What are probable solutions to rectify the situation, Civil Engineering

Assignment Help:

Question

If in case mud waves occur during reclamation, what are probable solutions to rectify the situation?


Answer

(i) Option 1 - Complete Removal of All Disturbed Mud
To take away all disturbed mud once mud waves occur is fastest means to treat problem. Later than that, filling material is used for replacing disturbed mud. Though, this alternative is a rather costly option because it involves dredging of all disturbed mud and replacement of large quantity of fill.

(ii) Option 2 - Accelerated consolidation of Disturbed Mud
This alternative involves placement of surcharging loads on top of mud waves, mutually with installation of band drains to accelerate consolidation of disturbed mud. This scheme suffers from drawback that enough long time is required for consolidation process of mud.

(iii) Option 3 - Partial Removal of Disturbed Mud
This alternative is a combination of first two options in which top weak layer of mud is removed even as lower mud is treated with surcharging with band drain installation.

 


Related Discussions:- What are probable solutions to rectify the situation

Concrete, Determine the quantity of materials required per batch and probab...

Determine the quantity of materials required per batch and probable output from a concrete mixing plant of 1200lts capacity. The design per 1000lts of mixed concrete is as follows

Consultant , how to convert a varying distributed load to a uniformly distr...

how to convert a varying distributed load to a uniformly distributed load

Paint system to protect steelwork from corrosion, Q. Paint system to protec...

Q. Paint system to protect steelwork from corrosion? In a typical painting system, there are generally three main layers primer, undercoat and finishing coat. Primer acts as th

Yugty, #quesjjhjhhjtion..

#quesjjhjhhjtion..

Determine the probable period of time, A clay stratum is 4.5 m thick and re...

A clay stratum is 4.5 m thick and rests on a rock surface. The coefficient of consolidation of a sample of this clay was found to be 4.5 × 10-8 m 2 /s in the laboratory. Verify pro

How to calculate the combined stresses, Compute the stresses at top and bot...

Compute the stresses at top and bottom fibers in a simply supported pre-stressed concrete beam with a rectangular cross section, 250 mm wide and 450 mm deep, as shown in Figure, at

Standard mixes of concrete, In some nations such as Britain, specification ...

In some nations such as Britain, specification for concrete doesn'tusually require cube tests for standard mixes of concrete. Quality control of standard mixes in Britain is achiev

Briefly explain about artificial cut offs, Q. Briefly explain about Artific...

Q. Briefly explain about Artificial cut offs? Alignment of a cut off is chosen so that approach and exit ends remain more or less tangential to the river course. A cut off can

#tile.., Material for formwork and their specifications

Material for formwork and their specifications

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd