I. The seller has agreed to a fixed price incentive (FPI) contract. The target cost is $450,000 and the target fee is 10% of the target cost. The price ceiling is $540,000 and the buyer/seller share ratio 80/20. The final actual cost is $430,000. Determine the following:
Final adjusted fee:
Final price:
2. The seller has agreed to a fixed price incentive (FPI) contract. The target cost is $450,000 and the target fee is 10% of the target cost. The price ceiling is $500,000 and the buyer/seller share ratio is 80/20. The final actual cost is $520,000. Determine the following:
Final adjusted fee:
Final price:
3. The seller has agreed to a cost plus fixed fee (CPFF) contract. The target cost is $450,000 and the fixed fee is 10% of the target cost. The final actual cost is $500,000. Determine the following:
Final fee:
Final price:
4. The seller has agreed to a cost plus incentive fee (CPIF) contract. The target cost is $450,000 and the target fee is I0% of the target cost. The maximum fee is $50,000, the minimum fee is $17,000 and the buyer/seller share ratio is 80/20. The final cost is $600,000. Determine the following:
Final adjusted fee:
Final price:
5. The seller has agreed to a cost plus incentive fee (CPIF) contract. The target cost is $450,000 and the fixed tee is I 0% of the target cost. The maximum fee is $50,000. the minimum fee is $17.000 and the share ratio is 80/20. The final cost is $400,000.
Determine the following:
Final adjusted fee:
6. Some 10 months ago you awarded a cost plus fixed fee (CPFF) contract to a large company to provide a telecommunications infra-structure at several locations. The contract was negotiated with a target cost of$200,000 and a fee of 0% of the target cost. The contract is complete and the final costs come in at $150.000. What is the total amount you must pay to the supplier?
7. As part of a project to renovate the airport in Peekskill, New York, you awarded a cost plus incentive fee (C PIF) contract for upgrading the restaurant and lounges. The target costs were negotiated at $200,000, with a 10% target profit. The buyer/seller share ratio is 80/20. The project was completed at $180,000. How much is the total contract cost which must be paid to the supplier?
8. You negotiated a cost plus fixed fee plus award fee (CPFF/AF) contract with a seller for a projected total value of $505,000, of which $500,000 is the target cost and $5,000 is the amount of the fixed fee. You have also set aside a budget for a possible award fee, with a not-to-exceed amount of$25,000. The seller's final cost comes in at $533,000. What is the final payment to the seller?
Would expect cell body of neuron 1 to be in right hemisphere
: Assuming that segmentation of the spinal cord follows a similar pattern in all mammals, approx in which of the 4 major regions of the spinal cord and within which spinal cord structure would you expect to find the axon terminals of neuron 1?
|
Social capital support innovation
: How can social media such as LinkedIn, Facebook and Twitter be used to improe knowledge sharing build social capital support innovation and aid problem solving in one of the following organisational contexts-
|
How would the deposit be reported in the financial statement
: Prepare the entry by Billy Pilgrim to record the delivery of 125 units during 2012. How would the deposit be reported in the financial statements at the end of 2012?
|
Average mass of the ramp and passengers
: The ramp shown below is used to assist passengers boarding light commuter aircrafts. The average mass of the ramp and passengers is 800 kg with the center of mass located at point G. As the ramp angle θ increases, the hydraulic cylinder extends bu..
|
Fixed price incentive (fpi) contract
: The seller has agreed to a fixed price incentive (FPI) contract. The target cost is $450,000 and the target fee is 10% of the target cost. The price ceiling is $540,000 and the buyer/seller share ratio 80/20. The final actual cost is $430,000. Det..
|
The conversion of binary numbers to decimal numbers
: You will need to use a for() loop to process the eight bits. You will need to use a while() loop to access the numbers in the data file (checking for the end of file). This program will help you read data from a data file, valid the data and proce..
|
Prepare the entry to record the payment of warranty claims
: What is the December 31, 2009, balance in the estimated warranty liability account? Compute the warranty expense for 2009. Prepare the entry to record the payment of the 2009 warranty claims.
|
Damon gain organisational knowledge
: A mentor has certain functions in an organisation. Identify the types of support offered by this mentor. What else could the mentor have done to help Damon gain organisational knowledge?
|
Country that have five components
: compare three countries, how are they different and what's that means? based on this website. And write 300 words about their difference report.
|