A construction project is broken down into the following 10 activities:

Activity Immediate Predecessor Time (weeks)

1 ---- 4

2 1 2

3 1 4

4 1 3

5 2,3 5

6 3 6

7 4 2

8 5 3

9 6,7 5

10 8,9 7

a. Draw the network diagram.

b. Find the critical path.

c. If activities 1 and 10 cannot be shortened, but activities 2 through 9 can be shortened to a minimum of one week each at a cost of $ 10,000 per week, which activities would you shorten to cut the project by four weeks?

Reference no: EM13810623

Ensuring safe and healthful working conditions

Do you believe OSHA is effective at ensuring safe and healthful working conditions for working men and women by setting and enforcing standards and by providing training, outr

Strategic staffing plan before employees leave

Like any other area of your business, good staffing requires careful attention and planning. Looking for new hires after someone leaves is simply crisis management, and it can

Organization might consider when developing a strategic plan

Your text explains why it is important to select the appropriate criteria for strategic planning. Part of this process is establishing metrics to measure the progressive suc

Accounting department has assigned holding costs fraction

A large hospital's nursery uses disposable diapers for its newborn babies at a rate of 60 cases per day. Ordering costs have been estimated at $50 per order. The hospital's Ac

Research on leader-member exchange-cognitive strategy

Studies on how managers perceive poor performance by a subordinate find that: Which of the following is a cognitive strategy for self management? Which was not found in the re

Annual cost of termminal fees

Terminal fees of $290 per take-off. Southwest airlines plans to offer three flights a day, every day of the year, in each direction. What would be the annual cost of termminal

Defined benefit to defined contribution retirement plans

What is the main reason that companies have been rapidly shifting from a defined benefit to defined contribution retirement plans? Defined contribution plans shift the investm

Under the digital millennium act

Under the Digital Millennium Act, online service providers, such as universities, can avoid liability if they take certain steps specified in the Act. These include cases when

Reviews

Write a Review

 
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd