Statements regarding project crashing

Assignment Help Advanced Statistics
Reference no: EM13228518

Question 1

A GANTT chart represents mainly
Answer
an immediate identification of predecessor task.
a record-keeping device used in scheduling activities.
a general identifier. the number of workers directly involved in the project.
 
Question 2

A PERT/CPM activity has an optimistic time estimate of 3 days, a most likely time estimate of 8 days, and a pessimistic time estimate of 10 days. The expected time (in days) of this activity is:
Answer
7.0
7.5
8.0
8.5
 
Question 3

A PERT/CPM activity has an optimistic time estimate of 4 days, a most likely time estimate of 6 days, and a pessimistic time estimate of 10 days. The standard deviation of this activity is:
Answer
7/6
1/3
2/3
1.0
 
Question 4

A list of the tasks, broken down into modules, components, and individual tasks, is called a
Answer
work breakdown structure (WBS).
PERT.
planning matrix.
critical path.
 
Question 5

A work breakdown structure breaks down a project into
Answer
weeks.
areas.
arcs.
modules.
 
Question 6

Consider the following project.

 


What is the critical path?
Answer
ACFG
ADFG
BEG
ACDFG
 
Question 7

Consider the following project.

 

What is the minimum possible time for completing this project?
Answer
15 days
16 days
18 days
20 days
 
Question 8

Consider the following project.


Compute the slack time for activity C.
Answer
0
4
2
3
 
Question 9

Consider the following project.


What is the latest possible time that Activity E can be started without delaying the completion of the project?
Answer
8
3
7
9
 
Question 10

Consider the following project.


What is the latest time that activity B can start without delaying the project?
Answer
0
8
4
7
 
Question 11

Consider the following project.


What is the latest time that activity B can finish without delaying any other activities?
Answer
0
8
9
4
 
Question 12

Consider the following project.

Determine the critical path.
Answer
ACEH
BCEH
BDFH
BDGH
 
Question 13

Consider the following project.


Determine the estimated completion time of the project.
Answer
23 days
22 days
25 days
20 days
 
Question 14

Consider the following project.

 

Determine the slack for activity D.
Answer
2 days
4 days
6 days
5 days
 
Question 15

Consider the following project.


Determine the slack for activity F.
Answer
2 days
3 days
4 days
5 days
 
Question 16

Consider the following project.


How much can activity F be delayed without delaying the project completion?
Answer
1 day
2 days
3 days
4 days
 
Question 17

Elements of project planning include
Answer
defining project objectives.
identifying activities to crash.
calculating expected times and standard deviations.
conducting a "lessons learned" session.
 
Question 18

If an activity cannot be delayed without affecting the entire project, then it is a ________ activity.
Answer
completed
critical
crashed
normal
 
Question 19

If t is the expected completion time for a given activity, then:
Answer
LF = LS - t
EF = ES - t
EF = ES + t
EF = LS - t
 
Question 20

In a CPM/PERT network the critical path is the
Answer
lowest path through the network.
highest path through the network.
shortest path through the network.
longest path through the network.
 
Question 21

Joe used a project management software package and has determined the following results for a given project:

What is the probability of completing the project within 20 days?
Answer
0.3849
0.8849
0.1151
0.7642
 
Question 22

Joe used a project management software package and has determined the following results for a given project.:

What is the probability of completing the project over 20 days?
Answer
0.3849
0.8849
0.1151
0.7642
 
Question 23

Once a project is underway, the project manager is responsible for the
Answer
people.
cost.
time.
All of these
 
Question 24

Project control involves
Answer
crashing.
three time estimates.
a backward or forward pass.
earned value analysis.
 
Question 25

Project management differs from management of more traditional day-to-day activities because
Answer
it has limited time frame.
it has an unlimited budget.
it is more expensive.
it involves more of the workforce.
 
Question 26

The LS and LF are calculated using the
Answer
backward pass through the network.
forward pass through the network.
values for ES and EF.
backward and forward pass through the network.
 
Question 27

The activities that must be completed prior to the start of an activity in question are called the immediate ________ of the activity in question.
Answer
successors
predecessors
successors and predecessors
followers
 
Question 28

The critical path is the ________ path through the network.
Answer
longest
shortest
straightest
most expensive
 
Question 29

The normal cost for an activity is $7,000 and the crash cost is $12,000. The normal time to complete this activity is 8 days and crash time is 4 days. If this activity is crashed by 2 days it will cost an additional:
Answer
$1000
$1250
$2000
$2500
 
Question 30

Which of these statements regarding project crashing is true?
Answer
Crashing is not possible unless there are multiple critical paths.
Activities not on the critical path cannot become critical after crashing.
Crashing shortens the project duration by assigning more resources to one or more of the critical tasks.
Crashing a project often reduces the time it takes for lengthy or complex, but noncritical activities.

Reference no: EM13228518

Questions Cloud

Decision on accepting additional business : Decision on Accepting Additional Business
What is the velocity of propagation of the cable : A slotted line is used to measure the voltage maximums and voltage minimums on a transmission line with a characteristic impedance of 50 . The voltage maximum is measured as 7.5 V and the minimum is 5 V. The line is terminated with a purely resist..
Paper on the french commune of 1971 and marxism : I need to write a paper on the French Commune of 1971 and Marxism. Can you help me write an introduction and give me themes to write about?
Explain what would be the best acid or base system : Suppose you wanted to make a pH=4.25buffer. What would be the best acid/base system: acetic acid/acetate or lactic acid/lactate? THe Ka of lactic acid is 8.32x10(exponent -4). Throughly explain your reasoning.
Statements regarding project crashing : The normal time to complete this activity is 8 days and crash time is 4 days. If this activity is crashed by 2 days it will cost an additional - statements regarding project crashing
Explain how many grams of dry nh4cl need to ammonia : How many grams of dry NH4Cl need to be added to 1.50 L of a 0.300 M solution of ammonia, NH3, to prepare a buffer solution that has a ph of 8.73? pkb for ammonia is 1.8X10^-5.
Describe the coming of the french revolution : Describe the coming of the french revolution. The information just have to be very accurate and presented well in a meaninful way in the order of the events
Create a scenario involving providing care : Part 1 Disease Process: Create a scenario involving providing care for a patient with a specific pathology of breast cancer. • Include a brief past and present health history, family and social history.
Prepare the adjusting journal entries : On July 31, 2013, the company paid a two-year premium of $18,000 on an insurance policy that is effective June 1, 2013, and expires May 31, 2015.

Reviews

Write a Review

Advanced Statistics Questions & Answers

  Breakeven point for managerial accounting

Compute the breakeven point for two product lines. Scotty's Scooters plans to sell a standard scooter for $40 and a chrome scooter for $50. Scotty's purchases the standard scooter for $25 and the chrome scooter for $30.

  Computing intrinsic value of a bond

Twin Oaks Health Center has a bond issue outstanding with a coupon rate of 7 percent and four years remaining until maturity. The par value of the bond is $1,000, and the bond pays interest annually.

  Making t-ledger and a journal

I just need help with setting this accounting question up on a t-ledger and a journal it has to be on an excel format as well. I am just confused on how to set it up

  Stock trading-payoff of call

You own a call option on Intuit stock with a strike price of $40. The option will expire in exactly three months time. Draw a payoff diagram showing the value of the call at expiration as a function of the stock price at expiration.

  Cultural dimension comparison of us

Information of a historical, political, economic, or social nature that helps to explain the values and placement on the various cultural dimensions will be helpful. Your results will be presented in a written report.

  Basic accounting principles

You have been nominated by your institution for a seminar because of your proficiency in basic accounting concepts. The participants and audience include college professors, practicing CPAs, and fellow students.

  Breakeven analysis-aviation maintenance company

By this time, you should have an organization selected and approved for your project. In this module, we are going to have our first application to that project. Identify any activity in your organization where you can apply breakeven analysis.

  Determining pert and cpm

Assume you are going to manage a large construction project involving many subcontractors. Why use PERT or CPM to plan the project rather than just logically scheduling the subcontractors?

  Project probability with variance

A project has an expected duration of 34 weeks with a critical path variance of 6. Suppose the project network is given and the critical path is identified on the network. Suppose the normal time, crash time, and the associated cost for each activ..

  Developing appropriate forecast model for bookstore

Develop an appropriate forecast model for bookstore management to use to forecast computer demand for next fall semester and indicate how accurate it appears to be. What other forecasts might be useful to the bookstore?

  Modelise as a markov chain

modelise as a markov chain

  Shape of normal frequency distribution graph

What is the shape of a normal frequency distribution's graph? What is the common term for the standardized score of a normal curve? Define correlation in your own words.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd