What is the critical path and expected completion time

Assignment Help Operation Management
Reference no: EM13225773

Question 1

A member of a project team that is implementing a new credit card payment process at a bank has direct responsibility to do all of the following EXCEPT:

be sensitive to conflicts between other team members and help resolve them.

ensure that the project has appropriate resources for the job to be completed.

help solve project problems that spill over into areas outside their expertise.

be called upon to share their expertise in credit card payment processes.

Question 2

Mike Multitask has three projects (A, B, and C) that are each four days long. Mike's supervisor suggests that he work first on project A, finish it, then work on project B until it is finished, and then on project C. Mike boldly declares, "My name isn't Multitask for nothing," so he decides to spend one day working on project A, one on B, one on C, then back to project A, and so on. There is no additional start up or shut down time required by splitting the projects this way. What is the difference in average completion time for all three projects when they are managed Mike's way when compared with his supervisor's suggestion?

There is no difference.

Mike's way is 3 days shorter.

Mike's way is 3 days longer.

Mike's way is 9 days longer.

Question 3

Slack time is routinely lost in a network:

at the point where multiple paths exit a common node.

at the point where multiple paths enter a common node.

at the point where the longest activity begins.

at the point where the shortest activity begins.

Question 4

Following are four sets of most optimistic, most likely, and most pessimistic times (in weeks) for an activity. Which one of the four sets will have a mean estimated time equal to the most likely time?

1, 9, 9

1, 5, 9

1, 1, 9

1, 5, 5

Question 5

You are responsible for managing a project with the following activities (times are given in days).

Activity      Expected Time    Immediate Predecessor(s)

A                 3                            ---

B                 6                            ---

C                 2                            ---

D                 5                             A

E                  2                            C

F                   7                            A

G                   4                         B, D, E

what is the critical path and expected completion time for this project?

A - F ; 12 days

A-D-G; 12 Days

B-G; 10 days

C, E, G; 10 days

Question 6

Assuming a beta distribution is being used, if the most pessimistic time for an activity increases by six weeks, what will happen to the expected time for that activity?


It will increase by one week.

It will decrease by one week.

It will increase by six weeks.

It will remain the same.

Question 7

If the sum of the variances on the critical path (and all other network paths) is equal to zero, what is the probability that the project will be completed by its earliest expected completion date?

50 percent

95 percent

100 percent

It cannot be determined.

Question 8

A project is currently scheduled to be finished on its normal earliest completion date. The project manager has the opportunity to earn a bonus if the project can be completed three weeks ahead of schedule. The increase in project direct costs related to crashing activities would be $40,000. Also, project indirect costs are $15,000 per week. What is the smallest bonus that the project manager should accept if he or she wants to avoid increasing overall project costs?

Less than or equal to $5,000

Greater than $5000 but less than or equal to $10,000

Greater than $10,000 but less than or equal to $15,000

Greater than $15,000

Question 9

You are given the following information about activity B:
Normal time = 9 weeks
Crash time = 5 weeks
Cost to crash per week = $2000
Crash cost = $41,000

What will it cost to complete activity B in 6 weeks?

Less than or equal to $34,000

Greater than $34,000 but less than or equal to $36,000

Greater than $36,000 but less than or equal to $38,000

Greater than $38,000

Question 10

You are given the following information about activity F:
Normal time = 16 weeks
Crash time = 10 weeks
Crash cost = $45,000
Cost to crash per week = $2,000

What is the normal cost for activity F?

Greater than or equat to $55,000

Less than $55,000 but greater than or equal to $47,000

Less than $47,000 but greater than or equal to $40,000

Less than $40,000

Reference no: EM13225773

Questions Cloud

The firm instead rents saucepans every period : Consider the pricing problem of Alcoa's cookware division. Suppose that the world last for only two periods, period 1 and period 2. A saucepan last two periods, so that a saucepan that is bought in period 1 can also be used in period 2. Consumers val..
What might happen with business across state lines : Also consider what might happen if there were no UCC in the United States. What might happen with business across state lines?
How did multitechs organization work : How did Multitech's organization work? How does he keep control?
What winding ratio should the transformer have : A 12V-DC power supply that gets it's power from the 110V (RMS) wall outlet needs a transformer as a first step in generating its output. The rectification and regulation stage of the power supply needs an input voltage of 15V (peak)
What is the critical path and expected completion time : What is the difference in average completion time for all three projects when they are managed Mike's way when compared with his supervisor's suggestion and what is the critical path and expected completion time for this project?
Determine the concentration of donor impurity atoms : A silicon sample at T = 300 K contains an acceptor impurity concentration of \(N_{A}\) = 1016 cm-3. Determine the concentration of donor impurity atoms that must be added so that the silicon is n-type and the Fermi energy is 0.20 eV
Define electrons in the new molecular orbitals : The four molecular p orbitals of the four carbon atoms can be lined up parallel in order to create four new molecular orbitals. The electrons in the new molecular orbitals benefit because they are not confined to just one atom.
How would you try to get individual managers : Assume for a moment that you are the HR Manager for a medium size company. How would you try to get individual managers to be more aware of the legal requirements of staffing systems and to take steps to ensure that they themselves engage in legal..
Allied health professional working with an endocrinologist : You are an allied health professional working with an endocrinologist. You have been working with the patient and need to update the doctor on the reason for the patient's visit. Begin describing the patient's concerns.

Reviews

Write a Review

Operation Management Questions & Answers

  Problem - more process analysis

What tasks should be assigned to each worker in order to maximize the capacity of the process and what is the resulting process capacity in toothbrushes per hour?

  How long is the line

How long is the line, and how much time do students spend waiting, on average?

  How an efficient supply chain can result in increased

how does Dell describe how an efficient supply chain can result in increased competitive advantage for this company.

  How do the language differences contribute to the challenges

In what ways would prejudice and stereotypes make it more difficult for the supervisors in a business to improve relations with employees?How do the language differences contribute to the challenges.

  Best practice for conducting an earned value

Determine the best practice for conducting an earned value analysis for the project in question. Provide a rationale for your determination and one (1) specific example which illustrates the significant ways in which the best practice in question wou..

  Do you think this criticism of organization behaviour fair

The subject of organization behaviour is sometimes being criticized as being only common sense, when we would rarely hear such a criticism on subject such as statistics. Do you think this criticism of organization behaviour is fair.

  Illustrate what types of organizations might it also work

Do you think arrangement would work for or types of organizations. Explain why or explain why not. Illustrate what types of organizations might it also work for.

  Once a company has diversified into a collection of related

Once a company has diversified into a collection of related or unrelated businesses and concludes that some strategy adjustments are needed

  What is the average number of customers in the system

What is the average waiting time in line? (Do not round intermediate calculations. Round your answer to 3 decimal places.) Average waiting time minutes.

  Factors that motivate company to set up foreign operation

What are the positive and negative impact of tariffs. Give a specific example of each. What are at least three factors that would motivate a company to set up a foreign operation.

  Illustrate what are the support also resources required

Illustrate what are the support also resources required from senior management to implement marketing plan.

  Illustrate do data on employee injuries-incidents turnover

Illustrate what do data on employee injuries, incidents, absences, also turnover suggest to you. Is there reason for concern about company's direction.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd