Siting departments for process layout - manufacturing, Operation Management

Assignment Help:

Siting Departments for Process Layout - Manufacturing

One of the most significant features of the siting of departments in a process layout is its surprising complexity. Even if we ignore the different possible shapes in which individual departments could be configured, there are n-factorial (n!) ways of arranging 'n' departments. For example, if there are 5 departments there are 120 possible arrangements (5! = 5 × 4 × 3 × 2 × 1 = 120); if there are 6 departments there are 720 arrangements; if there are 20 departments, then there are 2,432,902,008,176,640,000 possibilities (if you try to say this number you may struggle; it certainly ends with 'nine hundred and two trillion, eight billion, one hundred and seventy six million, six hundred and forty thousand').

895_Siting Departments for Process Layout – Manufacturing.png

If alternative shapes of department are brought into consideration, then, to all intents and purposes, there is an infinite number of feasible layouts. In the face of this combinatorial complexity, how then are we to proceed? In the manufacture of products, a popular measure of layout effectiveness is its effect on material movement costs. If minimising these costs is a major criterion, a cut-and-try method of layout design is available, based on analysis of loads and their movement costs. We will illustrate the method using a simple example. The departments listed in this figure are to be laid out in a building of dimensions 50m × 30m. The grid in part (a) of the figure indicates the area required by each department, and the estimated number of load-movements per day between departments. For example, it is estimated that there will be 60 daily movements between the milling and grinding departments. The grid in part (b) of the figure indicates the estimated costs per metre of load-movement between departments.

For simplicity, it has been assumed that these costs are independent of direction ie the cost of movement from, say, milling to grinding is the same as from grinding to milling. The entries in the grid of part (c) are calculated as the product of the corresponding cells of (a) and (b), and represent the anticipated daily costs per metre travelled. For example, for every metre separating assembly and shipping it will cost £75 per day (ie 30 load-movements per day × £2.50 per load-metre travelled). The next step is to draw a schematic representation (see figure) of the departments, Schematic relationship diagram linked by arcs accentuated in accordance with the cost per metre per day. This initial arrangement may be chosen arbitrarily. This graphical representation facilitates the visualisation of alternative configurations that might reduce the total costs of movement.

The figure below on the left shows an amended diagram resulting from such scrutiny. It now remains to fit this arrangement to the space available, whilst observing the individual area requirements of the departments. The figure on the right shows one of many layouts which could have been drawn, all conforming to the relationships of the first figure. Before going on to complete the detailed design of this layout, other issues would be considered, including such things as the positions of roof- supporting pillars and other obstructions, provision of passageways, access for fork-lift trucks, etc. For example, although the layout of the right hand figure above may be suitable if the access road (or railway depot) is adjacent to a long side of the building, if it is adjacent to the short side, the layout may have to be amended, as shown in these two figures.


Related Discussions:- Siting departments for process layout - manufacturing

Explain what is its current yield, Consider a $1,000 par value, 7% annual c...

Consider a $1,000 par value, 7% annual coupon bond. The bond matures in 9 years. Assuming the bonds required return is 10%, what is its current yield? (Semi-annually compounding)

Explain matrix structure and provide examples, Some people argue that the m...

Some people argue that the matrix structure should be adopted only as a last resort because dual chains of command can create more problems that they solve. Discuss and provide exa

Calculate a tracking signal for months, The following are monthly actual an...

The following are monthly actual and forecast demand levels for May thru December for units of a product manufactured by the N. Tamimi Pharmaceutical Company: Month Actual Deman

Implementation of the cost of quality, Question: What are different con...

Question: What are different conditions which a company has to make sure before the implementation of the Cost of Quality? Description/Definition of cost of Quality • The

supply chain, What is the primary objective of supply chain managemen

What is the primary objective of supply chain management

Explain multifactor productivity, The following table shows data on the ave...

The following table shows data on the average number of customers processed by several bank service units each day. The hourly wage rate is $15, the overhead rate is 1.0 times labo

Type of process technologies - continuous of flow production, Type of Proce...

Type of Process Technologies - Continuous of Flow Production Continuous of Flow Production: Batch methods are characterized by the irregularity in the way the work is carried

Define what is the probability that the battery will perform, An undergradu...

An undergraduate business student has purchased a laptop computer for use during exams. This laptop is perfectly reliable except for two parts: its microchip, which has a failure r

Explain investment economically acceptable, Orangemen Lofts plans to add 30...

Orangemen Lofts plans to add 300 luxury apartments to its complex in Cohoes. The cost of the land now is $16 million including taxes and fees. The construction cost is expected to

Do you think taylor''s position is similler applicable today, 1. Do you thi...

1. Do you think Taylor's position is equally applicable today? 2. Looking at Taylor's and Grayson's remarks, whick were made approximately 73 years apart, one has to wonder what

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd