Siting departments for process layout - manufacturing, Operation Management

Assignment Help:

Siting Departments for Process Layout - Manufacturing

One of the most significant features of the siting of departments in a process layout is its surprising complexity. Even if we ignore the different possible shapes in which individual departments could be configured, there are n-factorial (n!) ways of arranging 'n' departments. For example, if there are 5 departments there are 120 possible arrangements (5! = 5 × 4 × 3 × 2 × 1 = 120); if there are 6 departments there are 720 arrangements; if there are 20 departments, then there are 2,432,902,008,176,640,000 possibilities (if you try to say this number you may struggle; it certainly ends with 'nine hundred and two trillion, eight billion, one hundred and seventy six million, six hundred and forty thousand').

895_Siting Departments for Process Layout – Manufacturing.png

If alternative shapes of department are brought into consideration, then, to all intents and purposes, there is an infinite number of feasible layouts. In the face of this combinatorial complexity, how then are we to proceed? In the manufacture of products, a popular measure of layout effectiveness is its effect on material movement costs. If minimising these costs is a major criterion, a cut-and-try method of layout design is available, based on analysis of loads and their movement costs. We will illustrate the method using a simple example. The departments listed in this figure are to be laid out in a building of dimensions 50m × 30m. The grid in part (a) of the figure indicates the area required by each department, and the estimated number of load-movements per day between departments. For example, it is estimated that there will be 60 daily movements between the milling and grinding departments. The grid in part (b) of the figure indicates the estimated costs per metre of load-movement between departments.

For simplicity, it has been assumed that these costs are independent of direction ie the cost of movement from, say, milling to grinding is the same as from grinding to milling. The entries in the grid of part (c) are calculated as the product of the corresponding cells of (a) and (b), and represent the anticipated daily costs per metre travelled. For example, for every metre separating assembly and shipping it will cost £75 per day (ie 30 load-movements per day × £2.50 per load-metre travelled). The next step is to draw a schematic representation (see figure) of the departments, Schematic relationship diagram linked by arcs accentuated in accordance with the cost per metre per day. This initial arrangement may be chosen arbitrarily. This graphical representation facilitates the visualisation of alternative configurations that might reduce the total costs of movement.

The figure below on the left shows an amended diagram resulting from such scrutiny. It now remains to fit this arrangement to the space available, whilst observing the individual area requirements of the departments. The figure on the right shows one of many layouts which could have been drawn, all conforming to the relationships of the first figure. Before going on to complete the detailed design of this layout, other issues would be considered, including such things as the positions of roof- supporting pillars and other obstructions, provision of passageways, access for fork-lift trucks, etc. For example, although the layout of the right hand figure above may be suitable if the access road (or railway depot) is adjacent to a long side of the building, if it is adjacent to the short side, the layout may have to be amended, as shown in these two figures.


Related Discussions:- Siting departments for process layout - manufacturing

Observation methods, Observation  Methods: The  observation methods i...

Observation  Methods: The  observation methods is the most commonly used  methods  especially in studies  relating to  behavioural sciences. In a way we all observe things aro

Explain advantages of division of labour, Explain advantages of Division of...

Explain advantages of Division of Labour.  As the same worker does similar work repeatedly:- (i) It gains proficiency and skill on the job and becomes a professional. (ii

Describe mpc can run independent of the operation plan, Which of the follow...

Which of the following is true? MPC can run independent of the operation plan. Business failure can result from poor MPC performance. In PAC, order release directly affect

Describe delaying completion of the project, Using the data in Table 13-1, ...

Using the data in Table 13-1, what is the latest possible time that C may be started without delaying completion of the project? Table 13-1 The following represents a project with

Capacity implication, how can make a plan for appropriate capacity of a cin...

how can make a plan for appropriate capacity of a cinema by replacing amount of standard seats with luxury seats?

How several hours of production time would you schedule, For the four basic...

For the four basic configurations that follow, assume that the market is demanding product that must be processed by both Resource X and Resource Y for Cases I, II and III. For Cas

Calculate the path mean and network diagram, For the following data: ...

For the following data:   Time (in Days)   Activity Immediate Predecessor Optimistic Most Likely

Depict a fish-bone chart showing causes of defective product, Boston Electr...

Boston Electric Generators has been getting many complaints from its major customer, House Station, about the quality of its shipments of home generators. Daniel shimshak , the pla

Describe different leadership theories, This week you learned about a numbe...

This week you learned about a number of different leadership theories. Choose two of today's leaders listed below and research on their leadership styles: • Richard Branson •

Explain static and dynamic scheduling problems, 1. What are the implication...

1. What are the implications of not allocating material in a shop order after availability checking? 2. Provide some examples of static and dynamic scheduling problems.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd