Rolling - binder, Civil Engineering

Assignment Help:

Rolling - Binder:

The layer thickness is 40-50 mm. Rolling is done in three stages :

Initial Rolling

By 80-100 kN smooth wheeled roller.

Intermediate Rolling

By 80-100 kN vibratory roller or by pneumatic tyred roller.

Final Rolling

60-80 kN tandem roller.

Rolling is done till the laboratory density is achieved.


Related Discussions:- Rolling - binder

Air traffic control, Air Traffic Control: Importance of Air Traffic...

Air Traffic Control: Importance of Air Traffic Control Air Traffic Control is a system by which routes for flying aircraft are defined, flight rules are framed, and f

Disparities between regular precast and pipe jacking, Question What are...

Question What are main disparities in design between regular precast concrete pipes and pipes used for pipe jacking ? Answer For pipes used for pipe jacking, they h

Structural dynamics, A machine of 850 kg mass is acted upon by an external ...

A machine of 850 kg mass is acted upon by an external force of 1355 N at a frequency of 650 rpm. To reduce the effects of vibrations on the supporting structure, isolators having s

Dynamic force transfer test of shock transmission unit, Define Dynamic Forc...

Define Dynamic Force Transfer Test of Shock Transmission Unit? This test mainly prove the lock up capability of the device. The STU shall be loaded in tension from zero to the

Explain the equalization basins - hydraulic system, Equalization Basins - H...

Equalization Basins - Hydraulic System For influent flow to publicly owned treatment works (POTWs), flow rates may be excessive for short or long durations, especially in combi

Explain the term - moderate prestressing, Explain the term - Moderate Prest...

Explain the term - Moderate Prestressing In this form of prestressing, no limit is imposed on  the magnitude of tensile stresses which may be produced in a concrete member unde

State the natural frequency of a machine foundation, State the natural freq...

State the natural frequency of a machine foundation of base area 2m × 2m and weight 150 kN, suppose that the soil mass participating in the vibration is 20% of the weight of founda

Pre-tensioned concrete elements, Pre-tensioned concrete elements It is ...

Pre-tensioned concrete elements It is the act of transferring the stress in prestressing tendons to the concrete member. In the case of pre-tensioned concrete elements, this st

Explain the term - loss of prestress, Explain the term - Loss of Prestress ...

Explain the term - Loss of Prestress At the transfer stage, tendons produce compressive stresses in concrete. Sooner or later, the magnitude of  these stresses experiences a re

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd