Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
Question
If in case mud waves occur during reclamation, what are probable solutions to rectify the situation?
Answer
(i) Option 1 - Complete Removal of All Disturbed Mud To take away all disturbed mud once mud waves occur is fastest means to treat problem. Later than that, filling material is used for replacing disturbed mud. Though, this alternative is a rather costly option because it involves dredging of all disturbed mud and replacement of large quantity of fill.
(ii) Option 2 - Accelerated consolidation of Disturbed Mud This alternative involves placement of surcharging loads on top of mud waves, mutually with installation of band drains to accelerate consolidation of disturbed mud. This scheme suffers from drawback that enough long time is required for consolidation process of mud.
(iii) Option 3 - Partial Removal of Disturbed Mud This alternative is a combination of first two options in which top weak layer of mud is removed even as lower mud is treated with surcharging with band drain installation.
Measurement quantity of excavation, concrete, formwork as my assignment brief.
Question Now, mainly flap valves are ended of HDPE. What is the major compensation of using HDPE as compared with cast iron? Answer (i) It has no response with sewage
Determine the flow velocity in 2,000 ft of 8 inch diameter piping flowing full. The energy lost in piping is 54 ft. Use nominal pipe diameter and C = 140. Solution: Use v =
Ask question Design the pavement by group index method for heavy traffic using following subgrade data Soil passing 75micron sieve =65%,liquid limit =40%plastic limit =20% #Min
metal sizes required and adopted question #Minimum 100 words accepted#
example of continuity
why water is necessary for concrete
Strength: The strength of aggregates is determined from one of the three tests : Aggregate Impact Test In which the aggregates in a mould are subjected to impact caus
Q. Protection of line in case of ‘STOP DEAD RESTRICTION' for carrying out a work of short duration on a single line section on a B.G. route Ans. Protection in block sectio
The soil in a borrow pit has a void ratio of 0.90. A fill-in-place volume of 20,000 m 3 is to be constructed with an in-place dry density of 18.84 kN/m 3 . If the owner of borr
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd