Which testing company should be picked if the project manage

Assignment Help Project Management
Reference no: EM13774264

A Project Manager wants to pick the most efficient vendor to test a new prototype. He has previous experience with 3 testing companies. Prototype testing is a highly variable activity as shown in the table below. (HINT: For example, Company X completes testing in 40 hours in 60% of cases while it takes 90 hours in the remaining 40% of tests).


Company Probability Hours Required Cost / Hour 
X 60% 40 $12 
40% 90 
Y 10% 10 $11 
20% 20 
30% 60 
40% 100 
Z 50% 25 $10 
40% 90 
10% 200 

a. Which testing company should be picked if the Project Manager is primarily interested in completing the task in the shortest time?

b. Which testing company should be picked if the Project Manager is primarily concerned with completing the task for the lowest cost? 

Reference no: EM13774264

Questions Cloud

For any given level of output : For any given level of output:
A goatherd has the cost function : A goatherd has the cost function c(y) = 2y2, where y is the number of tubs of goat cheese she makes per month. She faces a competitive market for goat cheese,with a price of $40 a tub. How many tubs should she produce per month?
Burning the coke deposited on the catalyst particles : Burning the coke deposited on the catalyst particles generates all the heat necessary for catalytic cracking. Therefore, the coke burning rate is a critical parameter to control the rate of cracking. The composition of dry flue gas from the regenerat..
Suppose that the equilibrium nominal exchange rate : Suppose that the equilibrium nominal exchange rate is 130 Japanese yen to the U.S. dollar. If the Federal Reserve wishes to maintain an exchange rate of 140 Japanese yen to the U.S. dollar, it must meet the private excess ________ dollars in the fore..
Which testing company should be picked if the project manage : A Project Manager wants to pick the most efficient vendor to test a new prototype. He has previous experience with 3 testing companies. Prototype testing is a highly variable activity as shown in the table below. (HINT: For example, Company X complet..
Foreign-exchange markets and buys foreign currencies : If a central bank intervenes in the foreign-exchange markets and buys foreign currencies:
Fixed exchange rate and unrestricted capital flows : Suppose that a country has a fixed exchange rate and unrestricted (financial) capital flows. Which of the following would the country NOT experience?
Makes this event pareto optimal : Harry values a new jacket at $100 and buys it from Jenny at $80 (costing her $70 to produce it). Jim then offers Harry the same jacket at $60. Harry buys the jacket from Jim, and stops buying it from Jenny. Which of the following makes this event Par..
About a lingering recession : In 1992, thirst Bush administration was worried about a lingering recession. The administration announced that households would receive a reduction in their taxes for the year 1992. However, this was not accompanied by a reduction in tax rates, and t..

Reviews

Write a Review

Project Management Questions & Answers

  Characteristics of an effective project manager

Out of the eight traits associated with being an effective project manager, choose three that you possess and how do these traits contribute to effectively managing the execution of a project

  Project management-schedule, budget, cost estimation

Prepare a project schedule in Microsoft Project 2007 and explain the rationale behind time and cost estimation methods and why you would chose one method over another

  A crisis by the obama administration

Handling a crisis by the Obama administration - During a recent visit to Colombia, several members of the Secret Service apparently engaged in various forms of misconduct.

  Developing a cost analysis of items of library project

Develop a cost analysis of the above items relating to the library project so we have hard numbers to work with and have a monetary value for reporting and audit purposes.

  Issues of the treasury department

Due to these issues the Treasury Department are not paying incentive payments to these banks.

  Establishment of customer service department

Establishment of customer service department to address client's issues and requirements and conducting daily meeting for particular projects to review the progress of the project and to open the floor for new idea and suggestions.

  Project management and riskcomment on belowrisk management

project management and riskcomment on below.risk management is a major component of successful project management. from

  Salvage value of a projectgrant publishing just undertook a

salvage value of a projectgrant publishing just undertook a project that required a 340000 investment in nowc which

  Project management - multitasking

Multitasking has become the norm in our everyday society and why is it important for a project manager to be aware of multitasking during a project?

  Attributes of high-performing project teams

What would you consider the attributes of high-performing project teams?

  Calculate the return on equity

Determine whether a steel company or a retail food chain would have a greater business risk and calculate the return on equity (ROE) for 2010 and 2014, using all of the five components.

  Task 1evaluate the use of three different process planning

task 1evaluate the use of three different process planning techniquesselect and assess the use of a capacity assessment

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd