Brunswick Motors

Recently, Phil Harris, the production control manager at Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning.

Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown below. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram below. Phil noted that the gear box is assembled by the Subassembly Department and subsequently is sent to the main engine assembly line. The input shaft is one of several component parts manufactured by Brunswick that are needed to produce a gear box subassembly.

Thus, levels 0, 1, and 2 are included in the product structure diagram to indicate the three manufacturing stages that are involved in producing an engine: the Engine Assembly Department, the Subassembly Department, and the Machine Shop.

The manufacturing lead times required to produce the gear box and input shaft components are also indicated in the product structure diagram. Note that two weeks are required to produce a batch of gear boxes and that all the gear boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of input shafts, and all the shafts that are needed for the production of gear boxes in a given week must be delivered to the Sub assembly Department stockroom before Monday morning of that week.

In preparing the MRP example Phil planned to use the worksheets shown on the next page and to make the following assumptions:

1. Seventeen gear boxes are on hand at the beginning of Week 1, and five gear boxes are currently on order to be delivered at the start of Week 2.

2. Forty input shafts are on hand at the start of Week 1, and 22 are scheduled for delivery at the beginning of Week 2.

Questions

1. Initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period. Using the following forms, calculate the net requirements and planned order releases for the gear boxes and input shafts.

Assume that lot sizing is done using lot-for-lot (L4L).

2 Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. These costs are as follows:

Given the cost structure, evaluate the cost of the schedule from question 1. Assume inventory is valued at the end of each week.

3 Find a better schedule by reducing the number of orders and carrying some inventory. What are the savings with this new schedule?

Attachment:- Inventory Mangement.rar

Answered:-

Verified Expert

The task is based on the concept of Inventory Management. The problem is case specific and has been solved as per the requirements mentioned in the case and the application of the conceptual formula of the topic. The entire solution has been provided in excel. It consists of 3 parts that have been solved separately.



Put your comment
 
View Conversion
Minimize
  1. user image
    inf1448984

    Quick and productive. I couldn't be more joyful with this expert! I would utilize once more. This is a marvelous author, she does 5 star work for an A+ paper, My task was for a Professional Counseling Master's Program

  2. user image
    inf1448984

    Please use attached excel sheet MGT-655-RS-T3-InventoryMangement-Student 5.xlsx wk 3 assign.docx part cost 2.docx Model 1000 master schedule does not contain the demand units for week 5 and 9. Should they be considered as zero? Yes, I would consider them as 0



Ask Question & Get Answers from Experts
Browse some more (Managerial Accounting) Materials
Describe the importance of the cash/flow conversion cycle. 2) Compare and contrast various current asset management techniques. 3) Compare and contrast the various methods o
As the management accountant, you are responsible for setting costs for your manufacturing company's products, prior to setting the budget for the upcoming year.
Prepare a Statement of Cost of Goods Manufactured and an Income Statement for the month of May - calculate the over/under applied overhead - what is the estimated total cost o
Triple Play Sports manufactures baseball gloves. Information related to a recent production period is as follows: What might have caused the amount of overhead applied to be d
Analyze the physical flow for In the DoghouseIn the Doghouse produces wooden doghouses with shingled roofs. At the beginning of June, there were 300 units in BWIP with costs o
Write a 1,050- to 1,400-word paper in which you describe the relationship between strategic and financial planning. Describe some of the key activities that are a part of bo
Determine the company's predetermined overhead application rate - Determine the additions to the Work-in-Process Inventory account for direct material used, direct labor, and
Find an article about a specific company using a balanced scorecard. Cite the URL and summarize the article, including citing some specific measures and objectives as well a