Show the benefits of adopting marine fill, Civil Engineering

Assignment Help:

In reclamation involving large volumes of fill and tight programme, shall engineers use marine fill or mud extracted from land borrow area as filling material?

 There are two benefits of adopting marine fill over mud extracted from land borrow area:

(a)  In certain land borrow areas, it includes breaking up of rock to suitable sizes for reclamation and production rate isn't high. With modern equipment for dredging and placing marine fill, the filling rate is much higher.  

(b) Cost incurred for breaking up of rock to suitable sizes for reclamation is very expensive whereas the cost of hydraulic filling with marine fill is lower.


Related Discussions:- Show the benefits of adopting marine fill

Softening point of bitumen, Hi, i need discussion for softening point of bi...

Hi, i need discussion for softening point of bitumen 7.5 ?C

How quality control is maintained in a rolled fill dam, Sketch a curve show...

Sketch a curve showing the relation among dry density and moisture content for Standard Proctor test and indicate the salient features of the curve. Describe why soils are compacte

Failure analysis in designing of a structure, Modes of failure • For sa...

Modes of failure • For safe design, a knowledge of the possible modes of failure is also necessary, e.g. failure of the structure could occur due to - Tensile fracture due t

Desirable characteristics of a pavement, Desirable Characteristics of a Pav...

Desirable Characteristics of a Pavement: In order to fulfill the above function, the pavement has to have the following desirable properties : (a) It should be structurall

Career, does felid scope in civil eng. if we start consiltancy job

does felid scope in civil eng. if we start consiltancy job

Shoes of prefabricated drains, Q. Shoes of prefabricated drains? Shoes ...

Q. Shoes of prefabricated drains? Shoes are generally installed in prefabricated drains for the below : (i)  It avoids the entry of soils in the mandrel by sealing it at the

.levelling, differentiate between Dumpy level:The Wye or Y level:Cooke''s r...

differentiate between Dumpy level:The Wye or Y level:Cooke''s reversible level: Cushing''s level:Tilting level and Automatic level

Main principle of post-grouting for mini-piles, Question What is main p...

Question What is main principle of post-grouting for mini-piles? Answer During course of post-grouting , a tube with a hole at its base is lowered into pile and g

High and narrow beams, Question Give a reason that why are high and na...

Question Give a reason that why are high and narrow beams not desirable in concrete piers? Answer Supported on past experience in other, high and narrow beams after

Well foundation in bridges, what is the purpose of 6mm ms sheet for stainin...

what is the purpose of 6mm ms sheet for staining in various conditions at inner &outer of well

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd