Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
Question
If in case mud waves occur during reclamation, what are probable solutions to rectify the situation?
Answer
(i) Option 1 - Complete Removal of All Disturbed Mud To take away all disturbed mud once mud waves occur is fastest means to treat problem. Later than that, filling material is used for replacing disturbed mud. Though, this alternative is a rather costly option because it involves dredging of all disturbed mud and replacement of large quantity of fill.
(ii) Option 2 - Accelerated consolidation of Disturbed Mud This alternative involves placement of surcharging loads on top of mud waves, mutually with installation of band drains to accelerate consolidation of disturbed mud. This scheme suffers from drawback that enough long time is required for consolidation process of mud.
(iii) Option 3 - Partial Removal of Disturbed Mud This alternative is a combination of first two options in which top weak layer of mud is removed even as lower mud is treated with surcharging with band drain installation.
explanation for damping ration
Retaining Walls: Needed to retain the fill portion, and generally constructed in dry stone masonry with pucca bunds (Figure). Figure: Typical Design for a Retaining
Importance of racking load for a pre-stressed concrete beam Evaluation of cracking load for a pre-stressed concrete beam member is important for the following cases/reasons.
Ask question #Minimum 2000 words accepted#
Question Will it worthwhile to take out tests on particle density of soil particles for geotechnical design? Answer Particle density of soils is definite by ratio of
ADVANTAGE OF FLEMISH BOND
#questiohin..
Explain the Analysis of Singly Reinforced Rectangular Beams: 1. Determine the area of steel reinforcement, As. Multiply the number of bars by the area of each bar. 2. Calcul
1. On a 5-acre level terrain building site, an earthwork contractor has instructed her crew to strip and grub the topsoil of a 60,000-ft 2 proposed building pad to a minus 2-ft su
Good evening. I have two homework projects from the Soil Mechanics. I am interesting if anybody can solve them.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd