Nitin's  production line has three machines A, B, and C, with Reliabilities of 0.99. 0.96, and 0.93, respectively. The machines are arranged so that if one breaks down, the others must shut down. Engineers are weighing 2 two alternative designs for increasing the lines, reliability.  Plan one involves adding an identical back up line, and plan two involves providing a backup for each machine. In either case, three machines (A, B, C ) would be used with reliabilities equal to the original three.

a) Which plan will provide the higher reliability? Show all your calculations.
                                 
b) Describe why the two reliabilities are the same.
                      

c) What other factors may enter into the decision in which plan to adapt?
                                           
(d) Suppose that the single switch used in plan on98% reliable, while readabilities of the machine remain the same. Recalculate the ratability of plan one. Compare the reliability of this plan with the ratability of plan one calculated in solving the original problem. How much did the ratability of plan one decrease as a result of a 98% reliable switch?
                                       

e)  Suppose that the three switches used in plan two are all 98% reliable, while reliabilities of the machines remain the same. Recalculate the reliability of plan two. Compare the reliability of this plan with the reliability of plan two calculated in solving the original problem. How much did the reliability of plan two decreases?


Related Discussions:- The higher reliability

Maintenance 1 mechanic & servicing 50 machine described, M aintenance shop...

M aintenance shop employing one mechanic and servicing 50 machines would be described as a   a.     Single-channel, priority system. b.     Multi-channel, infinite cal

Capital asset pricing model, Capital Asset Pricing Model (CAPM): Part ...

Capital Asset Pricing Model (CAPM): Part of the huge capital market assumption that attempts to quantify investment risk. Under CAPM, systematic risk is calculated by a statis

Value Chain, Value chain for construction company

Value chain for construction company

Limitation of work sampling, Limitation of Work Sampling: 1. It is o...

Limitation of Work Sampling: 1. It is of little value in helping to improve work method and doesn't offer some of the opportunities for methods analysis that acc

Neoclassical, disadvantages of neoclassical

disadvantages of neoclassical

Vales, what is the differnce of customer value and the value the customer g...

what is the differnce of customer value and the value the customer gains from owing

Concept of PLC and video games, considering the concept of product life cy...

considering the concept of product life cycle where would you put the video games in their life cycle

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd