What are probable solutions to rectify the situation, Civil Engineering

Assignment Help:

Question

If in case mud waves occur during reclamation, what are probable solutions to rectify the situation?


Answer

(i) Option 1 - Complete Removal of All Disturbed Mud
To take away all disturbed mud once mud waves occur is fastest means to treat problem. Later than that, filling material is used for replacing disturbed mud. Though, this alternative is a rather costly option because it involves dredging of all disturbed mud and replacement of large quantity of fill.

(ii) Option 2 - Accelerated consolidation of Disturbed Mud
This alternative involves placement of surcharging loads on top of mud waves, mutually with installation of band drains to accelerate consolidation of disturbed mud. This scheme suffers from drawback that enough long time is required for consolidation process of mud.

(iii) Option 3 - Partial Removal of Disturbed Mud
This alternative is a combination of first two options in which top weak layer of mud is removed even as lower mud is treated with surcharging with band drain installation.

 


Related Discussions:- What are probable solutions to rectify the situation

Calculate roller production, Calculate Roller Production An excavating ...

Calculate Roller Production An excavating contractor determined through a test strip, that a smooth steel-wheel vibrating roller compactor operating at 3-mph can compact a 6-in

HJJJJKKK, #questiRJTIEJITIUDUAIIGIIYHU7S7URURE78ITIT8Y88R6ET8Y86U895R7YRGLH...

#questiRJTIEJITIUDUAIIGIIYHU7S7URURE78ITIT8Y88R6ET8Y86U895R7YRGLHKGJFn..

#title., Ask question #Minimum 100 words accepted2812539076# you

Ask question #Minimum 100 words accepted2812539076# you

Lines, find the equation of the line with slope 4 and passing through the p...

find the equation of the line with slope 4 and passing through the point of intersection of the line x+6y-4=0 ad 3x-4y+2=10

Determine the characteristic load for structure, Determine the Characterist...

Determine the Characteristic Load for structure The Load, which has 95 percent probability of not being exceeded during the life of a structure, is considered as characteristic

Define the predominant factor in atmospheric corrosion, Define the Predomin...

Define the Predominant factor in atmospheric corrosion? The predominant factor in atmospheric corrosion in areas located above splash zone is moisture as there is an excess ava

Pre-tensioned concrete elements, Pre-tensioned concrete elements It is ...

Pre-tensioned concrete elements It is the act of transferring the stress in prestressing tendons to the concrete member. In the case of pre-tensioned concrete elements, this st

Marine piles circular in cross section, Question Give reason that why a...

Question Give reason that why are most marine piles circular in cross section? Answer As marine piles, there are a number of options existing for selection, name as H-

Calcculate the material costs, A capital improvement project requires the i...

A capital improvement project requires the installation of a property line fence along the 250-ft Northern boundary line.The decorative aluminum fence is constructed of posts space

Projects, GIS AND REMOTE SENSING

GIS AND REMOTE SENSING

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd