Value steam mapping, Supply Chain Management

Assignment Help:
Kateville Textile Printing Company Ltd
Introduction
Kateville Textile Printing Company Ltd. design company which produces design fashion products and distribute to all branches of Stockwell Supermarket Chain Stores Ltd. The company’s currently functional layout in the shop floor has some operational problems which forced production to use large batch quantities due to the high set up times resulting in high build up in-process stock.
The company is looking to improve their competitiveness through the implementation of lean concepts to improve the manufacture of well designed men’s and women’s wears as well as children’s wear for an overseas market.
Customer Report:
Customer requirement: One daily shipment of 600 units to Stockwell Supermarket Chain Stores Ltd. The buyer, Kateville Textile Printing Company Ltd places weekly orders to Gennie Fabrics Ltd., the supplier by fax for 1,200units inventory to be supplied direct to production site.

Production Control Department:
I. Receives Stockwell Supermarket Chain Stores Ltd. 800 daily forecast and enter them into the MRP system
II. Issue weekly orders to supplier, Kay Fabrics
III. Secure 1,500 unit raw materials delivery by weekly fax order release
IV. Generate weekly department MRP requirement based upon customer order, WIP, F/G inventory levels and anticipate scrap and down tme.
V. WIP between cutting and screen print = 600units
VI. WIP between screen print and sewing = 1,600units
VII. Finished Goods Inventory = 2,500units
VIII. Manual daily directives from Production Supervisor

Based on the week forecasts, production department releases daily manual information through the Factory Supervisor to the shop floor.
Additional Information:
• Movement of production materials through the process is by push system
• Supplier delivery takes 3 days and hold ups between cutting and screen print takes 2 days.
• Queuing between screen print and sewing takes 2 days whilst finish goods remain at the warehouse five days before shipment to Kateville Textile Printing Company Ltd.

Process Information
A. Cuttings
i. 5 operators
ii. Cycle time = 4mins
iii. Changeover time = 65mins
iv. Uptime = 85%
v. 2 Shifts


B. Screen Print
i. 3 operators
ii. Cycle time = 14mins
iii. Changeover = 65mins
iv. Uptime= 80%
v. 3 Shifts

C. Sewing
i. 15 operators
ii. Cycle time= 18mins
iii. Changeover = 35mins
iv. Uptime = 95%
v. 1 shift

D. Shipping Department
Remove sewed dresses from finished goods warehouse and stages them for truck shipment to customer.

Requirement:
Question 1
From the above information create and comment on the current state map of Kateville Textile Printing Company Ltd. (14marks)
Question 2
From Q1 design to improve the manufacturing systems at a cell level using lean techniques to create a future state map and comment with justification any actions taken in arriving at your decision. (15marks)

Related Discussions:- Value steam mapping

Carrier selection, List factors that typically influence carrier selection...

List factors that typically influence carrier selection and briefly describe how each one influence the selection

What is pestle analysis, Question 1: Explain the need for category managem...

Question 1: Explain the need for category management - Adds strategic value - Optimizes supplier relationship - Cultivates sustainable relationships with suppliers - S

Integrate external suppliers, Case study on DIMCO they have multi external ...

Case study on DIMCO they have multi external suppliers - 10 regional (6 in US and 4 out). each has 12 local distributors that supply 35 retailers. recommendations to integrate the

Explain the structure of supermarket supply chain, Explain the structure of...

Explain the structure of supermarket supply chain. Categorisation in the structure of supermarket supply chain - Farmers or primary producers, members of cooperative groups, Pr

FACEBOOK VALUE CHAIN ANALYSIS YEAR 2012, FACEBOOK VALUE CHAIN AND THE EVAL...

FACEBOOK VALUE CHAIN AND THE EVALUATION BASED ON THE PRIMARY ACTIVITIES AND SECONDARY ACTIVITIES

Eoq model, #question Tom Rich and Joe Miser have an e-checking/savings acc...

#question Tom Rich and Joe Miser have an e-checking/savings account at the eKU bank. Both Tom and Joe had $5000 in their account at the start of the calendar year 2013. Both have

Explain the stages in food product development process, Explain the Stages ...

Explain the Stages in food Product development Process? Food Product Development Process: The food product coordinates the technology used by the company and its culture to de

Logistics, Discuss the logistics strategies

Discuss the logistics strategies

Material handling, what are the factors that affect materials handling

what are the factors that affect materials handling

Transportation, Add a dummy supply source to make it a balanced problem. Us...

Add a dummy supply source to make it a balanced problem. Use the least cost method and determine a shipping schedule and total cost of transportation

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd