Show the benefits of adopting marine fill, Civil Engineering

Assignment Help:

In reclamation involving large volumes of fill and tight programme, shall engineers use marine fill or mud extracted from land borrow area as filling material?

 There are two benefits of adopting marine fill over mud extracted from land borrow area:

(a)  In certain land borrow areas, it includes breaking up of rock to suitable sizes for reclamation and production rate isn't high. With modern equipment for dredging and placing marine fill, the filling rate is much higher.  

(b) Cost incurred for breaking up of rock to suitable sizes for reclamation is very expensive whereas the cost of hydraulic filling with marine fill is lower.


Related Discussions:- Show the benefits of adopting marine fill

Explain template jig, Explain Template Jig? 1) Template jig is the simp...

Explain Template Jig? 1) Template jig is the simplest type of jig, employed for accuracy than speed. 2) This jig fits over, on, or, into the work and is not generally clampe

Compute interior or intersection angle, Compute Interior or Intersection An...

Compute Interior or Intersection Angle for the following circular curve:   Answer- I = 180° - 60° - 60°= 60

Explain shear stiffness in elastomeric bearing, Q. Explain Shear stiffness ...

Q. Explain Shear stiffness in elastomeric bearing? For elastomeric bearing shear stiffness is a significant parameter for design since it influences the force transfer between

Use plain dumb-bell type and center-bulb sort, Question While selection...

Question While selection of waterstop, shall engineers use plain dumb-bell type , center-bulb sort ? Answer Plain dumb-bell kind is used for joint site where sm

Timber, What is exogenous tree?

What is exogenous tree?

Physical deterioration - underwater inspection of bridges, Define Physical ...

Define Physical deterioration - underwater inspection of bridges Typical defects include: -   Scaling -   Cracking -   Spalling -   Disintegration -   Abrasion

Max. moment at cantilever, max. moment at cantilever in up or down of suppo...

max. moment at cantilever in up or down of support or free of end

Determine equipment purchase yields a minimum 15% return, A contractor esta...

A contractor established a policy to purchase equipment over leasing only if the return is a minimum of 15%. Given the following conditions, the contractor's decision based on the

Survey question, Sir morng..i know about WCB AND RB.With diagram..pls help ...

Sir morng..i know about WCB AND RB.With diagram..pls help me sir

Measurement of cement and aggregates, Measurement of cement and aggregates ...

Measurement of cement and aggregates - by weight vs. by volume Measurement of constituents for concrete is usually carried out by weight since of the following reasons: (i)

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd