Show the audit work of the given capital project, Auditing

Assignment Help:

In planning the audit work of the Ministry, the audit staff member collected these details relating to the construction of an office complex.

1. In September 1994, the Ministry requested the assistance of the Ministry of Works, for the preparation of plans and preliminary drawings to ‘set up a building to accommodate its departments' of approximately 6000m2 at an estimated budgeted cost of Rs 50 million.

2. In September 1995, an architectural competition was launched with a view to have the best design and the winner was to be engaged as the Consulting Architect subsequently. The design was prepared on a project area of approximately 12,827m2, with costs estimated at Rs 127 million. In August 1997, the winner of the design competition was appointed the Consulting Architect and he was to charge a fee of 6 per cent of the construction cost.

3. The Consulting Architect discussed major requirements directly with the client ministry and brought major modifications to the design without informing the Ministry of Public Infrastructure.

4. In September 1997, the client ministry requested changes to be made to the proposed building to accommodate parking for 100 cars and making provision for three additional floors for future expansion.

5. In February 1999, confirmed that funds of Rs 285 million were available for the construction of the building that would comprise of three levels of approx. 13,460 m2 and provision of three additional floors.

6. In June 1999, the client proposed further modifications, semi-basement to be full basement and finished to be upgraded. The costs were estimated at Rs 326 million.

7. In September 1999, the client requested for the project cost to be curtailed to Rs 175 million. After The Central Tender Board had given its approval, the consultants brought modifications to the design and plan of the buildings and prepared the tender documents.

8. In April 2002, the contract was awarded to XYZ Builders Ltd at a contract price of Rs 161,310,621 and contract had to be completed on 17 January 2004. Soon after, i.e in August 2002, the client ministry again requested major modifications to accommodate two other units on both the first and second floors in place of the administrative block. Further modifications were made to the revised plan in July 2003 and March 2004 to consider the urgent needs of the client.

9. The project was completed and Consulting Architect issued the Practical Completion Certificate in October 2005. All works were completed on 21 August 2006.

10. In the Cost Report dated August 2005, the Quantity Surveyor mentioned the following extra costs related to the project:

a. Loss & expense claim from the contractor of Rs 44 million;
b. Claim of Rs 25 million for running the site beyond practical completion date;
c. Claim of Rs 6 million representing increases in costs of materials and labour;
d. Loss and expense claim from the subcontractor for electrical works of Rs 15 million.
11. On September 2007, the Central Tender these additional payments were approved
a. Consulting Architects - Rs 3,857,230 (inclusive of VAT)
b. Project Manager - Rs 1,739,130 (inclusive of VAT)
c. M&E Consultant - Rs 915,478 (inclusive of VAT)
d. Structural Consultant - Rs 87,000
e. Quantity Surveyor Consultant - Rs 561,000
12. The final cost of the project was much higher than the contractual price of Rs 161,310,621.

Required

(i) List down the audit work you would perform in respect of the above capital project.

(ii) List down 10 (ten) shortcomings that you could bring to the attention of the Accounting Officer of the ministry following the examination of any capital project. You may use the above- mentioned case as a reference.


Related Discussions:- Show the audit work of the given capital project

Amortization and impairment, Amortization and Impairment Amortization...

Amortization and Impairment Amortization - capitalized costs would be amortized to reflect the pattern whether the related economic benefits are identified. Once commercial

Audit Procedures - Intangible Assets, Audit Procedures - Intangible Assets ...

Audit Procedures - Intangible Assets The auditor's process as far as goodwill is relating would involve as: a) Vouching for details as per the buy agreement of the values

Summary of ias 2, Summary of IAS 2 Inventories are measured at the low...

Summary of IAS 2 Inventories are measured at the lower of cost and net realizable value. Entire realizable price is the calculated selling price in the regular course of busin

Standardization of working papers - auditing, Standardization of Working Pa...

Standardization of Working Papers - Auditing The ICPAK guideline states that the needs of standardized working papers may improve the effectiveness along with that they are re

A test for unrecorded liabilities, should your test for unrecorded liabilit...

should your test for unrecorded liabilities be affected by the fact that a letter is obtained in which a responsible management official certifies that to the test of his knowledge

Building societies - specialized audit situation, Building Societies - Spec...

Building Societies - Specialized Audit Situation Building Societies are organisations that exist to offer a savings and investment intermediate to the public and to lend to pe

Necessity of accountant, Necessity of Accountant The accountant is no...

Necessity of Accountant The accountant is not necessary To expand his enquiries beyond the information enclosed in the relevant documents as supplemented through such e

Completeness of liabilities, Completeness of Liabilities In distortion...

Completeness of Liabilities In distortion, the directors tend to involve non-existent assets or keep out liabilities. Hence whereas along with assets we are especially concern

ACL PROGRAME, I have some questions in ACL PROGRAME . IF YOU CAN HELP ME

I have some questions in ACL PROGRAME . IF YOU CAN HELP ME

Companies modes of operation, Companies Modes of Operation Some compani...

Companies Modes of Operation Some companies (especially small ones) operate without any overtly expressed plan and simply carry out the business as always, responding to market

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd