Show the benefits of adopting marine fill, Civil Engineering

Assignment Help:

In reclamation involving large volumes of fill and tight programme, shall engineers use marine fill or mud extracted from land borrow area as filling material?

 There are two benefits of adopting marine fill over mud extracted from land borrow area:

(a)  In certain land borrow areas, it includes breaking up of rock to suitable sizes for reclamation and production rate isn't high. With modern equipment for dredging and placing marine fill, the filling rate is much higher.  

(b) Cost incurred for breaking up of rock to suitable sizes for reclamation is very expensive whereas the cost of hydraulic filling with marine fill is lower.


Related Discussions:- Show the benefits of adopting marine fill

State the maximum amount of resistance in a pole, State the maximum amount ...

State the maximum amount of resistance in a pole The maximum amount of resistance in a pole is generally required at the base and, so, the maximum cross sectional area is requi

.levelling, differentiate between Dumpy level:The Wye or Y level:Cooke''s r...

differentiate between Dumpy level:The Wye or Y level:Cooke''s reversible level: Cushing''s level:Tilting level and Automatic level

Calculate the most probable value, The most probable value of the following...

The most probable value of the following observations on the same angle (35º 17' 42" ; 35º 17' 38" ; 35º 18' 00" ; 35º 17'; 22"; 35º 17' 42");  is most nearly:   35º 17' 40.8

Dynamic force transfer test of shock transmission unit, Define Dynamic Forc...

Define Dynamic Force Transfer Test of Shock Transmission Unit? This test mainly prove the lock up capability of the device. The STU shall be loaded in tension from zero to the

Levelling, the cooke''s reversible level

the cooke''s reversible level

Define masonry substructure- underwater inspection of bridge, Define Masonr...

Define Masonry substructure- underwater inspection of bridge? In early days, masonry, particularly stone masonry was extensively used for bridge piers and abutments. Typically,

Explain flow measurement with weirs, Explain Flow Measurement with Weirs ...

Explain Flow Measurement with Weirs Fixed plates positioned vertically in an open channel over which flow is directed through an opening. The opening linear distance is termed

Similarity between post and pre tensioned concrete, Similarity between post...

Similarity between post and pre tensioned concrete In the case of  pre-tensioned concrete members, a pattern of  small length and  small width cracks which are more in numbers

Maximum shear stress - state of stress, Maximum shear stress - state of str...

Maximum shear stress - state of stress: Consider the state of stress. (a) According to principal stress theory the equivalent stress for this case is simply σ 1 , i.e. 300

Stone tiles for construction material, Q. Stone tiles for construction mate...

Q. Stone tiles for construction material? For Public toilet bath rooms kitchen etc. we may be use stones tiles ( marble , kota stone , Polished Kuddapa stone or polished Dhura

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd