Siting departments for process layout - manufacturing, Operation Management

Assignment Help:

Siting Departments for Process Layout - Manufacturing

One of the most significant features of the siting of departments in a process layout is its surprising complexity. Even if we ignore the different possible shapes in which individual departments could be configured, there are n-factorial (n!) ways of arranging 'n' departments. For example, if there are 5 departments there are 120 possible arrangements (5! = 5 × 4 × 3 × 2 × 1 = 120); if there are 6 departments there are 720 arrangements; if there are 20 departments, then there are 2,432,902,008,176,640,000 possibilities (if you try to say this number you may struggle; it certainly ends with 'nine hundred and two trillion, eight billion, one hundred and seventy six million, six hundred and forty thousand').

895_Siting Departments for Process Layout – Manufacturing.png

If alternative shapes of department are brought into consideration, then, to all intents and purposes, there is an infinite number of feasible layouts. In the face of this combinatorial complexity, how then are we to proceed? In the manufacture of products, a popular measure of layout effectiveness is its effect on material movement costs. If minimising these costs is a major criterion, a cut-and-try method of layout design is available, based on analysis of loads and their movement costs. We will illustrate the method using a simple example. The departments listed in this figure are to be laid out in a building of dimensions 50m × 30m. The grid in part (a) of the figure indicates the area required by each department, and the estimated number of load-movements per day between departments. For example, it is estimated that there will be 60 daily movements between the milling and grinding departments. The grid in part (b) of the figure indicates the estimated costs per metre of load-movement between departments.

For simplicity, it has been assumed that these costs are independent of direction ie the cost of movement from, say, milling to grinding is the same as from grinding to milling. The entries in the grid of part (c) are calculated as the product of the corresponding cells of (a) and (b), and represent the anticipated daily costs per metre travelled. For example, for every metre separating assembly and shipping it will cost £75 per day (ie 30 load-movements per day × £2.50 per load-metre travelled). The next step is to draw a schematic representation (see figure) of the departments, Schematic relationship diagram linked by arcs accentuated in accordance with the cost per metre per day. This initial arrangement may be chosen arbitrarily. This graphical representation facilitates the visualisation of alternative configurations that might reduce the total costs of movement.

The figure below on the left shows an amended diagram resulting from such scrutiny. It now remains to fit this arrangement to the space available, whilst observing the individual area requirements of the departments. The figure on the right shows one of many layouts which could have been drawn, all conforming to the relationships of the first figure. Before going on to complete the detailed design of this layout, other issues would be considered, including such things as the positions of roof- supporting pillars and other obstructions, provision of passageways, access for fork-lift trucks, etc. For example, although the layout of the right hand figure above may be suitable if the access road (or railway depot) is adjacent to a long side of the building, if it is adjacent to the short side, the layout may have to be amended, as shown in these two figures.


Related Discussions:- Siting departments for process layout - manufacturing

Explain how many units are needed to break, A manufacturing process has a f...

A manufacturing process has a fixed cost of $150,000 per month. Each unit of product being produced contains $25 worth of material and takes $45 of labour. How many units are neede

Explain federal mediation and conciliation service, Based on the most curre...

Based on the most currently reported data by the American Arbitration Association and the Federal Mediation and Conciliation Service, you should factor all but one of the following

Explain what must the beta of this stock be, A stock has an expected return...

A stock has an expected return of 10.2 percent, the risk-free rate is 4.5 percent, and the market risk premium is 8.5 percent. What must the beta of this stock be?

Explain risks associated with the globalization, Are there any risks associ...

Are there any risks associated with the globalization of health care? Can these risks be mitigated? How

How to compute the expected labor, The following table shows data on the av...

The following table shows data on the average number of customers processed by several bank service units each day. The hourly wage rate is $30, overhead rate is 1.0 times labor co

Explain different levels of diversification firms, What are the different l...

What are the different levels of diversification firms can purpsue by using different corporate level strategies and what are the advantages to diversifying their operations?

Explain groups impact health care quality, Identify and discuss how these g...

Identify and discuss how these groups impact health care quality and patient safety: federal oversight agencies, accrediting bodies, and consumers.

Explain the fixed cost and the variable cost of production, The fixed cost ...

The fixed cost and the variable cost of production of product are 200000USD and demand is 500units to break even unit price of first 300 item will be?

Define performance appraisals are they necessary or not, Performance Apprai...

Performance Appraisals- 1. What purpose do they serve under a performance management system? 2. Performance appraisals are they necessary or not? 3. What to do if a perfor

Assignment on erp jit, how to write a good assignment report on erp jit

how to write a good assignment report on erp jit

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd