Siting departments for process layout - manufacturing, Operation Management

Assignment Help:

Siting Departments for Process Layout - Manufacturing

One of the most significant features of the siting of departments in a process layout is its surprising complexity. Even if we ignore the different possible shapes in which individual departments could be configured, there are n-factorial (n!) ways of arranging 'n' departments. For example, if there are 5 departments there are 120 possible arrangements (5! = 5 × 4 × 3 × 2 × 1 = 120); if there are 6 departments there are 720 arrangements; if there are 20 departments, then there are 2,432,902,008,176,640,000 possibilities (if you try to say this number you may struggle; it certainly ends with 'nine hundred and two trillion, eight billion, one hundred and seventy six million, six hundred and forty thousand').

895_Siting Departments for Process Layout – Manufacturing.png

If alternative shapes of department are brought into consideration, then, to all intents and purposes, there is an infinite number of feasible layouts. In the face of this combinatorial complexity, how then are we to proceed? In the manufacture of products, a popular measure of layout effectiveness is its effect on material movement costs. If minimising these costs is a major criterion, a cut-and-try method of layout design is available, based on analysis of loads and their movement costs. We will illustrate the method using a simple example. The departments listed in this figure are to be laid out in a building of dimensions 50m × 30m. The grid in part (a) of the figure indicates the area required by each department, and the estimated number of load-movements per day between departments. For example, it is estimated that there will be 60 daily movements between the milling and grinding departments. The grid in part (b) of the figure indicates the estimated costs per metre of load-movement between departments.

For simplicity, it has been assumed that these costs are independent of direction ie the cost of movement from, say, milling to grinding is the same as from grinding to milling. The entries in the grid of part (c) are calculated as the product of the corresponding cells of (a) and (b), and represent the anticipated daily costs per metre travelled. For example, for every metre separating assembly and shipping it will cost £75 per day (ie 30 load-movements per day × £2.50 per load-metre travelled). The next step is to draw a schematic representation (see figure) of the departments, Schematic relationship diagram linked by arcs accentuated in accordance with the cost per metre per day. This initial arrangement may be chosen arbitrarily. This graphical representation facilitates the visualisation of alternative configurations that might reduce the total costs of movement.

The figure below on the left shows an amended diagram resulting from such scrutiny. It now remains to fit this arrangement to the space available, whilst observing the individual area requirements of the departments. The figure on the right shows one of many layouts which could have been drawn, all conforming to the relationships of the first figure. Before going on to complete the detailed design of this layout, other issues would be considered, including such things as the positions of roof- supporting pillars and other obstructions, provision of passageways, access for fork-lift trucks, etc. For example, although the layout of the right hand figure above may be suitable if the access road (or railway depot) is adjacent to a long side of the building, if it is adjacent to the short side, the layout may have to be amended, as shown in these two figures.


Related Discussions:- Siting departments for process layout - manufacturing

Value driven approach, value driven approach to production managemeent

value driven approach to production managemeent

Explain the key factors in effective project control, Identify and describe...

Identify and describe the key factor(s) in effective project control.

division of labour theory, explain term related to historical evolution of...

explain term related to historical evolution of production and operation management

Evidenced predictive capabilities of a leader, Question 1: Traits theor...

Question 1: Traits theories are not sufficient for explaining Leadership! i. Give an account of the other complementary Contingency theories or parts of the theories that d

Capacity planning, outsourcing as external source of capacity

outsourcing as external source of capacity

What is myers-briggs type indicator, Many of us have taken assessments in t...

Many of us have taken assessments in the past, such as the ASVAB (Armed Services Vocational Aptitude Battery) or MBTI (Myers-Briggs Type Indicator); the latter is described in your

Situational Leadership Theory, Describe possible gaps you observe within Si...

Describe possible gaps you observe within Situational Leadership Theory. What strategies or adjustments in your own behavior, thinking, or worldview might you consider or employ to

Explain why are uniform laws like the ucita necessary, Why are uniform laws...

Why are uniform laws like the UCITA and the UETA necessary? Does it make any difference if these uniform laws are not enacted in every state? How should the law be applied to a dis

Describe why you agree or disagree with the results, Write your formal anal...

Write your formal analysis of your Color Q self-assessment results. I will look for the following information What primary and secondary color type are you? (MY COLOR ARE GOL

What are two reasons project management is not good, What are two reasons p...

What are two reasons project management is not well done in corporations? Why? What are some specific examples?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd