A hydraulic shovel will be used to excavate sandy clay and load into a 12 BCY dump trucks. The shovel's production at a 100% efficiency is estimated to be 300 BCY/h. and efficiency is 0.80. Truck travel time is estimated to be 8.0 minutes, and truck fixed cycle time (excluding loading ) is estimated to be 2 minutes. Equipment cost for the shovel and trucks are $40/hr and $20/hr respectively.

Calculate the expected production and unit cost of loading and hauling if the truck fleet consists of five trucks.




Put your comment
 
Minimize


Ask Question & Get Answers from Experts
Browse some more (Civil Engineering) Materials
EGB123 Civil Engineering Systems Assignment: Major Civil Engineering Initiative Position Paper. As an individual you are to prepare a position (term) paper on a current major
Due to a crash at a railroad crossing, an overpass is to be constructed on an existing level highway. the existing highway has a design speed of 50 mi/h.
during the next month, the amount of water available for a city is lognormally distributed with a mean of 1 million gallons and a c.o.v. of 40%, where as the total demand is
An 80-mil (2 mm) HDPE geomembrane with an allowable stress of 1,300 lb/in2 rests on a 3(H):1(V) side slope. A 18-inch thick cover soil with a unit weight of 110 lb/in3 (also
A cylindrical specimen of a metal alloy is stressed in compression. if its original and final diameters are 40.00mm and 40.10mm respectively, and its final length is 120.00mm
what are the possible combinations of inflow and outflow of water in the tank in a given day. if the water level in the tank is 7ft from the bottom at the start of day, what
A highway reconstruction project is being undertaken to reduce crash rates. the reconstruction project involves a major realignment of the highway such that a 60mi/h design
A water treatment plant is being designed for a flow of 1.6 m^3/s. How many rapid sand filters, using only sand as the medium, are needed for this plant if cross-sectional a