Statements regarding project crashing

Assignment Help Advanced Statistics
Reference no: EM13228518

Question 1

A GANTT chart represents mainly
Answer
an immediate identification of predecessor task.
a record-keeping device used in scheduling activities.
a general identifier. the number of workers directly involved in the project.
 
Question 2

A PERT/CPM activity has an optimistic time estimate of 3 days, a most likely time estimate of 8 days, and a pessimistic time estimate of 10 days. The expected time (in days) of this activity is:
Answer
7.0
7.5
8.0
8.5
 
Question 3

A PERT/CPM activity has an optimistic time estimate of 4 days, a most likely time estimate of 6 days, and a pessimistic time estimate of 10 days. The standard deviation of this activity is:
Answer
7/6
1/3
2/3
1.0
 
Question 4

A list of the tasks, broken down into modules, components, and individual tasks, is called a
Answer
work breakdown structure (WBS).
PERT.
planning matrix.
critical path.
 
Question 5

A work breakdown structure breaks down a project into
Answer
weeks.
areas.
arcs.
modules.
 
Question 6

Consider the following project.

 


What is the critical path?
Answer
ACFG
ADFG
BEG
ACDFG
 
Question 7

Consider the following project.

 

What is the minimum possible time for completing this project?
Answer
15 days
16 days
18 days
20 days
 
Question 8

Consider the following project.


Compute the slack time for activity C.
Answer
0
4
2
3
 
Question 9

Consider the following project.


What is the latest possible time that Activity E can be started without delaying the completion of the project?
Answer
8
3
7
9
 
Question 10

Consider the following project.


What is the latest time that activity B can start without delaying the project?
Answer
0
8
4
7
 
Question 11

Consider the following project.


What is the latest time that activity B can finish without delaying any other activities?
Answer
0
8
9
4
 
Question 12

Consider the following project.

Determine the critical path.
Answer
ACEH
BCEH
BDFH
BDGH
 
Question 13

Consider the following project.


Determine the estimated completion time of the project.
Answer
23 days
22 days
25 days
20 days
 
Question 14

Consider the following project.

 

Determine the slack for activity D.
Answer
2 days
4 days
6 days
5 days
 
Question 15

Consider the following project.


Determine the slack for activity F.
Answer
2 days
3 days
4 days
5 days
 
Question 16

Consider the following project.


How much can activity F be delayed without delaying the project completion?
Answer
1 day
2 days
3 days
4 days
 
Question 17

Elements of project planning include
Answer
defining project objectives.
identifying activities to crash.
calculating expected times and standard deviations.
conducting a "lessons learned" session.
 
Question 18

If an activity cannot be delayed without affecting the entire project, then it is a ________ activity.
Answer
completed
critical
crashed
normal
 
Question 19

If t is the expected completion time for a given activity, then:
Answer
LF = LS - t
EF = ES - t
EF = ES + t
EF = LS - t
 
Question 20

In a CPM/PERT network the critical path is the
Answer
lowest path through the network.
highest path through the network.
shortest path through the network.
longest path through the network.
 
Question 21

Joe used a project management software package and has determined the following results for a given project:

What is the probability of completing the project within 20 days?
Answer
0.3849
0.8849
0.1151
0.7642
 
Question 22

Joe used a project management software package and has determined the following results for a given project.:

What is the probability of completing the project over 20 days?
Answer
0.3849
0.8849
0.1151
0.7642
 
Question 23

Once a project is underway, the project manager is responsible for the
Answer
people.
cost.
time.
All of these
 
Question 24

Project control involves
Answer
crashing.
three time estimates.
a backward or forward pass.
earned value analysis.
 
Question 25

Project management differs from management of more traditional day-to-day activities because
Answer
it has limited time frame.
it has an unlimited budget.
it is more expensive.
it involves more of the workforce.
 
Question 26

The LS and LF are calculated using the
Answer
backward pass through the network.
forward pass through the network.
values for ES and EF.
backward and forward pass through the network.
 
Question 27

The activities that must be completed prior to the start of an activity in question are called the immediate ________ of the activity in question.
Answer
successors
predecessors
successors and predecessors
followers
 
Question 28

The critical path is the ________ path through the network.
Answer
longest
shortest
straightest
most expensive
 
Question 29

The normal cost for an activity is $7,000 and the crash cost is $12,000. The normal time to complete this activity is 8 days and crash time is 4 days. If this activity is crashed by 2 days it will cost an additional:
Answer
$1000
$1250
$2000
$2500
 
Question 30

Which of these statements regarding project crashing is true?
Answer
Crashing is not possible unless there are multiple critical paths.
Activities not on the critical path cannot become critical after crashing.
Crashing shortens the project duration by assigning more resources to one or more of the critical tasks.
Crashing a project often reduces the time it takes for lengthy or complex, but noncritical activities.

Reference no: EM13228518

Questions Cloud

Decision on accepting additional business : Decision on Accepting Additional Business
What is the velocity of propagation of the cable : A slotted line is used to measure the voltage maximums and voltage minimums on a transmission line with a characteristic impedance of 50 . The voltage maximum is measured as 7.5 V and the minimum is 5 V. The line is terminated with a purely resist..
Paper on the french commune of 1971 and marxism : I need to write a paper on the French Commune of 1971 and Marxism. Can you help me write an introduction and give me themes to write about?
Explain what would be the best acid or base system : Suppose you wanted to make a pH=4.25buffer. What would be the best acid/base system: acetic acid/acetate or lactic acid/lactate? THe Ka of lactic acid is 8.32x10(exponent -4). Throughly explain your reasoning.
Statements regarding project crashing : The normal time to complete this activity is 8 days and crash time is 4 days. If this activity is crashed by 2 days it will cost an additional - statements regarding project crashing
Explain how many grams of dry nh4cl need to ammonia : How many grams of dry NH4Cl need to be added to 1.50 L of a 0.300 M solution of ammonia, NH3, to prepare a buffer solution that has a ph of 8.73? pkb for ammonia is 1.8X10^-5.
Describe the coming of the french revolution : Describe the coming of the french revolution. The information just have to be very accurate and presented well in a meaninful way in the order of the events
Create a scenario involving providing care : Part 1 Disease Process: Create a scenario involving providing care for a patient with a specific pathology of breast cancer. • Include a brief past and present health history, family and social history.
Prepare the adjusting journal entries : On July 31, 2013, the company paid a two-year premium of $18,000 on an insurance policy that is effective June 1, 2013, and expires May 31, 2015.

Reviews

Write a Review

Advanced Statistics Questions & Answers

  Determining applied research and statistics

Discuss how this observation should be considered when building a research plan. How might it impact the level of detail you include in your plan?Discuss key issues and concerns arising from the fact tht you, the manager, are also the researcher?

  Investment in associate-equity method

On January 1, 2008, Jonsey Corporation purchased 30% of the common stock outstanding of Karsen Corporation for $200,000. During 2008, Karsen Corporation reported net income of $80,000 and paid cash dividends of $40,000.

  Difference in haemoglobin concentration at enrolment

Difference in haemoglobin concentration at enrolment between women with detectable peripheral malaria parasites and those without detectable parasites?

  Determining number of sales using algebra

A Cold Stone Creamery ice cream shop sells sundaes for $3.60 and banana splits for $4.25. The shop sells four times as many sundaes as banana splits. If total sales amounted to $3,730 last weekend, how many banana splits were sold?

  Use of statistics in business research

Why use statistics in business research, and what is its role? How can the concept of variance and standard deviation be applied to solving a real world business-related problem? Include a specific example from business. Explain.

  Estimating fair value of stock

A company currently pays a dividend of $2.25 per share, D0 = 2.25. It is estimated that the company's dividend will grow at a rate of 23% percent per year for the next 2 years, then the dividend will grow at a constant rate of 7% thereafter.

  Economic lot order quantity model

What would be the order size for Company A in the given scenario that would minimize total annual cost by using the economic order quantity model?

  Characterize the nash equilibrium

Explain how the authorities should choose the toll to bring the equilibrium number of trips to the efficient level.

  Create a scatter plot - correlation and regression

What would you predict the final exam points to be for a student with a GPA of 3.35 and an IQ of 120 and what is the relationship between a student's short-term IQ score, previous GPA, and final exam points?

  Determining efficienct market hypothesis

The Efficient Markets Hypothesis holds that markets do not react to news or announcements because by the time the information is disseminated, it has already been anticipated.

  What is the break-even quantity

Draw a decision tree for this problem and what should management do to achieve the highest expected payoff?

  Historical evolution of healthcare system

Why is it important to understand the historical evolution of the healthcare system?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd