What are probable solutions to rectify the situation, Civil Engineering

Assignment Help:

Question

If in case mud waves occur during reclamation, what are probable solutions to rectify the situation?


Answer

(i) Option 1 - Complete Removal of All Disturbed Mud
To take away all disturbed mud once mud waves occur is fastest means to treat problem. Later than that, filling material is used for replacing disturbed mud. Though, this alternative is a rather costly option because it involves dredging of all disturbed mud and replacement of large quantity of fill.

(ii) Option 2 - Accelerated consolidation of Disturbed Mud
This alternative involves placement of surcharging loads on top of mud waves, mutually with installation of band drains to accelerate consolidation of disturbed mud. This scheme suffers from drawback that enough long time is required for consolidation process of mud.

(iii) Option 3 - Partial Removal of Disturbed Mud
This alternative is a combination of first two options in which top weak layer of mud is removed even as lower mud is treated with surcharging with band drain installation.

 


Related Discussions:- What are probable solutions to rectify the situation

Underwater problems in bridge construction, Q. Underwater problems in bridg...

Q. Underwater problems in bridge construction? The major bridge construction materials are steel and concrete. In the past, stone and brick masonry, with lime mortar as binding

Determine the thickness of flexible pavement layer, Determine the thickness...

Determine the thickness of flexible pavement layer 2 given the following:  FACTS: Total Structural Number required = 7.0 Total number of layers = 2 Layer 1 consists of

Calculate the fuel consumed, A 160-HP Diesel engine (peak fuel consumption ...

A 160-HP Diesel engine (peak fuel consumption = 0.04-gal/HP-hr) hydraulic excavator operates on a cycle time of 20 seconds during a 50-min/hr.  During the filling of the bucket cyc

Fly levelling, we are given a project on field.i''d like to know about how...

we are given a project on field.i''d like to know about how to start n proceed vd fly levelling in the field

WBM Road, if the WBM Road is constructed with 80mm , 40mm metal what will b...

if the WBM Road is constructed with 80mm , 40mm metal what will be the depreciation factor per year, how much thickness of the layer will be reduced per year due to trafic and rai

Surveying, why we perform survey work from whole to the part?

why we perform survey work from whole to the part?

Ranging, defference between direct and indirect ranging..

defference between direct and indirect ranging..

Major drawbacks of using inverted siphons, Question What is key application...

Question What is key application of inverted siphons? What are major drawbacks of using inverted siphons ? Answer Inverted siphons are planned at locations in which sewer s

Bridge loadings, Bridge Loadings: Loadings of bridges have been standa...

Bridge Loadings: Loadings of bridges have been standardized by the Roads Congress. The major features of the various load classes are given below : Bridges and culvert

Cement, Ask What is the density of cement?

Ask What is the density of cement?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd