A project has an expected duration of 34 weeks with a critical path variance of 6. Suppose the project network is given and the critical path is identified on the network. Suppose the normal time, crash time, and the associated cost for each activity is given. You have been asked by your supervisor to prepare a research paper that addresses the follow criteria:

- What is the probability that the project will be completed in 32 weeks or less?

- If the project is to be shortened by four days, list the process you would take to determine which activities, in order of reduction, would be shortened and the resulting cost.

- Describe project cost and the requirements for it's determination and application in a production facility.

- Analyze implications of changes in the parameters of project timing and cost determination.

- Evaluate application of project cost and timing concepts on a firm's business operations.

Reference no: EM13114569

Questions Cloud

Illustrate what recommendations would you make to senior : Illustrate what recommendations would you make to senior management for the upcoming year? Note that stating you have no advice or that management should keep doing what they have been doing.
Compute confidence level for difference in means : Compute a 95% confidence level for the difference in the means of the two treatment methods and select the best answer below. Assume that the independent random samples were taken from normal distribution.
Provide a possible explanation : Provide a possible explanation as to why this test identifies the presence of cytochrome c oxidase and not the other electron carries.
Compare and contrast how quality new products : Compare and contrast how quality new products/services are likely to be developed at a McDonald's versus a bank in your neighborhood.
Project probability with variance : A project has an expected duration of 34 weeks with a critical path variance of 6. Suppose the project network is given and the critical path is identified on the network. Suppose the normal time, crash time, and the associated cost for each activ..
What controls should an organization : What controls should an organization like Tyco implement to ensure that such transactions do not take place in the future?
Use t test for dependent means and independent means : For each of the following studies, say whether you would use a t test for dependent means or a t test for independent means.
How many kilograms of methane is present : How many kilograms of methane (CH4) are in perfectly insulated piston with the following properties: Volume = 2 cubic meters.
Describe the unwinding process or the synthesis : A piece of DNA has unwound and the ends of the two strands have begun separating for replication. Describe, in full detail, the discontinuous synthesis of the lagging strand.

Reviews

Write a Review

Advanced Statistics Questions & Answers

  Techniques in business-economics

A sample of the monthly amounts spent for food by families of four receiving food stamps approximates a symmetrical distribution. The sample mean is $150 and the standard deviation is $20.

  Presentation on statistical test of snack foods

List at least three qualitative attributes of the snack food about which they might want to ask consumers. Make sure at least one of them is nominal.

  Steps and sequence in hypothesis testing

What are the steps espoused by the textbook (or instructor) for formal hypothesis testing? Explain why the sequence is important?

  Determine the area of the shaded region

Evaluate the area of the shaded region (z=0.99). The graph depicts the standard normal distribution of bone density scores with mean 0 and standard deviation 1.

  Credit default swap-unconditional default probability

Calculate a simple one-year credit default swap spread using a recovery rate of 30% and an unconditional default probability of 4%. Assume that there are no accruals, payments are made annually and ignore discounting any cash flows.

  Final price adjustment-defective pricing

Compute the amount of the final price adjustment because of defective pricing based on the following:

  Legal and ethical implications of media giant mergers

Discuss the legal and ethical implications of the ongoing debate and take a position as to whether the changes should be allowed and would they benefit DWI.

  Draw a two way anova design plot

Draw a two way ANOVA design plot (the mean plot you draw in class) to discuss whether there seems to be any interaction effects of gender and age.

  Company research outline

What forecasting techniques does this company use? How does your selected organization prepare budgets? What MRP concepts do you see with regard to your organization?

  Compute average before and average after in regulated areas

The dependent variable is hygiene score in a restaurant in a quarter and grade cards introduction has been shown to improve average grades in mandatory counties and voluntary counties.

  Computing averages and probability using excel

Zimmerman's Bank is the only bank in the small town of St. Thomas. On a typical Friday, an average of 10 customers per hour arrive at the bank to the transact business.

  Relationship between speed, flow and geometry

Write a project proposal on relationship between speed, flow and geometry on single carriageway roads.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd