What are probable solutions to rectify the situation, Civil Engineering

Assignment Help:

Question

If in case mud waves occur during reclamation, what are probable solutions to rectify the situation?


Answer

(i) Option 1 - Complete Removal of All Disturbed Mud
To take away all disturbed mud once mud waves occur is fastest means to treat problem. Later than that, filling material is used for replacing disturbed mud. Though, this alternative is a rather costly option because it involves dredging of all disturbed mud and replacement of large quantity of fill.

(ii) Option 2 - Accelerated consolidation of Disturbed Mud
This alternative involves placement of surcharging loads on top of mud waves, mutually with installation of band drains to accelerate consolidation of disturbed mud. This scheme suffers from drawback that enough long time is required for consolidation process of mud.

(iii) Option 3 - Partial Removal of Disturbed Mud
This alternative is a combination of first two options in which top weak layer of mud is removed even as lower mud is treated with surcharging with band drain installation.

 


Related Discussions:- What are probable solutions to rectify the situation

Define safety precaution for underwater inspection of bridge, Define Safety...

Define Safety Precautions for Underwater Inspection of Bridge? The working agency should have its own diving safety manual, which should be strictly followed. This manual shoul

Main purpose of conducting load test for piling works, Question What is...

Question What is main purpose of conducting load test for piling works ? Answer Pile load test gives information on ultimate bearing ability but not settlement be

Timber, uses of timber in civil engineering field and its physical state an...

uses of timber in civil engineering field and its physical state and chemical formula or symbol?

Grouted or penetration macadam, Grouted or Penetration Macadam: This ...

Grouted or Penetration Macadam: This is a specification where the binder is sprayed on a compacted layer of stone aggregates and is allowed to penetrate and bind the aggregat

Alluvial streams, Alluvial Streams: In alluvial streams, the regime w...

Alluvial Streams: In alluvial streams, the regime width of a river is calculated from the Lacey's formula : W = 4.8 Q ½ where  W = Regime width in m, and Q = Discha

Concrete mix design for Volumetric site mix, Please advise what is the prop...

Please advise what is the proportion of mix to achieve 45N/sq. mm compressive strength with 370Kg.SR cement per cubic meter and 35N/Sq.mm strength with OPC cement 330 kg per cubic

Explain standard penetration test used in soil exploration, Explain the "St...

Explain the "Standard Penetration Test" used in soil exploration. List the information that can be obtained by the test when made in (a) clay, (b) sand. Comment on the correctio

Insulating washer between steel bolts and aluminium plates, Q. Insulating w...

Q. Insulating washer between steel bolts and aluminium plates? Corrosion of aluminium can be activated by putting it in contact with another metal in the presence of water. Thi

Hydraulics, A tank with vertical sides contain 3m of water in the bottom, o...

A tank with vertical sides contain 3m of water in the bottom, overlain by 4m of oil with no intermixing. Draw pressure diagram due to the oil and water on one of the tank sides and

Functions of cap block drive cap and pile cushion, Question What are ma...

Question What are main functions of cap block drive cap and pile cushion in driven piles? Answer Cap block is fit amid hammer end and drive cap to manage hammer bl

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd