During a project earned value analysis

Assignment Help Business Management
Reference no: EM13960542

Of the three problems below, choose and solve one problem. Show your work. Along with your answer, define each term and explain the significance (meaning) of the solution.

1. During a project, Earned Value Analysis is performed and gives the following numbers:

EV: 523,000; PV: 623,000; AC: 643,000.

Which results are correct?

A. CV: +120,000; SV: +100,000

B. CV: +100,000; SV: +120,000

C. CV: -100,000; SV: -120,000

D. CV: -120,000; SV: -100,000

2. You found the following Earned Value Analysis information for a recently closed out project:
SPI = 0.7, CPI = 1.0

A. The project has been cancelled while it was executed. At that time the project was behind schedule and on budget.

B. The project's deliverables have all been finished. The project came in ahead of schedule but on budget.

C. The project's deliverables have all been finished. The project came in on schedule but over budget.

3. You are assigned as the project manager to a project which had a one-time cost variance in the past caused by unexpected rework which has meanwhile

been finished.
You perform Earned Value Analysis and find the following results:
EV: 250,000; PV: 200,000; AC 275,000
BAC is 500,000.
What is right?
A. EAC = 550,000

B. EAC = 525,000

C. EAC = 500,000

D. EAC = 425,000

Reference no: EM13960542

Questions Cloud

What value if interet was compounded quarterly : Type of investment: 36 month CD at 2% compounded daily What value if interet was compounded quarterly? How much is investment worth after 36 months?
Reaction paper that focuses on community treatment orders : Write a 3-5 page reaction paper that focuses on your key issue. You should summarize your issue, including the debate that exists surrounding that issue, and weigh in with an informed opinion
Summarize the business research project or article : Locate a business research article. This project should be one that you perceive to be conducted in an ethical manner. Write a 700- to 1,050-word paper in which you create a set of ethical research guidelines for the research:
Determine the period for planet kep to orbit if the distance : A 2.4 gram penny is on a turntable. It starts from rest at a radius of 0.14 meters and the turntable speeds up until the penny flies off with a tangential speed of .88 m/s. What coefficient of static friction (to three decimal places) exists betwe..
During a project earned value analysis : Of the three problems below, choose and solve one problem. Show your work. Along with your answer, define each term and explain the significance (meaning) of the solution.
Calculate the percent markdown after rebate for the product : Calculate the percent markdown after rebate for the product found in part 1. List three pros and three cons to the practice of markdowns/markups. Debate these points.
How does studying humanities help society in today world : How does studying humanities help society in today's world? How did the 19th century social reformation, such as the European revolution of 1848, influence theatre in multiple countries and religions
Venture capitalists seek to maximize economic returns : Venture capitalists seek to maximize economic returns. Considering all the risks in the development or expansion of business ventures, how do venture capitalists make money? How do venture capital firms balance their portfolios to minimize risks..
What is the speed of the satellite in its orbit : A satellite of mass 150kg is launched into orbit above the surface of the Earth in a circular orbit. what is the speed of the satellite in its orbit? What is providing the centripetal force on it? Find its value.

Reviews

Write a Review

 

Business Management Questions & Answers

  Can the brand of products impact buyers attitude

Can the BRAND of products from certatin countries impact buyers attitude towards the goods or services? Explain you answer with examples.

  Explain when does concentration of production make sense

Explain When does concentration of production make sense and Compare and contrast counterpurchase agreements and offset arrangements

  Identify any instances of pseudoreasoning in the following

identify any instances of pseudoreasoning in the following passage either by naming them or where they seem not to

  Explain if an employer has a good-faith reasonable doubt

Explain If an employer has a good-faith reasonable doubt as to whether a majority of its employees support an incumbent union

  Global pay structures

It provides the learner with an understanding of the intricities associated with Global Pay Structures

  Wealth maximization model and one governed by the

wealth maximization model and one governed by the stakeholder wealth maximization model.management objectives of a firm

  Write request for proposal about description of your company

You are a manager or supervisor of a company and Write a request for proposal about Description of your company and Your company's business goals.

  Describe the scope and analyze how to control the scope

Describe the scope and analyze how to control the scope

  What do we mean by triangulation

What do we mean by Triangulation? Why might triangulation be important in relation to researching an organization using a single case study approach?

  Shwo the employee responsibilities and leader

shwo the employee responsibilities and leader decisionsduring a day at work people make many decisions. do you believe

  Define leadership approaches

Determine leadership approaches that you may need to tailor for each person or note if the same leadership approach would work for all your team members. Explain why each approach was chosen for each member.

  International management personality and experience of the

international management personality and experience of the ceo drives strategyselect three successful international

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd