Draw an aoa network diagram representing the project

Assignment Help Project Management
Reference no: EM13962961

Network Diagrams are often used during project planning to give the project manager a visual map of the key activities of the project. Activity-On-Arrow (AOA) is often used to demonstrate the concept of activity sequencing.

Activity

Initial node

Final node

Duration estimate

A

1

2

2

B

2

3

2

C

2

4

3

D

2

5

4

E

3

6

2

F

4

6

3

G

5

7

6

H

6

8

2

I

6

7

5

J

7

8

1

K

8

9

2

Consider Figure the attachment to answer the following questions. All duration estimates are in days, and the network proceeds from Node 1 to Node 9.

1. Draw an AOA network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labeling each arrow with the activity letter and estimated time.

2. Identify all the paths on the network diagram and note how long they are, using Figure 152) as a guide for how to represent each path.

3. What is the critical path for this project and how long is it?

4. What is the shortest possible time it will take to complete this project?

5. Examine the network diagram and task schedule table to analyze the critical path and float or slack for each activity.

Write at least a paragraph that interprets this information for someone unfamiliar with project time management.

Reference no: EM13962961

Questions Cloud

Nutritional elements per pound of feed : A farmer can purchase 3 kinds of feed for his stock, with various percentages of each of 4 nutrients, called A, B, C, and D.  A mixture of feeds gives proportional amounts of nutrients.  The following table gives the minimum da..
The triangle has the angles 45,45,90 with a base of length : The triangle has the angles 45,45,90 with a base of length a. The dipole is located at the right base corner pointing in the -x direction.
How many trades must he made to break even : Use the contribution margin ratio CVP formula to compute Big Time's break even revenue in dollars. If the average trade leads to $800 in revenue for Big Time, how many trades must he made to break even?
Annual production capacity : The Sentry Lock Corporation manufactures a popular commercial security lock at plans in Macon, Louisville, Detroit, and Phoenix.  The per unit cost of production at each plant is $35.5, $37.5, $39, and $36.25, respectively, while the annual product..
Draw an aoa network diagram representing the project : Draw an AOA network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labeling each arrow with the activity letter and estimated time.
Small businesses are undercapitalized : Suppose that 30% of all small businesses are undercapitalized. Forty percent of all undercapitalized small businesses fail and 20% of all small businesses that are not undercapitalized fail. A small business is chosen at random. The probability th..
Describe your company operations and the market : For the company you selected, describe your company's operations and the market in which it operates. Search for the EVA, and free cash flow using the firm's annual report
Discuss the signal a large stock repurchase might foretell : Discuss the signal a large stock repurchase might foretell about management's outlook relative to the future of a company. Explain whether a repurchase of stock is typically a good or bad sign. Provide a rationale for your response
Understand and measure doppler shift : Now test this out. Move to the distance away from the tuning fork you calculated above. How would you describe the loudness of the sound now? Would you say it is twice as loud?

Reviews

Write a Review

Project Management Questions & Answers

  Risks factors on future infrastructure projects

Discuss the methodology you recommend for identifying and mitigating these risks factors on future infrastructure projects.

  Project management processes in an organization

The topic is gaining credibility among the non-project managers in a company and how important is it for a project manager to be an expert in the subject matter of the project?

  Show the project cash flow analysis

Your company plans to produce a product for two more years and then to shut down production and you are considering replacing an old machine used in production with a new machine.

  Business communication - routine and goodwill emails

Describe why you chose to emphasize these principles and why you wrote your message as you did. Discuss your objectives and how you used the background readings.

  The assignmentwrite a progress report about your own

the assignmentwrite a progress report about your own professional or work accomplishments. the period to be covered is

  Assistance on project management

How would you proceed and what tools would you use - when was a time that a situation like this was handled successfully

  Intercultural communication interpreting phrases in

intercultural communication interpreting phrases in different languages1. explain how can someone in a non-dominant

  Describe the five phases of a project

Describe the five phases of a project. Describe the key deliverables associated with the selected project(s)

  Four factors for productionimportance to economyexplain the

four factors for productionimportance to economyexplain the four factors for production that influence a countrys

  How to discuss the quality assurance practices

At each stage you will be required to discuss the quality assurance practices that are recommended and produce one or more examples of quality control documentation. The V model of software development is one method for implementing this approach.

  What are the three project team structures

What are the three project team structures and what are some of the elements that differentiate the team structures from one another

  Decission tree for capital investment decisionprepare a

decission tree for capital investment decisionprepare a decision tree using the method described in the textbook or any

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd