Waste water treatment, Mechanical Engineering

Assignment Help:

Q. Waste Water Treatment?

Typically, there are a number of waste water streams which need to be treated before disposal to land or water. Depending on the nature of contamination and the required discharge quality, significant treatment facilities may be required (including tanks, chemical dosing, skimmers, separators, cooling towers, aeration ponds, evaporation ponds, wetlands, etc.).

These are typically located away from, and downwind of, other plant facilities as there can be risk of odor and airborne bacteria (legionella). Surface water drains and sumps for collecting spillage are engineered by the civil design group. Agreement on the location of these drains with civil design department is required. Generally, surface water will run from the high point of paving, centre line of pipe racks, to collection grids, and into a collection pond.

Buried services are usually limited to firewater ring mains, cooling water and process drains to sumps. They need to be located early in the design, in co-ordination with the Civil Department. Local authorities may require buried process lines and sumps to secondary containment. Refer to applicable regulation. Waste treatment units are usually located in Offsite areas and should be designed to prevent contamination of local waterways, and located away from and downwind of any local communities. Sludge removal by road tanker may be required.


Related Discussions:- Waste water treatment

The motorcycle , Motorcycle, we have learnt about the various parts of a mo...

Motorcycle, we have learnt about the various parts of a motorcycle and their functions. Technical specifications of various models of motorcycles launched by the HHML were also not

Weld preparation-joint tolerance-cleaning, WELD PREPARATION: Joint Toleranc...

WELD PREPARATION: Joint Tolerance & Cleaning   Joint Tolerance The allowable tolerance of joint dimensions depends upon whether the welding is to be done manually or

Feed speed-spindle rpm-cutting time material removal rate, A hole of 25 mm ...

A hole of 25 mm diameter and 62.5 mm depth is to be drilled. The suggested feed is 1.25 mm/rev.and the cutting speed is 60 m/min. Assume the clearance height is 5 mm. Determine: f

Pmi testing of alloy materials, Q. Show PMI testing of alloy materials? ...

Q. Show PMI testing of alloy materials? Suppliers and Construction Subcontractors are required to verify or conduct PMI testing of alloy materials that they procure and use and

Final project , Hi ... I have a final project I need to finish it soon abou...

Hi ... I have a final project I need to finish it soon about 3 weeks from now ... to design any machine by the Solidworks program .... please feed me back if you can .. thank you

Equipment for resistance welding, EQUIPMENT FOR RESISTANCE WELDING The ...

EQUIPMENT FOR RESISTANCE WELDING The equipment for resistance welding is different from that for arc welding for the following reasons: Resistance welding machines are complica

Idle circuit of motorcycle, Idle Circuit : During Idling while the th...

Idle Circuit : During Idling while the throttle valve is almost closed the vacuum is very high at Venturi area and no air-fuel mixture is drawn through the main circuit, as t

Fluid Mechanics, Please help me solve the following problem. Steam is thro...

Please help me solve the following problem. Steam is throttled from a pressure of 700kPa to 100kPa and a temp. of 100 degrees Celsius. Determine the dryness factor of the steam

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd