Show the audit work of the given capital project, Auditing

Assignment Help:

In planning the audit work of the Ministry, the audit staff member collected these details relating to the construction of an office complex.

1. In September 1994, the Ministry requested the assistance of the Ministry of Works, for the preparation of plans and preliminary drawings to ‘set up a building to accommodate its departments' of approximately 6000m2 at an estimated budgeted cost of Rs 50 million.

2. In September 1995, an architectural competition was launched with a view to have the best design and the winner was to be engaged as the Consulting Architect subsequently. The design was prepared on a project area of approximately 12,827m2, with costs estimated at Rs 127 million. In August 1997, the winner of the design competition was appointed the Consulting Architect and he was to charge a fee of 6 per cent of the construction cost.

3. The Consulting Architect discussed major requirements directly with the client ministry and brought major modifications to the design without informing the Ministry of Public Infrastructure.

4. In September 1997, the client ministry requested changes to be made to the proposed building to accommodate parking for 100 cars and making provision for three additional floors for future expansion.

5. In February 1999, confirmed that funds of Rs 285 million were available for the construction of the building that would comprise of three levels of approx. 13,460 m2 and provision of three additional floors.

6. In June 1999, the client proposed further modifications, semi-basement to be full basement and finished to be upgraded. The costs were estimated at Rs 326 million.

7. In September 1999, the client requested for the project cost to be curtailed to Rs 175 million. After The Central Tender Board had given its approval, the consultants brought modifications to the design and plan of the buildings and prepared the tender documents.

8. In April 2002, the contract was awarded to XYZ Builders Ltd at a contract price of Rs 161,310,621 and contract had to be completed on 17 January 2004. Soon after, i.e in August 2002, the client ministry again requested major modifications to accommodate two other units on both the first and second floors in place of the administrative block. Further modifications were made to the revised plan in July 2003 and March 2004 to consider the urgent needs of the client.

9. The project was completed and Consulting Architect issued the Practical Completion Certificate in October 2005. All works were completed on 21 August 2006.

10. In the Cost Report dated August 2005, the Quantity Surveyor mentioned the following extra costs related to the project:

a. Loss & expense claim from the contractor of Rs 44 million;
b. Claim of Rs 25 million for running the site beyond practical completion date;
c. Claim of Rs 6 million representing increases in costs of materials and labour;
d. Loss and expense claim from the subcontractor for electrical works of Rs 15 million.
11. On September 2007, the Central Tender these additional payments were approved
a. Consulting Architects - Rs 3,857,230 (inclusive of VAT)
b. Project Manager - Rs 1,739,130 (inclusive of VAT)
c. M&E Consultant - Rs 915,478 (inclusive of VAT)
d. Structural Consultant - Rs 87,000
e. Quantity Surveyor Consultant - Rs 561,000
12. The final cost of the project was much higher than the contractual price of Rs 161,310,621.

Required

(i) List down the audit work you would perform in respect of the above capital project.

(ii) List down 10 (ten) shortcomings that you could bring to the attention of the Accounting Officer of the ministry following the examination of any capital project. You may use the above- mentioned case as a reference.


Related Discussions:- Show the audit work of the given capital project

What method would you use to test an individual account bal., You are audit...

You are auditing the accounts receivable balance of a cable television provider. Individual accounts receivables tend to be similar in amount to each other and cover one or two mon

INTANGIBLE ASSET, problems associated with intangible asset audit

problems associated with intangible asset audit

Specialized audit situations, Specialized Audit Situations Companies c...

Specialized Audit Situations Companies carry on thousands of different types of trade, business or professional activities.  It is not possible in a manual on general auditing

Information in the fixed assets register, Information in the Fixed Assets R...

Information in the Fixed Assets Register The register can obtain the following information: i. Fixed asset number. ii. The cost and the date of purchase. iii. Descrip

Ownership and existence - verification procedures, Ownership and Existence ...

Ownership and Existence - Verification Procedures Establishment of title and beneficial ownership of investments is not convincingly possible. Conversely, evidence is obtainab

Existence - audit process, Existence - Audit Process In the case of ta...

Existence - Audit Process In the case of tangible assets existence is confirmed through the auditor visually, considering the asset examining and concerned its condition.  Thi

Auditing, State the FIVE threats contained within Auditor''s Code of Ethics...

State the FIVE threats contained within Auditor''s Code of Ethics and Conduct and for each threat list ONE example of a circumstance that may create the threat.

Profesional ethic, Ask quesThe following situations involve a possible viol...

Ask quesThe following situations involve a possible violation of the MIA ByLaws (on professional ethics, conduct and practice). For each situation, (1) decide whether or not the Co

Steps in critical thinking principle, Step 1: Determine learning objective...

Step 1: Determine learning objectives. Considering the importance of a course, its placement in a program of study, and its role in providing a base of knowledge to be built upon

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd