Siting departments for process layout - manufacturing, Operation Management

Assignment Help:

Siting Departments for Process Layout - Manufacturing

One of the most significant features of the siting of departments in a process layout is its surprising complexity. Even if we ignore the different possible shapes in which individual departments could be configured, there are n-factorial (n!) ways of arranging 'n' departments. For example, if there are 5 departments there are 120 possible arrangements (5! = 5 × 4 × 3 × 2 × 1 = 120); if there are 6 departments there are 720 arrangements; if there are 20 departments, then there are 2,432,902,008,176,640,000 possibilities (if you try to say this number you may struggle; it certainly ends with 'nine hundred and two trillion, eight billion, one hundred and seventy six million, six hundred and forty thousand').

895_Siting Departments for Process Layout – Manufacturing.png

If alternative shapes of department are brought into consideration, then, to all intents and purposes, there is an infinite number of feasible layouts. In the face of this combinatorial complexity, how then are we to proceed? In the manufacture of products, a popular measure of layout effectiveness is its effect on material movement costs. If minimising these costs is a major criterion, a cut-and-try method of layout design is available, based on analysis of loads and their movement costs. We will illustrate the method using a simple example. The departments listed in this figure are to be laid out in a building of dimensions 50m × 30m. The grid in part (a) of the figure indicates the area required by each department, and the estimated number of load-movements per day between departments. For example, it is estimated that there will be 60 daily movements between the milling and grinding departments. The grid in part (b) of the figure indicates the estimated costs per metre of load-movement between departments.

For simplicity, it has been assumed that these costs are independent of direction ie the cost of movement from, say, milling to grinding is the same as from grinding to milling. The entries in the grid of part (c) are calculated as the product of the corresponding cells of (a) and (b), and represent the anticipated daily costs per metre travelled. For example, for every metre separating assembly and shipping it will cost £75 per day (ie 30 load-movements per day × £2.50 per load-metre travelled). The next step is to draw a schematic representation (see figure) of the departments, Schematic relationship diagram linked by arcs accentuated in accordance with the cost per metre per day. This initial arrangement may be chosen arbitrarily. This graphical representation facilitates the visualisation of alternative configurations that might reduce the total costs of movement.

The figure below on the left shows an amended diagram resulting from such scrutiny. It now remains to fit this arrangement to the space available, whilst observing the individual area requirements of the departments. The figure on the right shows one of many layouts which could have been drawn, all conforming to the relationships of the first figure. Before going on to complete the detailed design of this layout, other issues would be considered, including such things as the positions of roof- supporting pillars and other obstructions, provision of passageways, access for fork-lift trucks, etc. For example, although the layout of the right hand figure above may be suitable if the access road (or railway depot) is adjacent to a long side of the building, if it is adjacent to the short side, the layout may have to be amended, as shown in these two figures.


Related Discussions:- Siting departments for process layout - manufacturing

Explain why does it appeal to an approach to leadership, Write several para...

Write several paragraphs describing the aspects of a servant leader. Why does it appeal to an approach to leadership? What are some concerns? Why does servant leadership seem appro

Calculate the total cost of ordering and carrying clay pots, 1. Garden Vari...

1. Garden Variety Flower Shop uses 1000 clay pots a month. The pots are purchased at $3 each. Annual carrying costs per pot are estimated to be 25% of cost, and ordering costs are

Explain vent-promotion bauiness, Hirizontal intergration has benefits to th...

Hirizontal intergration has benefits to the firms involved. Consider the consolidation in the vent-promotion bauiness when Live Nation bought Ticketmaster in 2010. List some specif

Compute the appropriate loan table, You just took a $20,000, eight-year loa...

You just took a $20,000, eight-year loan. Payments at the end of each year are flat (equal in every year) at an interest rate of 8 percent. Calculate the appropriate loan table, sh

Explain a project supply and materials budget, Create a project supply and ...

Create a project supply and materials budget based on the information in the case. I need an example of the supply budget

Class work, define the following key terms in product layout: a) Product in...

define the following key terms in product layout: a) Product interval time b) Product duration (throughput time) c) Assembly line balancing

Explain work in an information technology department, You are talking with ...

You are talking with another MIS 200student who is complaining about having to learn about the information systems development life -cycle (SDLC- Chapter 6), because he is not goin

Describe what is role of a cio in todays global business, 1. What is the ro...

1. What is the role of a CIO in today's global business environment? 2. Dr. Carr presents a good argument in the "IT doesn't matter" reading. Present your view of Carr's central

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd