assignment is of high quality - that is, free of spelling and grammatical errors.

Related Discussions:- Analysis assumptions explicitly

Case1, ATo: You From: Danny Wilco Subject: Re: Ordering product for EBB...

ATo: You From: Danny Wilco Subject: Re: Ordering product for EBBD from the Kentucky Hooch and Beer Company Now that you have become familiar with EBBD and how we do things her

Inspection accuracy, I nspection Accuracy: Project management status r...

I nspection Accuracy: Project management status report is provided in a particular way. As an a example, consider the criteria for doctor to monitor health , he or she checks

Supply chain and sourcing management, The purpose of this project is to cri...

The purpose of this project is to critically analyze one major aspect of the supply chain of a specific company, preferably your own company.  You may choose to examine: Upst

Analytics Exercise: Forecasting Supply Chain Demand—Starbuck, 1 Consider us...

1 Consider using a simple moving average model. Experiment with models using five weeks’ and three weeks’ past data. The past data in each region are given below (week 21 is the we

The expected profit for blockbuster, A  movie studio sells  the latest movi...

A  movie studio sells  the latest movie on DVD to Blockbuster at $10 per DVD.  The marginal production cost for the movie studio is $1 per DVD.  Blockbuster prices each DVD at $20

Category Management, Executive summery to write an assignment about Categor...

Executive summery to write an assignment about Category Management

Beoing, developing a brief synopsis outlining the business and capitalisati...

developing a brief synopsis outlining the business and capitalisation strategies of Boeing and Airbus

Sensitivity analysis, If I follow your recommended approach to managing my ...

If I follow your recommended approach to managing my farm so as to maximize my operating income next month, how much will I earn from selling the 100 hogs?” asks Igor. “How many ho

Resources management, The resources such as equipment and human resources s...

The resources such as equipment and human resources should be effectively managed. To facilitate effective management of equipment resources on line records of equipment location a

Principles of demand and supply, Critically summarize the article, "Ethical...

Critically summarize the article, "Ethical Dilemmas in Forecasting for Public Policy" by Martin Wachs in approximately 800 words. Carefully explain how the author explores the nat

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd