In reclamation involving large volumes of fill and tight programme, shall engineers use marine fill or mud extracted from land borrow area as filling material?
There are two benefits of adopting marine fill over mud extracted from land borrow area:
(a) In certain land borrow areas, it includes breaking up of rock to suitable sizes for reclamation and production rate isn't high. With modern equipment for dredging and placing marine fill, the filling rate is much higher.
(b) Cost incurred for breaking up of rock to suitable sizes for reclamation is very expensive whereas the cost of hydraulic filling with marine fill is lower.
Determine about the pre-stressed concrete beam A pre-stressed concrete beam has a width of 200 mm and an overall depth of 400 mm. The permissible stresses in tension and compre
which truss is suitable for 19*22m span on which mangalore tiles can be placed or shud steel truss be preferred for such span and which 1 is more profitable in rural desiggn...
Q. What do you mean by Plain elastomeric pads? Plain pads are used for light or moderate loadings. Plain pads have a tendency to bulge under heavy loadings. In order to reduce
Explain Energy Grade Line (EGL) Graph of the sum of the potential, pressure and kinetic energies along a pipe or open channel. Energies are plotted along the y-axis above a dat
Ask question #Explalin a joint frame by stiffness method
Loss of Prestress due to Elastic Shortening of Concrete Due to elastic shortening of concrete, tendons are able to reduce their stretched length to the same extent upto which
stress
Prime Coat: A prime coat is the application of a low viscosity binder, usually a bituminous emulsion, to a gravel, WBM or WMM surface, to enable the binder to fill up the voi
A sample of clay taken from a natural stratum was originated to be partially saturated and when tested in the laboratory gave the following results. Calculate the degree of saturat
Question What are thought in determining whether casings have to be left in for mini-piles ? Answer Contrary to most of pile design, design of min-piles is controlled
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd