Determine the corrected production for the dozer

Assignment Help Other Engineering
Reference no: EM13753809

26. Determine the maximum production for a Caterpillar D11R Dozer fitted with a Universal Blade using the diagram below for a dozing distance of 60m.

Determine the corrected production for the dozer for downhill dozing on a 5% slope, with a 50 minute working hour and an average operator as per the correction factors below.

 

27.Normally the height of windrow is?

28.Which of the following has the lowest power consumption in kwh/m3


a. BWE
b. Electric Face shovel c. Walking dragline
d. BCE

 

29.Which of these would be considered an excessively steep a grade for a normal rear dump truck?
a. 4% b. 6% c. 8% d. 10%


30.Draw and label in detail a hydraulic excavator

31.Sketch a cross section of an open cut mine, label the major components, and explain briefly the purpose of each.

 

32.Sketch and label the four most common slope failure types.

33.Calculate the efficiency of a 24H Caterpillar grader maintaining a 40m wide haul road, given the following:
? road length is 16,500m

? machine takes 8 hours to complete the task ? average speed of the machine is 22km/hr
? task completion requires making 8 passes

34.Given are the following data for a shovel-truck surface mine operation:

??required production/bench = 16,000 tonnes/shift

??operating period = 1 shift/day

??material = well blasted rock

??working time = 51 min/hr and 10.5 hrs/shift

??operating factor = 83%

??specific weight of rock = 2.35 t/m3 Calculate the idealised output (m3/hr) of the shovel.


35.

a. What are the different types of haul roads in use in surface mining?


b. Design a spiral haul road system for the following surface mine:
i. pit consists of 6 benches
ii. bench height is taken as 12m=H

iii. crest-to-crest distance is 21m
iv. bench face angle is 59?
v. a haul road having a width of 30m and 8% (=G%) gradient will be added to the inside of the pit wall


36.If the width of a haul unit is 15m, determine the minimum width of a haul road for:
o Single lane haul road operation
o Two lane operation
o Three lane operation


37.Describe the various methods of truck loading using either a shovel or excavator fitted as a backhoe


38.Estimate the cycle time and production of a Caterpillar 777D flat floor off highway truck operating on a level haul road of 2000m length. The road is a rutted dirt roadway with no maintenance and no stabilisation, tyre penetration is 4 cm. The following can be assumed;
o Loading time 1.4 min
o Manoeuvre and dump time 0.8 min
o Truck hauls 40 tonnes of ore each trip o Job efficiency of 0.8


39.For the situation in question 38, determine the cycle time if road conditions were improved to a rolling resistance of 30 kg/tonne.
40.For the problem in question 38 and 39 the engineer at the site is considering the use of a shorter, 1000m, haul road that has a slope of 6% adverse. If all other factors remain the same which haul route should be selected on the basis of shortest cycle times? What are the cycle times and hourly productions?
41)An off highway truck weighs 23 t empty and carts a payload of 35 t up an 8% grade. The RR factor is 40 kg/tonne. Calculate:


a) The total resistance (kg)


b) The effective grade (%)


42)A rubber tyred scraper unit weighing 50 t is towed by a crawler tractor weighing 40t up a 4% grade. The RR factor is 50kg/t. Calculate:
a) The rolling resistance (kg) b) The grade resistance (kg) c) The total resistance (kg)


43)A Caterpillar D30D articulated dump truck has the rim pull curve in figure 1. (Gross weight 21.9 t empty, 49.117 t loaded). If the truck ascends a 5% grade with a rolling resistance of 50kg/t, find the following:
a) Total resistance (kg)
b) The required rim pull (kg) when loaded
c) The maximum speed of the truck when loaded (km/h)


Figure 1: CAT D30D Rimpull, Speed, Gradeability (Caterpillar Performance Handbook version 31 (2000)).

44)The average speed of an 18m3 scraper is 40 km/hr and its return speed uphill is 22 km/hr over a 400 m haul distance and a 450m return distance. Using a fixed time of 4 minutes, calculate the cycle time (min).

 

45) What are the advantages and disadvantages of in-pit crushing


46) Continuous surface miners such as the Wirtgen surface miners are used at a number of operations worldwide. Describe such a machine and detail the type of operation where such a machine has advantages over traditional surface mining techniques.

Note: The Caterpillar and Komatsu Performance Handbooks are provided on the course Moodle page


1. For a 77t truck with Gross Vehicle Weight (GVW) of 136078 kg with dual rear tyres and a tyre inflation pressure is 120 psi (or 8.43 kg/cm2). Use the equivalent single tyre loading.


i. Determine the contact surface area

ii. If the sub-grade material is a firm or stiff clay, then determine the minimum required distance between the wearing surface and the top of the sub-grade.

iii. With the same truck specifications, design an acceptable haul road (ie determine different thicknesses of different layers) using CBR method. Choose your own material for different layers with proper justifications. (Use the required conversion factors) 


2.
a. A pit with a straight ramp of 800m, with a gradient of 10%, supplies a ROM pad 1500m away via a level haul road all of loose gravel. Mining of a dipping ore body, with a specific weight of 2.5 t/m3, is required to be carried out at a rate of 10,000 tonnes/8 hour shift to feed the mill.

Since truck speed is restricted to 50kmph, assume the average speed of a truck during a round trip is 45kmph, including reversing to load. Waste material of specific weight = 1.85 t/m3 is also to be mined, and deposited on a waste dump 200m from the pit. The waste dump

already has a height of 10m, and an area of 100m x 60m from pre-stripped overburden. Excluding the overburden, the strip ratio is 1:4.5.
Other factors that are working assumptions are:
Availability of excavator 83%, Swell factor of 30%
Bucket fill factor of 88% Excavator cycle time 45 seconds

Rolling Resistance Factor (RRF) = 15 kg/t

Coefficient of Friction, µ = 0.25 Grade Resistance Factor = 20 kg/t

(i) Calculate required output by a single excavator appropriate to this production and select an appropriate machine.
(ii) Calculate cycle times for trucks.
(iii) Calculate number and size of trucks.
(iv) Ensure trucks are capable of carrying out this mining safely.

List and justify your assumptions.


3. Working Bench
Consider a mining sequence on a working bench.
a. Define the width of a working bench with a neat sketch.
b. Design a working bench when a single shovel of 6.8m3 capacity details of

which are supplied in the notes with single spotting is used: Given:
i. design bench height =15m
ii. shovel will move along one line parallel to the bench face

iii. bench face angle 65°

iv. parallel cut will be used with turn and back
v. single spotting
vi. haulage by 50 tonne capacity truck
vii. truck width = 5.5m
viii. truck tyre rolling radius = 1.2 m
ix. a safety berm is required

4. Pit Slope Angles.

Define, with a neat sketch, the different types of slope angles in a surface mine

Given:

- No. of benches = 9

- Bench face angle =69°

- Safety bench width = 10m
Based on the above data determine the following:
1. the overall slope angle
2. the overall slope angle if you introduce a ramp of 27 m width on the 5th bench

3. the inter-ramp angles
4. on the initial design, the overall slope angle if you introduce a working bench only on the 2nd bench

5. on the initial design, the overall slope angle if you introduce a ramp of 27 m width on the 7th bench
6. the inter-ramp angles
7. final slope angle at the end of pit limit

Assume bench height of 20m.

5) A Caterpillar 631 E tractor scraper has the following characteristics:

Maximum heaped volume = 19.6 Bm3
Maximum payload = 34,000 kg
The material hauled is earth with a density of 1825 kg/Bm3

Rolling resistance is 40 kg/t and operating conditions are average with a job efficiency of 45 min/hour.

The haul route comprises of the following sections:

Section 1 (100m) level-loading zone
Section 2 (800m) 5% down grade
Section 3 (100m) level dumping zone
Section 4 (1km) 6% up grade
Section 5 (80m) level turnaround area.

Estimate the machines production under these conditions using the travel time curves given in the Caterpillar Performance handbook.

Reference no: EM13753809

Questions Cloud

Monitor and implement the promotional activities : Prepare a one to two page project update report that outlines the current progress of the marketing activities against the marketing plan and overall objectives. monitor and implement the promotional activities
Describe the marketing strategies and tactics : Briefly overview the marketing activities you are involved in implementing. Describe the marketing strategies and tactics your marketing activities relate to
How were marketing and non-marketing personnel briefed : How were marketing and non-marketing personnel briefed and Summaries stakeholder briefings regard ng their implementation roles
Operations and information management : Operations and Information Management Assignment: You are asked to provide a critical discussion on the implementation of lean which addresses the following questions: Is there a best way to implement lean? Are all organisations suitable for lean imp..
Determine the corrected production for the dozer : Determine the corrected production for the dozer for downhill dozing on a 5% slope, with a 50 minute working hour and an average operator as per the correction factors below.
Determine the loosening costs in the following situation : Determine the loosening costs in the following situation: Machine D11R Tractor with No. 11 single shank ripper in coal Rip spacing 1600mm
Define stripping ratio and give three examples : Define stripping ratio and give three examples of the units it may be expressed in.
Operations that are associated with surface mining : List all the major mining operations that are associated with surface mining.
Draw a plan of a typical strip mine : Draw a plan of a typical strip mine showing all operational features and equipment.

Reviews

Write a Review

Other Engineering Questions & Answers

  Identify at least four of the key decisions made during the

1. identify at least four of the key decisions made during the pre-initiating and initiating processes. do you think

  Games of all kinds are the result of a process that

you will explore a game through the lens set up by the weekly material.games of all kinds are the result of a process

  Design an appropriate ventilation system

Design an appropriate ventilation system for production for whole mine through ventilation and develop an appropriate auxiliary ventilation system for stope development

  How rayleigh scattering occurs in optical fiber cable

how rayleigh scattering occurs in optical fiber cable? explain

  When the athlete has lifted the bar to the top of the lift

When the athlete has lifted the bar to the top of the lift, what is the potential energy of the bar?

  Task 1part onea research strategy is a plan of action that

task 1part onea research strategy is a plan of action that gives direction to your efforts enabling you to conduct your

  Formulate a binary linear programming model

Formulate a binary linear programming model for the above inspection planning problem by defining you decision variables and writing the objective and objective function and the constraints in terms of your decision variables. Combine everything t..

  What is the primary assumption behind using an analyst

What is the primary assumption behind using an analyst and what is the purpose behind the data collection?

  Determine how many units of each product to produce

Determine how many units of each product to produce so as to maximize profit. For each unit of product 1, 1 unit of frame parts and 2 units of electrical components are required.

  What are two key elements of a sis

CI-3110 - Give key reasons for the BP Texas City refinery explosion. What are recommendations to prevent further catastrophic event and what does SIS include

  Dimension of the unit cell of andalusite crystal structure

What is happening to the a 0 dimension of the unit cell of the andalusite crystal structure, when it is being heated?

  Design a building which is located in tasmania

Assignment is about design a building which is located in Tasmania- Describe the renewable energy resources that might be available in the geographic region of interest. How would you harness the energy?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd