Show the audit work of the given capital project, Auditing

Assignment Help:

In planning the audit work of the Ministry, the audit staff member collected these details relating to the construction of an office complex.

1. In September 1994, the Ministry requested the assistance of the Ministry of Works, for the preparation of plans and preliminary drawings to ‘set up a building to accommodate its departments' of approximately 6000m2 at an estimated budgeted cost of Rs 50 million.

2. In September 1995, an architectural competition was launched with a view to have the best design and the winner was to be engaged as the Consulting Architect subsequently. The design was prepared on a project area of approximately 12,827m2, with costs estimated at Rs 127 million. In August 1997, the winner of the design competition was appointed the Consulting Architect and he was to charge a fee of 6 per cent of the construction cost.

3. The Consulting Architect discussed major requirements directly with the client ministry and brought major modifications to the design without informing the Ministry of Public Infrastructure.

4. In September 1997, the client ministry requested changes to be made to the proposed building to accommodate parking for 100 cars and making provision for three additional floors for future expansion.

5. In February 1999, confirmed that funds of Rs 285 million were available for the construction of the building that would comprise of three levels of approx. 13,460 m2 and provision of three additional floors.

6. In June 1999, the client proposed further modifications, semi-basement to be full basement and finished to be upgraded. The costs were estimated at Rs 326 million.

7. In September 1999, the client requested for the project cost to be curtailed to Rs 175 million. After The Central Tender Board had given its approval, the consultants brought modifications to the design and plan of the buildings and prepared the tender documents.

8. In April 2002, the contract was awarded to XYZ Builders Ltd at a contract price of Rs 161,310,621 and contract had to be completed on 17 January 2004. Soon after, i.e in August 2002, the client ministry again requested major modifications to accommodate two other units on both the first and second floors in place of the administrative block. Further modifications were made to the revised plan in July 2003 and March 2004 to consider the urgent needs of the client.

9. The project was completed and Consulting Architect issued the Practical Completion Certificate in October 2005. All works were completed on 21 August 2006.

10. In the Cost Report dated August 2005, the Quantity Surveyor mentioned the following extra costs related to the project:

a. Loss & expense claim from the contractor of Rs 44 million;
b. Claim of Rs 25 million for running the site beyond practical completion date;
c. Claim of Rs 6 million representing increases in costs of materials and labour;
d. Loss and expense claim from the subcontractor for electrical works of Rs 15 million.
11. On September 2007, the Central Tender these additional payments were approved
a. Consulting Architects - Rs 3,857,230 (inclusive of VAT)
b. Project Manager - Rs 1,739,130 (inclusive of VAT)
c. M&E Consultant - Rs 915,478 (inclusive of VAT)
d. Structural Consultant - Rs 87,000
e. Quantity Surveyor Consultant - Rs 561,000
12. The final cost of the project was much higher than the contractual price of Rs 161,310,621.

Required

(i) List down the audit work you would perform in respect of the above capital project.

(ii) List down 10 (ten) shortcomings that you could bring to the attention of the Accounting Officer of the ministry following the examination of any capital project. You may use the above- mentioned case as a reference.


Related Discussions:- Show the audit work of the given capital project

Describe the detailed audit works, Your firm has recently been appointed au...

Your firm has recently been appointed auditors of the Social Transport Corporation and you are commencing the audit of the wages system. The Corporation has about 2500 employee

#TITLE, WHAT OF COST OF JOURNAL ENTRY?

WHAT OF COST OF JOURNAL ENTRY?

Beneficial ownership or title, Beneficial Ownership or Title In Januar...

Beneficial Ownership or Title In January 1976 the famous case of Aluminium Industries vaassen B V v. Romalpa Aluminium Ltd radically altered the law along with regard to norma

Presentation and disclosure - audit process, Presentation and Disclosure - ...

Presentation and Disclosure - Audit Process Specific presentation involves presentation in accordance along with the suitable IFRS/IAS or International Accounting Standards.

Measures taken by the individual auditor, Measures To Be Taken By the Indiv...

Measures To Be Taken By the Individual Auditor Proper recruitment and training of all staff; Allocating staff to particular audits where they have the appropriate skills;

Calculate the loss suffered by the shareholders, In June 2004, Feltex Carpe...

In June 2004, Feltex Carpets Limited raised NZ $254 million in an initial public offering. Twenty seven months later the company was in receivership, its share price having collaps

Experts as a source of audit evidence, Experts as a source of Audit Evidenc...

Experts as a source of Audit Evidence Mostly the auditor's work on evidence obtained from along within the entity supported through confirmations from third parties will provi

Joint auditing, what is the role of a joint auditor

what is the role of a joint auditor

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd