Siting departments for process layout - manufacturing, Operation Management

Assignment Help:

Siting Departments for Process Layout - Manufacturing

One of the most significant features of the siting of departments in a process layout is its surprising complexity. Even if we ignore the different possible shapes in which individual departments could be configured, there are n-factorial (n!) ways of arranging 'n' departments. For example, if there are 5 departments there are 120 possible arrangements (5! = 5 × 4 × 3 × 2 × 1 = 120); if there are 6 departments there are 720 arrangements; if there are 20 departments, then there are 2,432,902,008,176,640,000 possibilities (if you try to say this number you may struggle; it certainly ends with 'nine hundred and two trillion, eight billion, one hundred and seventy six million, six hundred and forty thousand').

895_Siting Departments for Process Layout – Manufacturing.png

If alternative shapes of department are brought into consideration, then, to all intents and purposes, there is an infinite number of feasible layouts. In the face of this combinatorial complexity, how then are we to proceed? In the manufacture of products, a popular measure of layout effectiveness is its effect on material movement costs. If minimising these costs is a major criterion, a cut-and-try method of layout design is available, based on analysis of loads and their movement costs. We will illustrate the method using a simple example. The departments listed in this figure are to be laid out in a building of dimensions 50m × 30m. The grid in part (a) of the figure indicates the area required by each department, and the estimated number of load-movements per day between departments. For example, it is estimated that there will be 60 daily movements between the milling and grinding departments. The grid in part (b) of the figure indicates the estimated costs per metre of load-movement between departments.

For simplicity, it has been assumed that these costs are independent of direction ie the cost of movement from, say, milling to grinding is the same as from grinding to milling. The entries in the grid of part (c) are calculated as the product of the corresponding cells of (a) and (b), and represent the anticipated daily costs per metre travelled. For example, for every metre separating assembly and shipping it will cost £75 per day (ie 30 load-movements per day × £2.50 per load-metre travelled). The next step is to draw a schematic representation (see figure) of the departments, Schematic relationship diagram linked by arcs accentuated in accordance with the cost per metre per day. This initial arrangement may be chosen arbitrarily. This graphical representation facilitates the visualisation of alternative configurations that might reduce the total costs of movement.

The figure below on the left shows an amended diagram resulting from such scrutiny. It now remains to fit this arrangement to the space available, whilst observing the individual area requirements of the departments. The figure on the right shows one of many layouts which could have been drawn, all conforming to the relationships of the first figure. Before going on to complete the detailed design of this layout, other issues would be considered, including such things as the positions of roof- supporting pillars and other obstructions, provision of passageways, access for fork-lift trucks, etc. For example, although the layout of the right hand figure above may be suitable if the access road (or railway depot) is adjacent to a long side of the building, if it is adjacent to the short side, the layout may have to be amended, as shown in these two figures.


Related Discussions:- Siting departments for process layout - manufacturing

Explain case studies with ethnographic research, 1. What benefits can be ga...

1. What benefits can be gained from case studies? What dangers, if any, are there in using case studies? In what ways are they useful? Support your answers. 2. Provide some exam

Explain procurement management, Which of the nine knowledge areas defined i...

Which of the nine knowledge areas defined in the Project Management Body of Knowledge includes the activities of generating, collecting, distributing, storing, retrieving and dispo

What type of strategy will you utilized to meet this demand, Dell Computers...

Dell Computers is known for revolutionizing the personal computer market using mass customization. This company can turn out a huge volume of computers while still having a variety

Describe how to do in excel, Can you show how to do in excel? Bowman Bui...

Can you show how to do in excel? Bowman Builders manufactures steel storage sheds for commercial use, Joe Bowman, president of Bowman Builders, is contemplating producing sheds

Explain what benefit would using the optimal order quantity, Garden Variety...

Garden Variety Flower Shop uses 760 clay pots a month. The pots are purchased at $2 each. Annual carrying costs per pot are estimated to be 30 percent of cost, and ordering costs a

How do strategic sources help long-term business process, Question 1: W...

Question 1: What are the main characteristics of a Supply Chain? Mutually linked companies and Supplier-Customer relationships Gathers products from supplier to customer al

Productivity challenge in organisations, Productivity Challenge in Organisa...

Productivity Challenge in Organisations Productivity is the ratio of outputs (goods and services) divided by the inputs (resources: labour, capital and services). It is one of

Explain the rop that will provide a risk of stockout, Given this informatio...

Given this information: Expected demand during lead time = 300 units Standard deviation of lead time demand = 30 units Determine each of the following, assuming that lead time dema

Explain all types of worker's participation, Explain all types of worker's ...

Explain all types of worker's participation. Types of Worker's Participation - Worker's participation in management may take several forms, for example:   (a) Formal partici

Explain visual inspection, Develop a forecast for years 2 through 12 using ...

Develop a forecast for years 2 through 12 using exponential smoothing with ? = .4 and a forecast for year 1 of 6. Plot your new forecast on a graph with the actual data and the nai

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd